The City of Demopolis, Alabama v. The United States

334 F.2d 657, 167 Ct. Cl. 94, 1 ERC (BNA) 1051, 1964 U.S. Ct. Cl. LEXIS 118
CourtUnited States Court of Claims
DecidedJuly 17, 1964
Docket470-60
StatusPublished
Cited by4 cases

This text of 334 F.2d 657 (The City of Demopolis, Alabama v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The City of Demopolis, Alabama v. The United States, 334 F.2d 657, 167 Ct. Cl. 94, 1 ERC (BNA) 1051, 1964 U.S. Ct. Cl. LEXIS 118 (cc 1964).

Opinion

WHITAKER, Judge.

Plaintiff is an incorporated municipality situated on a bluff overlooking the Tombigbee River in Alabama. In 1904 it constructed and has since operated a gravity sewage disposal system, consisting of drainage pipes running throughout the city and emptying into the river through three outfalls. Through these outfalls, plaintiff has discharged its raw sewage into the river.

Both parties admit that the river is a navigable stream.

In section 2 of the Rivers and Harbors Act of 1945, 59 Stat. 10, 17, Congress authorized the construction of the De-mopolis Dam and Lock Project. Pursuant to this authority, defendant constructed a dam downstream from the City of Demopolis. The dam, which was completed in 1954, raised the level of the river opposite the city, reduced its rate of flow and created a lake of substantial surface area. The lake’s potential as the basis for recreational use, coupled with the fact that the decreased rate of flow retarded dispersal of plaintiff’s untreated sewage, caused the State of Alabama to object to the continuance of plaintiff’s method of sewage disposal. The State’s Water Improvement Commission has required that plaintiff build a plant for the treatment of its sewage before disgorging it into the river. Plaintiff says that the cost of constructing and operating this facility will be $950,052, for which sum it sues on the ground that its present system has been wrongfully “seized” by defendant.

The rights of a riparian landowner to use a navigable waterway are subject to the paramount right of the Federal Government to improve navigation in it. This right extends to the entire bed of the stream up to ordinary high water mark. To this extent, it has been held many times, that the right of the United States to the bed and flow of a navigable river is superior to that of *659 any other competing interest. The latest decision so holding is United States v. Virginia Electric & Power Co., 365 U.S. 624, 627-628, 81 S.Ct. 784, 787-788, 5 L.Ed.2d 838 (1961), in which the Supreme Court summarized this doctrine and its consequences as follows:

“This navigational servitude— sometimes referred to as a ‘dominant servitude,’ Federal Power Commission v. Niagara Mohawk Power Corp., 347 U.S. 239, 249 [74 S.Ct. 487, 493, 98 L.Ed. 686], or a ‘superior navigation easement,’ United States v. Grand River Dam Authority, 363 U.S. 229, 231 [80 S.Ct. 1134, 1136, 4 L.Ed.2d 1186]—is the privilege to appropriate without compensation which attaches to the exercise of the ‘power of the government to control and regulate navigable waters in the interest of commerce.’ United States v. Commodore Park, 324 U.S. 386, 390 [65 S.Ct. 803, 805, 89 L.Ed. 1017]. The power ‘is a dominant one which can be asserted to the exclusion of any competing or conflicting one.’ United States v. Twin City Power Co., 350 U.S. 222, 224-225 [76 S.Ct. 259, 260-261, 100 L.Ed. 240]; United States v. Willow River Power Co., 324 U.S. 499, 510 [65 S.Ct. 761, 767, 89 L.Ed. 1101]. * * *”

The outlet in the river for plaintiff’s sewage system was much below high water mark, as plaintiff has admitted.

Plaintiff’s claim is not for the physical destruction of its sewage system by the flooding of land above the ordinary high water mark. As plaintiff admits, its sewage system is still capable of operating in the same manner, and with the same efficiency, as it has operated since 1904. The damages that plaintiff claims spring entirely from the altered flow of the Tombigbee River. The construction of the dam causes the waters to flow more slowly, which retards the washing away of the raw sewage, and makes necessary the treatment of the sewage before it can be discharged into the river. But the United States had the unrestricted right to the full use of the flow of the river to the exclusion of any other party, and to change its flow in the improvement of navigation without compensating any riparian owner or user. Plaintiff cannot now complain because defendant has exercised that right. It is not entitled to compensation under the Fifth Amendment, and defendant’s motion is granted as to the first count of its petition.

In the second count of its petition, plaintiff has asserted a statutory cause of action founded upon the Congressional declaration of policy contained in section 1 of the Rivers and Harbors Act of 1945, supra, which reads:

“That in connection with the exercise of jurisdiction over the rivers of the Nation through the construction of works of improvement, for navigation or flood control, as herein authorized, it is hereby declared to be the policy of the Congress to recognize the interests and rights of the States in determining the development of the watersheds within their borders and likewise their interests and rights in water utilization and control, as herein authorized to preserve and protect to the fullest possible extent established and potential uses, for all purposes, of the waters of the Nation’s rivers; to facilitate the consideration of projects on a basis of comprehensive and coordinated development; and to limit the authorization and construction of navigation works to those in which a substantial benefit to navigation will be realized therefrom and which can be operated consistently with appropriate and economic use of the waters of such rivers by other users.” [59 Stat. 10]

Plaintiff argues that this provision gives a cause of action to riparian landowners who have been damaged by the construction of projects which the Act authorizes.

*660 The sole function of this provision was to encourage cooperation between the National Government and the several States in planning and constructing the public works which the Act authorized. It is obvious that it was not intended to give to a riparian user a right of action it did not have before. 1 The position of the State of Alabama has been contrary to that of the plaintiff. Acting through its Water Improvement 'Commission, the State has said that the construction of this dam was beneficial to its interests and that plaintiff must defer to the new uses of which the river is now susceptible. Accordingly, we must hold that plaintiff cannot recover on this count of its petition and that defendant’s motion must be granted as to it.

In its petition and brief plaintiff sought damages only for the loss of use of its sewage disposal system and asked no relief for the flooding of municipal land above the ordinary high water mark of the river. At oral argument, however, plaintiff requested and was granted leave to amend its petition to add a third count, alleging that a strip of land above the high water mark, known as Arch Street, had been “taken” by defendant. Unlike plaintiff’s other claims, this count cannot be disposed of at this stage of the proceedings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mildenberger v. United States
91 Fed. Cl. 217 (Federal Claims, 2010)
Tri-State Materials Corp. v. United States
550 F.2d 1 (Court of Claims, 1977)
Borough of Ford City v. United States
345 F.2d 645 (Third Circuit, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
334 F.2d 657, 167 Ct. Cl. 94, 1 ERC (BNA) 1051, 1964 U.S. Ct. Cl. LEXIS 118, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-city-of-demopolis-alabama-v-the-united-states-cc-1964.