G.R.A.V.I.T.Y. Enterprises, Inc. v. Reece Supply Co.

177 S.W.3d 537, 2005 WL 1870668
CourtCourt of Appeals of Texas
DecidedDecember 13, 2005
Docket05-04-00637-CV
StatusPublished
Cited by98 cases

This text of 177 S.W.3d 537 (G.R.A.V.I.T.Y. Enterprises, Inc. v. Reece Supply Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G.R.A.V.I.T.Y. Enterprises, Inc. v. Reece Supply Co., 177 S.W.3d 537, 2005 WL 1870668 (Tex. Ct. App. 2005).

Opinion

OPINION

Opinion by

Justice FITZGERALD.

G.R.A.V.I.T.Y. Enterprises, Inc. (Gravity) appeals the judgment for $217,142.50 for attorney’s fees rendered against it in favor of Reece Supply Co. in this breach of contract action: Gravity brings nine issues asserting the trial court erred in rendering a take-nothing judgment on its claims against Reece and in awarding Reece its attorney’s fees. We conclude the trial court erred in awarding Reece attorney’s *541 fees, render judgment that Reece take nothing against Gravity, and otherwise affirm the trial court’s judgment.

BACKGROUND

Gravity is a commercial sign manufacturer, and Reece is a supplier to sign manufacturers. In 1997, Gravity received an order for about 2700 neon signs to advertise the customer’s products. Most of these signs needed to have adjustable brightness, that is, be “dimmable,” through a knob on the sign’s transformer. Gravity required the transformers not cost more than $40 each. In October 1997, Gravity contacted Reece about obtaining the transformers, and Reece contacted Lighting Components.

Tom Hull, the president of Lighting Components, went to Gravity’s manufacturing plant, saw the signs, and spoke with Gravity’s employees. Hull explained to Reece and Gravity that Lighting Components did not make a dimmable transformer, but given the size of the order, it could design one based on its nondimmable transformer. According to Gravity, the representation was made that Lighting Components had previously manufactured the dimmable transformer and so would not have to design a new one. Hull determined Lighting Components could sell the transformers to Reece for about $32, and Reece agreed to sell them to Gravity for $36.69, well within Gravity’s $40 price break.

Due to its history with Gravity, Reece required Gravity obtain a letter of guaranty from a bank securing payment for the transformers. When Gravity obtained the letter of guaranty, Reece placed the order for the dimmable transformers with Lighting Components.

Gravity received a shipment of 50 of the dimmable transformers in March 1998 and another shipment of 2200 dimmable transformers in May 1998. In March, when it hooked up ten of the transformers to the neon tubing for the signs, six of the transformers shut down, and four of them ran hot. Testimony about how hot the transformers were varied from “a little warm” to hot enough to burn a person touching them. Gravity contacted Reece, who contacted Lighting Components. Hull explained that Lighting Components’ transformers ran warmer than other manufacturers’ transformers because they were designed to dissipate heat into the surrounding air through their aluminum cases. This heat-dissipation feature protected the internal components of the transformers and allowed Lighting Components to give a longer warranty on the transformers.

In May 1998, after the delivery of the 2200 transformers, various Reece employees visited Gravity’s facility to work on the problem of the transformers shutting down. According to Gravity’s witnesses, none of Reece’s employees were able to solve the problem. According to Reece’s witnesses, Dan Blair, Reece’s sales manager with over twenty years’ experience in signs and neon signs, went to Gravity’s plant and examined one of the signs. Blair testified the transformer worked when the “lid” was open but shut down when it was closed. Blair determined the problem was that the GTO cable, a high-voltage cable connecting the transformer to the neon tubing, was touching the neon tubing and the transformer when the lid was closed but was pulled free of them when the lid was open. The touching of the GTO cable to the neon tubing and the transformer caused the transformer to overload and shut down. Blair recommended putting sleeving on the GTO cable and using tube supports to keep the GTO cable away from the neon tubing and transformer. Blair used them on one of *542 the signs, and when the lid was closed, the transformer did not shut down.

