The Antonio B. Won Pat International Airport Authority, Guam v. DFS Guam, L.P.

2023 Guam 7
CourtSupreme Court of Guam
DecidedAugust 7, 2023
DocketCVA19-003
StatusPublished
Cited by2 cases

This text of 2023 Guam 7 (The Antonio B. Won Pat International Airport Authority, Guam v. DFS Guam, L.P.) is published on Counsel Stack Legal Research, covering Supreme Court of Guam primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Antonio B. Won Pat International Airport Authority, Guam v. DFS Guam, L.P., 2023 Guam 7 (guam 2023).

Opinion

IN THE SUPREME COURT OF GUAM

THE ANTONIO B. WON PAT INTERNATIONAL AIRPORT AUTHORITY, GUAM, Plaintiff-Appellant,

v.

DFS GUAM L.P., Defendant-Appellee.

Supreme Court Case No.: CVA19-003 Superior Court Case No.: CV0371-16 (consolidated with CV0595-16 and SP0128-16)

OPINION

Appeal from the Superior Court of Guam Argued and submitted on February 21, 2023 Hagåtña, Guam

Appearing for Plaintiff-Appellant: Appearing for Defendant-Appellee: Kathleen V. Fisher, Esq. Maurice Suh, Esq. (argued) Genevieve P. Rapadas, Esq. (argued) Gibson, Dunn & Crutcher LLP E. Christian Calvo, Esq. 333 South Grand Ave. Calvo Fisher & Jacob LLP Los Angeles, CA 90071 259 Martyr St., Ste. 100 Hagåtña, GU 96910 G. Patrick Civille, Esq. Joyce C.H. Tang, Esq. Civille & Tang, PLLC 330 Hernan Cortez Ave., Ste. 200 Hagåtña, GU 96910 Antonio B. Won Pat Int’l Airport Auth. v. DFS Guam L.P., 2023 Guam 7, Opinion Page 2 of 23

BEFORE: F. PHILIP CARBULLIDO, Presiding Justice; KATHERINE A. MARAMAN, Associate Justice; and JOSEPH N. CAMACHO, Justice Pro Tempore.

PER CURIAM:

[1] This court is no stranger to the parties in this case. They have come before this court

several times already, and, we surmise, they will have future issues to litigate. But the question

we are asked to answer today is a narrow one: Did the Arbitration Panel, convened at the behest

of DFS Guam L.P. (“DFS”), act within its authority in ruling for DFS? We conclude it did, and

therefore affirm the decision of the trial court confirming the Arbitration Award.

I. FACTUAL AND PROCEDURAL BACKGROUND

[2] Though the question we are asked to decide is fairly straightforward, the facts underlying

that question can get easily tangled. To better understand the present case, it is helpful to

establish at the outset that in the proceedings below, Plaintiff-Appellant Antonio B. Won Pat

International Airport Authority, Guam (“GIAA”) and Defendant-Appellee DFS Guam L.P.

(“DFS”) have been litigating two contracts, which spawned three separate cases before

everything was consolidated into one proceeding.1 Two relate to an Arbitration Award issued on

May 6, 2015 (CV0371-16 and SP0128-16). These cases (the “Arbitration Actions”) concern the

Main Concession Agreement, a contract signed by both parties. Conversely, the Government

Claims Act case (“Government Claims Action”) is solely about the Mama Bear Agreement

(CV0595-16). While all the cases involve similar and often the same facts, the Arbitration

Actions focus on a separate contract compared to the Government Claims Action. This matter

involves the Arbitration Actions and is thus focused on the Main Concession Agreement. With

that understanding, a fuller explanation of the factual and procedural history can now follow.

1 There is a third contract between the parties, the so-called “Baby Bear Agreement.” However, this agreement has not been implicated by the current lawsuits, so it may be set aside for now. Antonio B. Won Pat Int’l Airport Auth. v. DFS Guam L.P., 2023 Guam 7, Opinion Page 3 of 23

[3] For this case, the parties began their legal relationship on November 6, 2002, when they

signed a leasing agreement for commercial space at the airport called the Main Concession

Agreement. This agreement covered the “main retail concession area” within the airport.

