The Boldt Company v. Black & Veatch Construction, Inc.

CourtDistrict Court, N.D. Illinois
DecidedMay 12, 2025
Docket1:19-cv-08383
StatusUnknown

This text of The Boldt Company v. Black & Veatch Construction, Inc. (The Boldt Company v. Black & Veatch Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Boldt Company v. Black & Veatch Construction, Inc., (N.D. Ill. 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF ILLINOIS EASTERN DIVISION THE BOLDT COMPANY, ) ) Plaintiff ) and Counter-Defendant, ) ) No. 19-cv-08383 v. ) ) Judge Andrea R. Wood BLACK & VEATCH CONSTRUCTION, ) INC., ) ) Defendant ) and Counter-Plaintiff. )

MEMORANDUM OPINION AND ORDER Defendant and Counter-Plaintiff Black & Veatch Construction, Inc. (“BVCI”) served as the contractor for the construction of a 60-turbine wind farm in Good Hope, Illinois (“Project”). BVCI subcontracted with Plaintiff and Counter-Defendant The Boldt Company (“Boldt”) to offload and erect the Project’s wind turbines. When the Project fell behind schedule, BVCI terminated Boldt for cause. Boldt claimed that BVCI wrongfully blamed it for delaying the Project when BVCI and the Project’s wind-turbine vendor were actually to blame for the Project getting off schedule. Boldt therefore brought this lawsuit, alleging that BVCI breached its subcontract with Boldt when it terminated Boldt from the Project. In turn, BVCI filed a counterclaim against Boldt, also for breach of contract. The Court granted summary judgment in BVCI’s favor as to Boldt’s claim, finding that there was no genuine dispute of material fact that BVCI properly terminated Boldt for cause due to its schedule default. The Court also denied Boldt’s motion for summary judgment as to BVCI’s counterclaim. With Boldt’s liability on BVCI’s counterclaim having been decided, the Court held a jury trial to determine BVCI’s damages. Following a trial lasting approximately three weeks, the jury returned a verdict awarding BVCI nominal damages of $1.00. Now before the Court are BVCI’s motion for a new trial pursuant to Federal Rule of Civil Procedure 59(a) (Dkt. No. 326) and Boldt’s motion to alter or amend judgment pursuant to Rule 59(e) (Dkt. No. 325). For the reasons that follow, both motions are denied. BACKGROUND

On February 8, 2019, BVCI entered into a prime contract under which it agreed to serve as the engineering, procuring, and construction contractor in connection with the Project. To erect the wind turbines, BVCI subcontracted with Boldt. Under the parties’ subcontract (“Subcontract”), Boldt was to offload wind-turbine parts delivered by the wind-turbine vendor and then erect 60 wind turbines in accordance with the specified construction schedule. The Subcontract called for Boldt to complete erection of all 60 wind turbines by November 8, 2019. Boldt began erecting the wind turbines in August 2019. Quickly, Boldt encountered numerous difficulties that delayed its work on the Project. By mid-August, BVCI began raising concerns to Boldt regarding its failure to adhere to the construction schedule. Boldt, however, insisted that the delays were not its fault. Nonetheless, by the beginning of September, Boldt had

yet to fully erect a single wind turbine. Thus, on September 3, 2019, BVCI issued Boldt a notice of default, citing Boldt’s failure to meet its schedule obligations. BVCI issued a second notice of continued default on September 7, 2019, accusing Boldt of rejecting its obligation to cure its schedule default. That led to extended discussions between BVCI and Boldt about getting the Project back on track. Beginning on September 11, 2019, BVCI took over Boldt’s offloading responsibilities to allow Boldt to focus solely on erection work. Then, on September 20, 2019, BVCI reduced Boldt’s scope of erection work to 40 turbines and took over for Boldt as to the other 20 turbines. Those efforts were unsuccessful in getting the Project back on schedule. Thus, on September 27, 2019, BVCI notified Boldt that, due to its continued default and unwillingness to cure that default at its own expense, BVCI was terminating Boldt’s work on the 20 wind turbines that previously had been removed from Boldt’s scope of work. Subsequently, on September 30, 2019, BVCI gave Boldt notice that Boldt’s remaining work on the Project was terminated for cause. BVCI then assumed responsibility for the completion of Boldt’s work. BVCI did not

complete work on the Project until February 2020. Following its termination, Boldt sued BVCI for breach of the Subcontract in December 2019. In response, BVCI asserted a counterclaim alleging that Boldt breached the Subcontract by failing to complete its work on the Project in a timely manner. The parties then filed cross- motions for summary judgment focused on whether BVCI properly terminated Boldt pursuant to the Subcontract’s “Termination for Cause” provision. The Court ultimately granted summary judgment in BVCI’s favor as to Boldt’s breach-of-contract claim and denied summary judgment to Boldt as to BVCI’s counterclaim. The bottom line of the Court’s summary judgment ruling was a finding as a matter of law that BVCI properly terminated Boldt for cause due to its failure

