the Daneshjou Company, Inc. v. W. Lee Brown & Sons, Inc.

CourtCourt of Appeals of Texas
DecidedAugust 8, 2008
Docket03-04-00740-CV
StatusPublished

This text of the Daneshjou Company, Inc. v. W. Lee Brown & Sons, Inc. (the Daneshjou Company, Inc. v. W. Lee Brown & Sons, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
the Daneshjou Company, Inc. v. W. Lee Brown & Sons, Inc., (Tex. Ct. App. 2008).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-04-00730-CV NO. 03-04-00734-CV NO. 03-04-00735-CV NO. 03-04-00737-CV NO. 03-04-00738-CV NO. 03-04-00739-CV NO. 03-04-00740-CV

The Daneshjou Company, Inc., Appellant

v.

Joe Goergen & CNA Construction, Inc. & Modern Design and Construction, Inc. & Loredo Truss Company, Inc. & Loma Excavation, Inc. & G. P. Equipment Company & W. Lee Brown & Sons, Inc., Appellees

FROM THE DISTRICT COURT OF TRAVIS COUNTY, 126TH JUDICIAL DISTRICT NOS. GN403647, GN403032, GN402512, GN402481, GN403033, GN402513 & GN402685, HONORABLE PAUL DAVIS, JUDGE PRESIDING

MEMORANDUM OPINION

This appeal involves claims by a general contractor against its subcontractors. The

Daneshjou Company, Inc. (“DCI”) was retained to build a house for Sandra Bullock. DCI hired several subcontractors for the project, including appellees Joe Goergen, CNA Construction, Inc.,

Modern Design and Construction, Inc., Loredo Truss Company, Inc., Loma Excavation, Inc.,

G. P. Equipment Company, and W. Lee Brown & Sons, Inc. DCI and Bullock (together with

John Bullock) filed suits against each other, and DCI filed third-party claims against its

subcontractors to recover direct damages and for contribution and indemnity in the event it had to

pay damages to the Bullocks. The appellee subcontractors filed motions for summary judgment

and/or to dismiss. The trial court granted the motions in part or in whole, eventually disposing of

all claims between DCI and these subcontractors. The trial court then severed the claims involving

these subcontractors from the other claims in the case, and proceeded to trial on the remaining claims

(“the Bullock trial”). DCI appeals the decisions in the cases involving these subcontractors.

DCI argues (1) that genuine issues of material fact exist, precluding

summary judgment; (2) that severing the claims against the subcontractors while admitting evidence

of their allegedly deficient work prejudiced DCI at the Bullock trial; and (3) that DCI should have

been allowed to pursue its claims for contribution and indemnity against the subcontractors after the

Bullock trial.

We find no reversible error in the trial court rulings challenged by DCI on appeal.

The court did not err by dismissing all of DCI’s third-party claims against G. P. Equipment for

failure to serve citation timely. DCI’s brief lacks argument or citation to facts or authorities showing

error in the disposition of its direct claims against CNA and Modern. The record supports the

summary judgments that DCI take nothing on its negligence, DTPA, contract, and warranty claims

against Goergen, Loredo, Loma, and Brown. Further, the district court did not err by dismissing all

2 of DCI’s claims for contribution and indemnity from appellees because (1) any contribution claims

DCI had against any of its subcontractors for tort liabilities were released when DCI settled with the

Bullocks after the Bullock trial; and (2) DCI’s contractual indemnity claim against the subcontractors

is unenforceable. Finally, no error in these causes can be predicated on events occurring in or around

the Bullock trial after these causes were severed from the Bullock case. Accordingly, we affirm the

district court’s orders and judgments.

Factual and Procedural Background

DCI sued Sandra Bullock and John Bullock, personally and as trustee of

Vito Pietanza, trustee of Band-Aid Trust, for breach of contract and tortious interference with

employment and business relationships, alleging that the Bullocks delayed the progress of the

construction of their house by DCI. The Bullocks counterclaimed for breach of contract,

statutory/real estate fraud, fraudulent inducement, common-law fraud, and violations of the DTPA

and the Racketeer Influenced Corrupt Organizations Act (“RICO”).

DCI then filed third-party claims against its subcontractors, alleging that their work

on the house was deficient. Several subcontractors filed motions seeking dismissal or summary

judgment, among them:

• G. P. Equipment filed a motion to dismiss arguing that it had not been timely served with citation by DCI;

• Loredo filed no-evidence and traditional motions for summary judgment contending that the limitations period had expired on DCI’s claims, that the DTPA was inapplicable, that it did not make any express warranties, that DCI’s contractual indemnity claims were unenforceable, and that there was no evidence that its truss system was a cause in fact of any damage to the Bullocks; and

3 • Goergen, CNA, Modern, Loma, and Brown filed no-evidence motions for summary judgment and motions to dismiss asserting that DCI could not maintain its third-party action against them because DCI’s claims were meritless, these subcontractors had settled Bullock’s claims against them, and DCI’s contractual indemnity claims against them were unenforceable.

