The Construction and General Laborers’ District Council of Chicago and Vicinity v. Global Builders & Developers Inc.

CourtDistrict Court, N.D. Illinois
DecidedDecember 4, 2025
Docket1:24-cv-09706
StatusUnknown

This text of The Construction and General Laborers’ District Council of Chicago and Vicinity v. Global Builders & Developers Inc. (The Construction and General Laborers’ District Council of Chicago and Vicinity v. Global Builders & Developers Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Construction and General Laborers’ District Council of Chicago and Vicinity v. Global Builders & Developers Inc., (N.D. Ill. 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF IL LINOIS EASTERN DIVISION

THE CONSTRUCTION AND GENERAL ) LABORERS’ DISTRICT COUNCIL OF ) CHICAGO AND VICINITY, ) ) Case No. 24 C 9706 Plaintiff, ) ) Judge Joan H. Lefkow v. ) ) ) GLOBAL BUILDERS & DEVELOPERS ) INC., ) ) Defendant. )

OPINION AND ORDER The Construction and General Laborers’ District Council of Chicago and Vicinity (the Union) brings this action against Global Builders and Developers Incorporated (GBDI), under § 301 of the Labor Management Relations Act (LMRA), 29 U.S.C. § 185 et seq. The Union asserts that GBDI owes approximately $170,000 in fines—the award decided by the Joint Grievance Committee (Grievance Committee). GBDI argues the award was not final and that the Grievance Committee’s decision was outside the scope of the parties’ agreement. Both parties move for summary judgment. Because the issues raised in the cross-motions are largely the same, this opinion addresses both motions. For the reasons stated below, the Union’s motion (Dkt. 24) is granted, and GBDI’s motion (Dkt. 27) is denied. BACKGROUND1 GBDI is a construction company operating in Chicago, Illinois. Local 6 is a local union affiliated with the Union. On November 10, 2020, a general contractor, Global Builders, Inc.

1 Facts are drawn from those included in parties’ Rule 56 disclosures and that were admitted to by the other party. (General Contractor) entered into an agreement with Gateway Residential Partners, LLC to construct 161 residential apartments at 2050 W. Ogden Ave. in Chicago (the Project). On March 4, 2022, the General Contractor hired GBDI to provide one union laborer for the Project to help with cleanup on the construction site, including vacuuming, mopping, and cleaning windows. On

the same day, GBDI signed an agreement with Local 6 (Longform Agreement). The Union has a collective bargaining agreement (CBA) with the Chicago Area Independent Contractors Association, and Paragraph 2 of the Longform Agreement binds GBDI to the Union’s CBA. The CBA provides that “any dispute concerning the interpretation or application of this Agreement between an Employer and the Union shall be adjusted by the particular Employer and Union, in the first instance . . . . In the event that the matter is not settled, the Union may file a written grievance, which shall be submitted to a Joint Grievance Committee.” (Exhibit 2, Dkt. 26 at 44.) The Grievance Committee is composed of an equal number of union and management representatives, each of whom has equal voting power. The Grievance Committee’s resolution of a grievance is “final and binding.” (Exhibit 1, Dkt. 26 at 12.) Article 11, Paragraph 2 of the CBA

states that the “determination of the [Grievance Committee] shall be governed by majority vote” and, if “decided by majority vote, the grievance determination and any relief determined to be appropriate shall be final and binding upon the parties.” (Exhibit 2, Dkt. 26 at 44.) If the Grievance Committee is deadlocked on disposition of the grievance, the matter is referred to arbitration. On July 27, 2022, Local 6 filed Grievance No. 22-44 alleging that GBDI violated Article 2 of the CBA by using non-union labor. Article 2 requires all new employees to join the Union and remain members in good standing as a condition of continued employment. On October 10, 2022, Local 6 filed an additional grievance, No. 22-64, asserting that GBDI violated Article 4 of the CBA by subcontracting to a non-signatory company. Article 4 provides, in part, that the employer signatory agrees it will only contract or subcontract work covered by the CBA to persons, firms, and corporations that are signatories to the CBA. The Grievance Committee conducted a hearing on both grievances on December 14,

