The Borough of Brentwood v. Plavchak Construction

Superior Court of Pennsylvania·Decided July 26, 2018·No. 872 WDA 2017·Unpublished

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

THE BOROUGH OF BRENTWOOD : IN THE SUPERIOR COURT OF : PENNSYLVANIA

:

v. :

:

:

PLAVCHAK CONSTRUCTION CO., : INC. :

: No. 872 WDA 2017

PLAVCHAK CONSTRUCTION CO., : INC. :

:

v. :

:

:

THE BOROUGH OF BRENTWOOD : AND THE GATEWAY ENGINEERS, : INC. :

:

:

APPEAL OF: THE BOROUGH OF : BRENTWOOD

Appeal from the Order Entered May 17, 2017 In the Court of Common Pleas of Allegheny County Civil Division at No(s): GD 16-016171,

No. GD-16-021983

BEFORE: BOWES, J., DUBOW, J., and MURRAY, J. MEMORANDUM BY DUBOW, J.: FILED JULY 26, 2018 The Borough of Brentwood (“Brentwood”), appeals from the trial court’s May 17, 2017 Order denying Borough’s Petition to Confirm Arbitration Award. After careful review, we affirm.

The facts and procedural history, as gleaned from the record, are as follows. On April 1, 2014, Brentwood entered into a construction contract (“Contract”) with Plavchak Construction Co., Inc. (“Contractor”) for the

construction of facilities associated with a football stadium, and based on a design provided by The Gateway Engineers, Inc. (“Engineer”). The Contract included deadlines for substantial and final completion, and achieving certain milestones, and set per diem monetary penalties for failure to meet those deadlines and milestones.1 The deadline for completion of the project was September 15, 2014.

The Contract also included a step-by-step dispute resolution procedure, which included submission of claims to Engineer for a decision. Specifically, Article 10.05 of the Contract provided that following the submission of a claim and a response, Engineer must deny, approve, or decline to resolve the claim, in writing, within 30 days. Engineer’s decision would become final and binding unless submitted to a mediator within 30 days. See Contract, 4/11/14, at Article 10.05.

With respect to giving notice, the Contract provides that, where written notice is required, a party will be deemed to have given it validly if the written notice is: (1) delivered in person to a member of the firm or to an officer of the corporation for whom the notice is intended; or (2) delivered at or sent by registered mail. See Contract at Article 17.01.

For reasons that are immaterial to our disposition, Contractor was

unable to complete the project by the completion deadline. By December

1 Contractor agreed to pay liquidated damages of $5,000/day for failing to meet the substantial completion and final completion deadlines and $750/day for missed milestones.

2014, Brentwood had stopped paying Contractor for the completed work. On December 15, 2014, Brentwood sent Contractor a letter by certified mail indicating that it was withholding payment, and asserting that Appellee was responsible for the project delays. In that letter, Brentwood notified Contractor of its claim for liquidated damages, but did not specify the amount of damages. Brentwood copied Engineer on this letter.

On January 14, 2015, Borough sent Contractor, by certified mail, a detailed calculation of the liquidated damages Borough alleged Contractor owed, totaling $1,281,750. This letter also contained a request for a settlement meeting. Borough copied Engineer on this letter.

On January 27, 2015, Contractor, through its Attorney Kevin J. Fiore, sent Brentwood a letter disputing the claim. Contractor copied Engineer on this letter. That same day, Brentwood sent a letter to Contractor by certified mail indicating that it planned to withhold an additional $305,111.50 payment from Contractor.

On February 6, 2015, Brentwood sent another certified letter to Contractor renewing its request that the parties schedule a settlement meeting. Brentwood copied Engineer on this letter.

On February 12, 2015, Engineer sent Brentwood a letter addressing Brentwood’s request for liquidated damages from Contractor. In the letter, Engineer concluded that Contractor had not substantially completed the

project2 and he included a punch-list of items that Contractor needed to complete. Engineer opined, “since work is still incomplete, we believe the Borough is entitled to their claim of liquidated damages.” Engineer Letter, 2/12/15, at 1. Engineer did not determine the amount of liquidated damages due to Brentwood. Gateway sent the letter to Attorney Fiore and Brentwood’s counsel, but not by certified mail. Engineer did not address or send the letter to Contractor.