The terms of the agreement called for Gravity to pay Reece within seven days after shipping; however, Gravity did not pay Reece. On May 25, 1998, Gravity wrote the bank, informing it that the transformers “are a potential fire hazard” and that it had refused payment.

In 1999, Reece turned over collection of the debt to its attorneys. Gravity declared bankruptcy in November 1999. Reece then demanded payment from the bank under the letter of guaranty, but the bank refused. Reece sued the bank and recovered a summary judgment for the amount owing for the transformers plus interest, costs, and Reece’s attorney’s fees. The defective condition, if any, of the transformers was not litigated. Following exhaustion of appeals, the bank paid the judgment. The bank then debited Gravity’s account for the amount of the judgment plus the bank’s attorney’s fees.

In this suit, Gravity sued Reece for the amount the bank debited its account plus its attorney’s fees, asserting breach of warranty, breach of contract, violation of the Deceptive Trade Practices Act, and fraud. Reece counterclaimed for breach of contract and requested the fees and costs it incurred in defending against Gravity’s suit. The jury found Gravity breached the contract and that Reece was not liable under any of the causes of action. The trial court entered judgment denying all relief sought by Gravity and awarding Reece its attorney’s fees of $217,142.50.

AMENDED PETITION

In its second issue, Gravity asserts the trial court erred in striking its second amended petition filed November 21, 2003, ten days before trial. The trial court must allow the parties to amend their pleadings up to the deadline for amending pleadings. Tex.R. Civ. P. 63. Even after the time for filing amended pleadings has past, the trial court abuses its discretion in denying leave to file an amended pleading unless (1) the party opposing the amendment presents evidence of surprise or prejudice, or (2) the amendment asserts a new cause of action or defense, and thus is prejudicial on its face, and the opposing party objects to the amendment. State Bar v. Kilpatrick, 874 S.W.2d 656, 658 (Tex.1994); Greenhalgh v. Serv. Lloyds Ins. Co., 787 S.W.2d 938, 939 (Tex.1990); Graham v. Adesa Tex., Inc., 145 S.W.3d 769, 775 (Tex.App.-Dallas 2004, pet. filed). In these two situations, the decision to allow or deny the amendment rests with the sound discretion of the trial court, and the trial court’s decision will not be overturned unless it constitutes a clear abuse of discretion. Kilpatrick, 874 S.W.2d at 658. In this case, Gravity does not dispute that its second amended petition asserted several new defenses and thus was prejudicial on its face; instead, Gravity argues it timely filed its second amended petition.

The deadline for filing amended pleadings was set by the trial court’s scheduling order. The trial court’s enforcement of a scheduling order is reviewed for abuse of discretion. See Wil-Roye Inv. Co. II v. Washington Mut. Bank, FA, 142 S.W.3d 393, 401 (Tex.App.-El Paso 2004, no pet.); see also Clanton v. Clark, 639 S.W.2d 929 (Tex.1982) (trial court has discretion to manage its docket).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sharlene Baker v. Ferrier Builders, Inc.
Court of Appeals of Texas, 2024
Michael Beal v. Pruvit Ventures, Inc.
Court of Appeals of Texas, 2023
Joe D. Boucher v. Mark A. Thacker
Court of Appeals of Texas, 2020
Kubbernus v. ECAL Partners, Ltd.
574 S.W.3d 444 (Court of Appeals of Texas, 2018)
Robert H. Holmes v. GMAC, Inc.
458 S.W.3d 85 (Court of Appeals of Texas, 2014)
Jerry Mullendore v. Kurt Michael Muehlstein
441 S.W.3d 426 (Court of Appeals of Texas, 2014)
Celmer, Elizabeth W. v. McGarry, Charles
412 S.W.3d 691 (Court of Appeals of Texas, 2013)
Versata Software, Inc. v. Internet Brands, Inc.
902 F. Supp. 2d 841 (E.D. Texas, 2012)
Imagine Automotive Group, Inc. v. Boardwalk Motor Cars, LLC
356 S.W.3d 716 (Court of Appeals of Texas, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
177 S.W.3d 537, 2005 WL 1870668, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gravity-enterprises-inc-v-reece-supply-co-texapp-2005.