The Borough of Brentwood v. Plavchak Construction

CourtSuperior Court of Pennsylvania
DecidedJuly 26, 2018
Docket872 WDA 2017
StatusUnpublished

This text of The Borough of Brentwood v. Plavchak Construction (The Borough of Brentwood v. Plavchak Construction) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Borough of Brentwood v. Plavchak Construction, (Pa. Ct. App. 2018).

Opinion

J-A09019-18

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

THE BOROUGH OF BRENTWOOD : IN THE SUPERIOR COURT OF : PENNSYLVANIA : v. : : : PLAVCHAK CONSTRUCTION CO., : INC. : : No. 872 WDA 2017 PLAVCHAK CONSTRUCTION CO., : INC. : : v. : : : THE BOROUGH OF BRENTWOOD : AND THE GATEWAY ENGINEERS, : INC. : : : APPEAL OF: THE BOROUGH OF : BRENTWOOD

Appeal from the Order Entered May 17, 2017 In the Court of Common Pleas of Allegheny County Civil Division at No(s): GD 16-016171, No. GD-16-021983

BEFORE: BOWES, J., DUBOW, J., and MURRAY, J.

MEMORANDUM BY DUBOW, J.: FILED JULY 26, 2018

The Borough of Brentwood (“Brentwood”), appeals from the trial court’s

May 17, 2017 Order denying Borough’s Petition to Confirm Arbitration Award.

After careful review, we affirm.

The facts and procedural history, as gleaned from the record, are as

follows. On April 1, 2014, Brentwood entered into a construction contract

(“Contract”) with Plavchak Construction Co., Inc. (“Contractor”) for the J-A09019-18

construction of facilities associated with a football stadium, and based on a

design provided by The Gateway Engineers, Inc. (“Engineer”). The Contract

included deadlines for substantial and final completion, and achieving certain

milestones, and set per diem monetary penalties for failure to meet those

deadlines and milestones.1 The deadline for completion of the project was

September 15, 2014.

The Contract also included a step-by-step dispute resolution procedure,

which included submission of claims to Engineer for a decision. Specifically,

Article 10.05 of the Contract provided that following the submission of a claim

and a response, Engineer must deny, approve, or decline to resolve the claim,

in writing, within 30 days. Engineer’s decision would become final and

binding unless submitted to a mediator within 30 days. See Contract,

4/11/14, at Article 10.05.

With respect to giving notice, the Contract provides that, where written

notice is required, a party will be deemed to have given it validly if the written

notice is: (1) delivered in person to a member of the firm or to an officer of

the corporation for whom the notice is intended; or (2) delivered at or sent by

registered mail. See Contract at Article 17.01.

For reasons that are immaterial to our disposition, Contractor was

unable to complete the project by the completion deadline. By December ____________________________________________

1 Contractor agreed to pay liquidated damages of $5,000/day for failing to meet the substantial completion and final completion deadlines and $750/day for missed milestones.

-2- J-A09019-18

2014, Brentwood had stopped paying Contractor for the completed work. On

December 15, 2014, Brentwood sent Contractor a letter by certified mail

indicating that it was withholding payment, and asserting that Appellee was

responsible for the project delays. In that letter, Brentwood notified

Contractor of its claim for liquidated damages, but did not specify the amount

of damages. Brentwood copied Engineer on this letter.

On January 14, 2015, Borough sent Contractor, by certified mail, a

detailed calculation of the liquidated damages Borough alleged Contractor

owed, totaling $1,281,750. This letter also contained a request for a

settlement meeting. Borough copied Engineer on this letter.

On January 27, 2015, Contractor, through its Attorney Kevin J. Fiore,

sent Brentwood a letter disputing the claim. Contractor copied Engineer on

this letter. That same day, Brentwood sent a letter to Contractor by certified

mail indicating that it planned to withhold an additional $305,111.50 payment

from Contractor.

On February 6, 2015, Brentwood sent another certified letter to

Contractor renewing its request that the parties schedule a settlement

meeting. Brentwood copied Engineer on this letter.