Record on Appeal (“RA”),2 tab 13 (Decl. Jay Trickett, July 11, 2016), Ex. A of Ex. 2 at 2

(Stipulated Facts, Nov. 12, 2015). One of the terms of this agreement was that DFS would post a

$3,375,000 faithful performance bond, which DFS originally satisfied through two instruments.

First, DFS obtained a standby letter of credit from HSBC Bank worth $2 million; then it received

a surety bond issued by Travelers for $1,375,000. On September 12, 2005, DFS replaced the

letter of credit from HSBC with one from Citibank in the same amount, $2 million.

[4] Shortly after making the bank change, DFS and GIAA entered into another agreement,

this one called the Mama Bear Agreement. The Mama Bear Agreement constituted a separate

leasing agreement, covering a different space at the airport, resulting from a separate request for

proposal from GIAA and separate negotiations from the Main Concession Agreement. The

Mama Bear Agreement had its own faithful performance bond requirement set at $250,000.

Because it would be “easier,” DFS proposed releasing its surety bond with Travelers and

satisfying the faithful performance requirements of the two contracts through one letter of credit

issued by Citibank. RA, tab 13 (Decl. Jay Trickett), Ex. 3 at 172 (Joint List Agreed Docs., Jan.

22, 2016). Thus, its existing letter of credit would be increased by $1,375,000 to cover the

Travelers surety bond being released and another $250,000 for the requirement under the Mama

Bear Agreement, for a total increase of $1,625,000. GIAA agreed, and the Citibank letter of

2 Unless otherwise noted, the Record on Appeal refers to documents filed in what became the lead case in the consolidated proceeding: CV0371-16. Antonio B. Won Pat Int’l Airport Auth. v. DFS Guam L.P., 2023 Guam 7, Opinion Page 4 of 23

credit was amended to total $3,625,000 and referred to both agreements. RA, tab 3 (Decl.

Michael Pangelinan), Ex. 1 at 7 (Arbitration Award, May 6, 2016).3

[5] Both contracts contained “evergreen” provisions attached to the surety bond

requirements. This refers to the fact that, in the event of a drawdown of the faithful performance

bond by GIAA, DFS was responsible for replenishing the original amount of the bond. There

was no cap on the evergreen provisions. So, GIAA could draw down more than the amount

required by the surety bond provision for violations of the contract as long as each drawdown

was less than the total bond required to be posted by the contract. At the same time, the

evergreen provisions afforded DFS with a certain amount of time to secure the necessary

funding. RA, tab 13 (Decl. Jay Trickett), Ex. 3 at 44, 117 (Joint List Agreed Docs.) (giving DFS

ten days to offer additional security to GIAA in amount sufficient to restore Faithful

Performance Bond in both contracts).

[6] Besides the different leasing spaces and bond requirements, the two agreements also

differed in how they addressed dispute resolution. The Main Concession Agreement required the

parties to go through arbitration in the event of a dispute. Conversely, the Mama Bear

Agreement provided that any dispute would be handled by the courts of Guam.

[7] In 2013, GIAA alleged DFS had violated the Mama Bear Agreement. GIAA demanded

Citibank pay out $2,104,582.88 for the damages it had suffered, which Citibank eventually did

by drawing down on the letter of credit. At no point throughout this entire dispute has GIAA

alleged that DFS violated the Main Concession Agreement; it has only ever alleged a violation of

the Mama Bear Agreement. See RA, tab 13 (Decl. Jay Trickett), Ex. A of Ex. 2 at 7 (Stipulated

Facts).

3 The letter of credit would be amended once more to cover the amount required by a faithful performance bond provision of the Baby Bear Agreement. RA, tab 3 (Decl. of Michael Pangelinan), Ex. 1 at 8 (Arbitration Award, May 6, 2016). Antonio B. Won Pat Int’l Airport Auth. v. DFS Guam L.P., 2023 Guam 7, Opinion Page 5 of 23

[8] DFS disputes that it violated the Mama Bear Agreement and, in addition, argues that

GIAA violated the Main Concession Agreement by drawing down on funds reserved for the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2023 Guam 7, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-antonio-b-won-pat-international-airport-authority-guam-v-dfs-guam-guam-2023.