2023. At the hearing, GBDI President Carmen Gratace represented GBDI, and Dexter Ziemann, Local 6’s business manager, represented Local 6. Joanna Barrera, the Union’s attorney, also attended. At the hearing, Gratace contended that GBDI did not use non-bargaining unit employees, nor did it subcontract work to entities that did not have a labor contract with the Union. Gratace also asserted that GBDI was merely one subcontractor at the Project and had only been hired to provide one Union laborer for the Project. The Union asserts that Gratace told the Grievance Committee that he would be able to provide documents supporting his position. GBDI disputes this and asserts that Gratace told the Union that it would need to provide documentation showing GBDI was the responsible party.2 After the hearing, the Grievance Committee sent a letter to GBDI informing it that “the

[g]rievances were upheld in their entirety.” (Exhibit F, Dkt. 26 at 255.) The letter instructed GBDI to “(2) pay $334.33 to the Laborers’ Pension and Welfare Funds pursuant to the fringe benefit audit for the time period of March 4, 2022, through November 30, 2022 . . .” and to “(3) provide the Joint Grievance Committee with the following documents by Friday, December 29, 2023: a. the construction contract for final cleaning on the . . . Project; b. the construction contract, including the date [GBDI] turned the Project over for occupancy; and c. the contract signed between [GBDI] and Gateway covering the project.” (Id.)

2 As discussed further below, this is not a material dispute, due to the court’s limited jurisdiction to review the Grievance Committee’s reasoning, decision-making, and remedy. The letter further stated that if the documents listed in Item 3 were not provided to the Grievance Committee by December 29, 2023, GBDI was to pay $115,000 to the Laborers’ Charitable Foundation, in addition to 50 percent liquidated damages, which totaled $57,500. The letter further stated that if, seven days after December 29, 2023, GBDI did not pay the Laborers’

Charitable Foundation $115,000 plus $57,500, GBDI must also pay the Union liquidated damages equal to 10 percent of the monetary award and all court costs and reasonable attorney fees incurred by the party enforcing the award. GBDI paid $334.33 pursuant to the fringe benefit audit. It did not provide the documents listed in Item 3, nor did it pay the amounts the letter called for if the documents were not produced. Instead, on December 29, 2023, GBDI President Gratace sent Barrera a letter insisting that GBDI could not provide the documents in Item 3 because it was not the general contractor on the job. Gratace insisted that the Union, not GBDI, should provide documents to prove its claims. Barrera responded via email the same day, writing that the onus was on GBDI to provide the documents and prove that it did not violate the bargaining agreement. GBDI did not respond

to Barrera, did not provide any documents, did not pay the award, and did not file a lawsuit challenging the validity of the award. Each member of the Grievance Committee has since signed affidavits attesting that they considered the December 14, 2023, award letter to be their final decision. LEGAL STANDARD Summary judgment is appropriate “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). “The law considers a dispute genuine ‘if the evidence is such that a reasonable jury could return a verdict for the nonmoving party.’” Lord v. Beahm, 952 F.3d 902, 903 (7th Cir. 2020) (quoting Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986)). The court “consider[s] all of the evidence in the record in the light most favorable to the non-moving party, and . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Steelworkers v. American Manufacturing Co.
363 U.S. 564 (Supreme Court, 1960)
At&T Technologies, Inc. v. Communications Workers
475 U.S. 643 (Supreme Court, 1986)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Wisconsin Knife Works v. National Metal Crafters
781 F.2d 1280 (Seventh Circuit, 1986)
Teamsters Local No. 579 v. B & M Transit, Inc.
882 F.2d 274 (Seventh Circuit, 1989)
Sullivan v. Gilchrist
87 F.3d 867 (Seventh Circuit, 1996)
Major League Baseball Players Assn. v. Garvey
532 U.S. 504 (Supreme Court, 2001)
Robert Spierer v. Corey Rossman
798 F.3d 502 (Seventh Circuit, 2015)
Janice LaRiviere v. Board Trustees of Southern Ill
926 F.3d 356 (Seventh Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
The Construction and General Laborers’ District Council of Chicago and Vicinity v. Global Builders & Developers Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-construction-and-general-laborers-district-council-of-chicago-and-ilnd-2025.