On February 12, 2015, Engineer sent Brentwood a letter addressing

Brentwood’s request for liquidated damages from Contractor. In the letter,

Engineer concluded that Contractor had not substantially completed the

-3- J-A09019-18

project2 and he included a punch-list of items that Contractor needed to

complete. Engineer opined, “since work is still incomplete, we believe the

Borough is entitled to their claim of liquidated damages.” Engineer Letter,

2/12/15, at 1. Engineer did not determine the amount of liquidated damages

due to Brentwood. Gateway sent the letter to Attorney Fiore and Brentwood’s

counsel, but not by certified mail. Engineer did not address or send the letter

to Contractor.

On March 26, 2015, and April 23, 2015, the parties participated in an

unsuccessful settlement meeting and a mediation session, respectively. At

the April 23, 2015 mediation, Brentwood characterized Engineer’s February

12, 2015 letter as an “arbitration award.”

Following the unsuccessful mediation, on August 25, 2016, Contractor

filed a Complaint seeking a declaratory judgment regarding the parties’ rights

relating to liquidated damages and Contractor’s entitlement to payment for

the work it had completed. Brentwood filed Preliminary Objections to

Contractor’s Complaint on November 10, 2016. Brentwood asserted that

Contractor was responsible for liquidated damages related to a delay of more

than one year in completion of the project and that Engineer had already

determined Contractor’s liability in its February 12, 2015 “arbitration award.”

On November 14, 2016, Brentwood filed a Petition to Confirm Arbitration

Award and enter Judgment. The next day, the trial court consolidated

____________________________________________

2 Contractor ultimately completed the project on July 15, 2016.

-4- J-A09019-18

Contractor’s and Brentwood’s actions. The parties conducted limited

discovery, consisting only of the deposition of Brian R. May, Engineer. The

court held argument on the Petition at which it considered only Mr. May’s

deposition transcript and the parties’ arguments. Following the hearing, the

court entered an Order denying Brentwood’s Petition.3 Brentwood timely

appealed. Both Brentwood and the trial court complied with Pa.R.A.P. 1925.

Brentwood raises the following two issues on appeal, which we have

reordered for ease of disposition:

1. Whether the lower court erred as a matter of law in its conclusion that [Contractor] did not receive proper notice of the February 12, 2015 determination, when [Contractor’s] counsel received actual, timely notice[?]

2. Whether the lower court erred as a matter of law in its conclusion that the February 12, 2015 determination issued by [Engineer] did not constitute an enforceable arbitration award although the determination was made pursuant to the dispute resolution process agreed upon by the parties in their April 11, 2014 Contract[?]

Brentwood’s Brief at 5.

In its first issue, Brentwood claims that the trial court erred in finding

that Contractor did not have proper notice of Engineer’s purported February

12, 2015 determination. Id. at 28. Brentwood offers five alternative

arguments in support of this claim.

First, it argues that notice to Contractor was proper because “in-person

delivery, registered mail, or certified mail are not the exclusive means of ____________________________________________

3 As far as this Court is aware, Contractor’s Petition for Declaratory Judgment remains outstanding.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Garcia v. Community Legal Services Corp.
524 A.2d 980 (Supreme Court of Pennsylvania, 1987)
Yeager v. United Natural Gas Co.
176 A.2d 455 (Superior Court of Pennsylvania, 1961)
Ragnar Benson, Inc. v. HEMPFIELD TOWNSHIP MUNICIPAL AUTHORITY
916 A.2d 1183 (Superior Court of Pennsylvania, 2007)
Insurance Adjustment Bureau, Inc. v. Allstate Insurance
905 A.2d 462 (Supreme Court of Pennsylvania, 2006)
Stamerro v. Stamerro
889 A.2d 1251 (Superior Court of Pennsylvania, 2005)
M & T Mortgage Corp. v. Keesler
826 A.2d 877 (Superior Court of Pennsylvania, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
The Borough of Brentwood v. Plavchak Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-borough-of-brentwood-v-plavchak-construction-pasuperct-2018.