Before the claims between DCI and the Bullocks were submitted to the jury, the trial court disposed

of all claims involving the subcontractors by signing orders granting their motions for dismissal

and/or summary judgment. The court then severed the claims involving these subcontractors from

the Bullock case into individual suits, making the orders in the severed cases final. DCI appealed.

After a jury delivered a verdict on the claims between DCI and the Bullocks,1 DCI and the Bullocks

settled all claims between them.

Discussion

DCI contends that the trial court erred by granting summary judgment in favor of

various of the subcontractors, dismissing its other claims against various subcontractors, severing

its claims against the subcontractors before trial while admitting evidence of their allegedly deficient

work at the Bullock trial, and preventing DCI from pursuing its claims for contribution

and indemnity against the subcontractors after the Bullock trial. However, DCI’s claims in

1 After all the claims involving the appellees in these causes had been severed from the Bullock case, the jury at the Bullock trial awarded the Bullocks $4,492,875 in actual damages, $560,850 in punitive damages, and attorneys’ fees against DCI. The jury also awarded $841,275 in punitive damages against DCI’s owner, M.B. “Benny” Daneshjou, individually.

4 these various appeals fail because (1) they are barred by limitations, (2) they are inadequately briefed,

or (3) they lack merit.

I. Claims against G. P. Equipment Co., No. 03-04-00739-CV

DCI contends that the trial court erred by enforcing the deadline for service of citation

set in the Amended Docket Control Order when dismissing DCI’s claims against G. P. Equipment.

DCI first named G. P. Equipment as a third-party defendant in its Fifth Amended Third-Party

Petition filed on September 26, 2003, more than two years after DCI filed the underlying cause.

On November 23, 2003,2 the state district court entered an Amended Scheduling Order stating that

parties could be joined in this suit only if they were served by November 30, 2003. G. P. Equipment

was served on December 2, 2003. G. P. Equipment moved to dismiss DCI’s claims against it

because it was not served by the deadline set in the trial court’s Amended Docket Control Order.

The trial court granted the motion to dismiss.

Trial courts have wide discretion in managing their dockets, and appellate courts will

not interfere with the exercise of that discretion absent a showing of clear abuse. Clanton

v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Landis v. North American Co.
299 U.S. 248 (Supreme Court, 1936)
Storage & Processors, Inc. v. Reyes
134 S.W.3d 190 (Texas Supreme Court, 2004)
Western Investments, Inc. v. Urena
162 S.W.3d 547 (Texas Supreme Court, 2005)
Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
Cooper Tire & Rubber Co. v. Mendez
204 S.W.3d 797 (Texas Supreme Court, 2006)
MacK Trucks, Inc. v. Tamez
206 S.W.3d 572 (Texas Supreme Court, 2006)
Mathis v. Restoration Builders, Inc.
231 S.W.3d 47 (Court of Appeals of Texas, 2007)
Fisk Electric Co. v. Constructors & Associates, Inc.
888 S.W.2d 813 (Texas Supreme Court, 1994)
Filter Fab, Inc. v. Delauder
2 S.W.3d 614 (Court of Appeals of Texas, 1999)
Clanton v. Clark
639 S.W.2d 929 (Texas Supreme Court, 1982)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
G-W-L, Inc. v. Robichaux
643 S.W.2d 392 (Texas Supreme Court, 1982)
Hargis v. RADIO CORP. OF AMER., ELECTRONIC COMPONENTS
539 S.W.2d 230 (Court of Appeals of Texas, 1976)
Melody Home Manufacturing Co. v. Barnes
741 S.W.2d 349 (Texas Supreme Court, 1987)
Miller v. Spencer
732 S.W.2d 758 (Court of Appeals of Texas, 1987)
Marathon Oil Co. v. Sterner
632 S.W.2d 571 (Texas Supreme Court, 1982)
G.R.A.V.I.T.Y. Enterprises, Inc. v. Reece Supply Co.
177 S.W.3d 537 (Court of Appeals of Texas, 2005)
Mobil Chemical Company v. Bell
517 S.W.2d 245 (Texas Supreme Court, 1974)
Provident Life & Accident Insurance Co. v. Knott
128 S.W.3d 211 (Texas Supreme Court, 2003)
Todd v. Perry Homes
156 S.W.3d 919 (Court of Appeals of Texas, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
the Daneshjou Company, Inc. v. W. Lee Brown & Sons, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-daneshjou-company-inc-v-w-lee-brown-sons-inc-texapp-2008.