The District of Columbia Armory Board v. D. G. Volkert, T/a Ewin Engineering Associates, and Reynolds Metals Company

402 F.2d 215, 131 U.S. App. D.C. 74, 1968 U.S. App. LEXIS 5617
CourtCourt of Appeals for the D.C. Circuit
DecidedSeptember 6, 1968
Docket21283_1
StatusPublished
Cited by9 cases

This text of 402 F.2d 215 (The District of Columbia Armory Board v. D. G. Volkert, T/a Ewin Engineering Associates, and Reynolds Metals Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The District of Columbia Armory Board v. D. G. Volkert, T/a Ewin Engineering Associates, and Reynolds Metals Company, 402 F.2d 215, 131 U.S. App. D.C. 74, 1968 U.S. App. LEXIS 5617 (D.C. Cir. 1968).

Opinion

McGOWAN, Circuit Judge:

Appellants, the District of Columbia Armory Board and its individual members, complain of a District Court order granting summary judgment against them in their suit seeking damages for cracks which appeared in the D. C. Stadium. The judgment appealed from was founded upon assertions by appellees that the suit was untimely under the applicable statute of limitations. For the reasons hereinafter appearing, we find no error in the District Court’s disposition of the matter.

I

The action was begun in the District Court on March 14, 1966. It alleged that the cause of the cracks was the use of aluminum electrical conduit in conjunction with calcium chloride in the concrete mix, thereby causing electric current to escape with consequent damage to the concrete structure. Appellee Reynolds Metals Company [“Reynolds”] was the manufacturer and supplier of the aluminum conduit to General Electric Company, which was the immediate vendor of the electrical subcontractor. Appellee D. G. Volkert, t/a Ewin Engineering Associates [“Ewin”], contracted with the Board to supply architectural-engineering services in the preparation of plans and specifications and in supervising construction under them. Reynolds had no direct contractual relations with the Board, and is sued in two counts of negligence and one count of breach of implied warranty. Ewin is sued in one count of negligence, one count of breach of implied warranty, and one count of breach of a contract under seal.

The essence of appellants’ complaint is that appellees either knew, or should have known, that the interaction of aluminum conduit and calcium chloride would inevitably result in damage to the structure, and that Ewin should not have prepared plans and specifications contemplating the use of both, nor should Reynolds have supplied aluminum conduit for such use.

Ewin and Reynolds each moved for summary judgment, under Rule 56, Fed. R.Civ.P., and Local Rule 9(h) of the District Court, relying upon 12 D.C.Code § 301. 1 They asserted that, because of *217 information elicited in pretrial discovery, there were no material issues of fact to be tried with respect to the Board’s knowledge of the damage and its cause more than three years prior to the filing of suit. The principal item upon which appellees rely is the deposition taken of Mr. James A. Blaser, Director of the Department of Buildings and Grounds of the District of Columbia, who served as the Board’s Contracting Officer for the construction of the D. C. Stadium.

That construction began in July, 1960, and was completed in April, 1962. Mr. Blaser, a qualified civil engineer, testified that the cracking first came to his attention in “late January or early February of ’62.” He related that, because similar problems had developed in the construction of other buildings in the Washington Metropolitan Area, a study group had been set up by a number of governmental agencies to try to ascertain the cause, apparently under the primary leadership of the Federal Bureau of Standards. Mr. Blaser’s D. C. Department of Buildings and Grounds had a representative in the study group in the person of Mr. Richard Crutchfield, Chief of Design and Engineering for the D. C. Department of Buildings and Grounds.

By “late February of ’62,” according to Mr. Blaser, the group had concluded its effort, and, to his knowledge, it had decided that the cracking was due to the interaction of aluminum conduit and calcium chloride. Mr. Blaser said that, in response to this conclusion, “[W]e immediately stopped any usage of aluminum conduit imbedded in concrete.” 2 This reference is presumably to other buildings than the Stadium because Mr. Blaser went on to say that all of the conduit installation at the Stadium had been completed by mid-February, 1962. He formally accepted the Stadium on behalf of the Board in April, 1962. The deposition includes this colloquy upon the Board’s state of knowledge as of February, 1962:

Q. Mr. Blaser, it is a fair summary of your information that by mid-February, approximately mid-February 1962, it was common knowledge to the people working on the stadium project that there was a problem of concrete cracking and the probable cause of it was aluminum conduit in the presence of steel reinforcing rods to *218 which additives of calcium chloride had been added?
A. I would say, the end of February would be better than the middle of February.
Q. There isn’t any doubt in. your mind about the year involved, is there?
A. No, sir.

Appellants filed a pleading in opposition to the motions for summary judgment. It does not challenge Mr. Blaser’s deposition but asserts instead that it was not until July 1, 1963, that any “serious disturbance was reported,” and that it thereafter engaged an engineering firm to look into the matter. This firm reported to the Board on July 20, 1964, that the damage was caused by the juxtaposition of aluminum conduit and calcium chloride. As noted above, suit was not brought until nearly two years later. The only issue of material fact tendered by the Board in its opposition to summary judgment was phrased by it in these terms:

Therefore, an issue of fact of grave materiality is in issue, to wit, at what point in time were the plaintiffs aware, with sufficient, scientific and technical justification, to aver and establish the ground upon which suit could be brought against these defendants.

II

Appellants argue to us that they were entitled to refrain from suit until they had explored the matter in their own way by means of retaining an independent expert, and that they cannot be charged with knowledge of the accrual of a cause of action until this more leisurely process had been completed. They do not contest before us that Blaser was their responsible representative, and that whatever he knew is imputable to them. This last is a concession which, it seems to us, they had no choice but to make. In the light of it, we think there was no material issue of fact to be tried on the issue of when the Board must be said to have known of the damage to the Stadium and of the factors asserted in the complaint to have been its cause. 3 On the record before us, and to the extent that the applicable period of limitations is three years, the District Court cannot be said to have erred in granting summary judgment.

As to Reynolds, not even appellants contend that a limiting period of longer than three years applies; and the same is true of the negligence count against Ewin. As to the other two counts against Ewin, appellants, not in their opposition papers but somewhat belatedly in oral argument, suggested to the District Court that a longer period applied because Ewin’s contract with the Board was under seal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Simmons v. District of Columbia Armory Board
656 A.2d 1155 (District of Columbia Court of Appeals, 1995)
National Railroad Passenger Corp. v. Notter
677 F. Supp. 1 (District of Columbia, 1987)
L'Enfant Plaza East, Inc. v. John McShain, Inc.
359 A.2d 5 (District of Columbia Court of Appeals, 1976)
Hartford Insurance Group v. Statewide Appliances, Inc.
484 P.2d 569 (Nevada Supreme Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
402 F.2d 215, 131 U.S. App. D.C. 74, 1968 U.S. App. LEXIS 5617, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-district-of-columbia-armory-board-v-d-g-volkert-ta-ewin-cadc-1968.