to timely perform its work on the Project. After a trial on the limited issue of BVCI’s damages, the jury returned a verdict awarding nominal damages of $1.00. DISCUSSION Both BVCI and Boldt have filed post-trial motions. BVCI asks that the Court vacate the jury’s verdict awarding it only nominal damages and order a new trial on damages. For its part, Boldt argues that, given the jury’s award of nominal damages, it is now entitled to collect from BVCI as part of this action the amounts that it is owed for its work on the Project. The Court begins with BVCI’s motion for a new trial before turning to Boldt’s motion. I. BVCI’s Motion for a New Trial A party may prevail on a motion for a new trial under Rule 59(a) only “if the jury’s verdict is against the manifest weight of the evidence, or if for other reasons the trial was not fair to the moving party.” Willis v. Lepine, 687 F.3d 826, 836 (7th Cir. 2012) (internal quotation marks and alteration omitted). “In assessing a motion for a new trial, the trial judge must

‘perform its own assessment of the evidence presented,’ and do so ‘neutrally.’” Magnuson v. Trulite Glass & Aluminum Sols., LLC, No. 19 C 6158, 2024 WL 1216338, at *2 (N.D. Ill. Mar. 21, 2024) (quoting Lewis v. McLean, 941 F.3d 886, 893 (7th Cir. 2019)). However, “[a] new trial should be granted only when the record shows that the jury’s verdict resulted in a miscarriage of justice or where the verdict, on the record, cries out to be overturned or shocks the conscience.” Davis v. Wis. Dep’t of Corrs., 445 F.3d 971, 979 (7th Cir. 2006) (internal quotation marks omitted). A. Manifest Weight of the Evidence BVCI first challenges the sufficiency of the evidence supporting the jury’s verdict. Where a party argues that the jury’s verdict is against the manifest weight of the evidence, a district court has a “narrow role,” which “is to determine if a reasonable basis exists in the record

to support the verdict.” Lewis, 941 F.3d at 893 (internal quotation marks omitted). To set aside a jury’s verdict, a district court must conclude that “no rational jury could have rendered it.” Id. Here, the sole question before the jury was the proper amount of money to award BVCI to compensate it for Boldt’s breach of the Subcontract. In Illinois, “[t]he party claiming damage bears the burden of proving those damages to a reasonable degree of certainty.” TAS Distrib. Co. v. Cummins Eng. Co., 491 F.3d 625, 632 (7th Cir. 2007). That burden cannot be met through “conjecture or speculation.” Kirkpatrick v. Strosberg, 894 N.E.2d 781, 793 (Ill. App. Ct. 2008).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anthony Wilson v. Billy Groaning and Chris Dunn
25 F.3d 581 (Seventh Circuit, 1994)
Whitehead v. Bond
680 F.3d 919 (Seventh Circuit, 2012)
Michael A. Willis v. William J. Lep
687 F.3d 826 (Seventh Circuit, 2012)
United States v. Mallett
496 F.3d 798 (Seventh Circuit, 2007)
Kirkpatrick v. Strosberg
894 N.E.2d 781 (Appellate Court of Illinois, 2008)
Belleville Toyota, Inc. v. Toyota Motor Sales, U.S.A., Inc.
770 N.E.2d 177 (Illinois Supreme Court, 2002)
Northern Illinois Gas Co. v. Vincent DiVito Construction
573 N.E.2d 243 (Appellate Court of Illinois, 1991)
Amp-Rite Electric Co. v. Wheaton Sanitary District
580 N.E.2d 622 (Appellate Court of Illinois, 1991)
Castricone v. Michaud
583 N.E.2d 1184 (Appellate Court of Illinois, 1991)
Brewer v. Custom Builders Corp.
356 N.E.2d 565 (Appellate Court of Illinois, 1976)
G.M. Harston Construction Co. v. City of Chicago
371 F. Supp. 2d 949 (N.D. Illinois, 2005)
Santorini Cab Corp. v. Banco Popular North America
2013 IL App (1st) 122070 (Appellate Court of Illinois, 2013)
Thorncreek Apartments III, LLC v. Mick
886 F.3d 626 (Seventh Circuit, 2018)
Union Tank Car Co. v. NuDevco Partners Holdings, LLC
2019 IL App (1st) 172858 (Appellate Court of Illinois, 2019)
Karahodzic v. JBS Carriers, Inc.
881 F.3d 1009 (Seventh Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
The Boldt Company v. Black & Veatch Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-boldt-company-v-black-veatch-construction-inc-ilnd-2025.