On March 26, 2015, and April 23, 2015, the parties participated in an unsuccessful settlement meeting and a mediation session, respectively. At the April 23, 2015 mediation, Brentwood characterized Engineer’s February 12, 2015 letter as an “arbitration award.”

Following the unsuccessful mediation, on August 25, 2016, Contractor filed a Complaint seeking a declaratory judgment regarding the parties’ rights relating to liquidated damages and Contractor’s entitlement to payment for the work it had completed. Brentwood filed Preliminary Objections to Contractor’s Complaint on November 10, 2016. Brentwood asserted that Contractor was responsible for liquidated damages related to a delay of more than one year in completion of the project and that Engineer had already determined Contractor’s liability in its February 12, 2015 “arbitration award.”

On November 14, 2016, Brentwood filed a Petition to Confirm Arbitration Award and enter Judgment. The next day, the trial court consolidated

2 Contractor ultimately completed the project on July 15, 2016.

Contractor’s and Brentwood’s actions. The parties conducted limited discovery, consisting only of the deposition of Brian R. May, Engineer. The court held argument on the Petition at which it considered only Mr. May’s deposition transcript and the parties’ arguments. Following the hearing, the court entered an Order denying Brentwood’s Petition.3 Brentwood timely appealed. Both Brentwood and the trial court complied with Pa.R.A.P. 1925.

Brentwood raises the following two issues on appeal, which we have reordered for ease of disposition:

1. Whether the lower court erred as a matter of law in its conclusion that [Contractor] did not receive proper notice of the February 12, 2015 determination, when [Contractor’s]

counsel received actual, timely notice[?]

2. Whether the lower court erred as a matter of law in its conclusion that the February 12, 2015 determination issued by [Engineer] did not constitute an enforceable arbitration award although the determination was made pursuant to the dispute resolution process agreed upon by the parties in their April 11, 2014 Contract[?]

Brentwood’s Brief at 5.

In its first issue, Brentwood claims that the trial court erred in finding that Contractor did not have proper notice of Engineer’s purported February 12, 2015 determination. Id. at 28. Brentwood offers five alternative arguments in support of this claim.

First, it argues that notice to Contractor was proper because “in-person

delivery, registered mail, or certified mail are not the exclusive means of

3 As far as this Court is aware, Contractor’s Petition for Declaratory Judgment remains outstanding.

providing written notice under the contract.” Id. (emphasis in original). Rather, it avers that the parties’ Contract included a non-exhaustive list of methods of service, which, if used, would deem notice as having been validly given, but that the Contract did not require use of one of those enumerated methods. Id. (emphasis added).

Next, Brentwood argues that actual notice to Contractor’s attorney satisfied the parties’ intent that “the information is successfully conveyed to the party who should have notice of the information at issue.” Id. at 30.

Brentwood also argues that notice to Attorney Fiore constituted notice to Contractor because the February 12, 2015 letter fell within the scope of Attorney Fiore’s representation of Contractor. Id. at 33.

Free access — add to your briefcase to read the full text and ask questions with AI

The Borough of Brentwood v. Plavchak Construction, (Pa. Ct. App. 2018).

The Borough of Brentwood v. Plavchak Construction (The Borough of Brentwood v. Plavchak Construction) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Garcia v. Community Legal Services Corp.
524 A.2d 980 (Supreme Court of Pennsylvania, 1987)
Yeager v. United Natural Gas Co.
176 A.2d 455 (Superior Court of Pennsylvania, 1961)
Ragnar Benson, Inc. v. HEMPFIELD TOWNSHIP MUNICIPAL AUTHORITY
916 A.2d 1183 (Superior Court of Pennsylvania, 2007)
Insurance Adjustment Bureau, Inc. v. Allstate Insurance
905 A.2d 462 (Supreme Court of Pennsylvania, 2006)
Stamerro v. Stamerro
889 A.2d 1251 (Superior Court of Pennsylvania, 2005)
M & T Mortgage Corp. v. Keesler
826 A.2d 877 (Superior Court of Pennsylvania, 2003)