Thanks But No Tank v. Maine Dep't of Envtl. Protection

CourtSuperior Court of Maine
DecidedNovember 13, 2012
DocketKENap-11-058
StatusUnpublished

This text of Thanks But No Tank v. Maine Dep't of Envtl. Protection (Thanks But No Tank v. Maine Dep't of Envtl. Protection) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thanks But No Tank v. Maine Dep't of Envtl. Protection, (Me. Super. Ct. 2012).

Opinion

STATE OF MAINE SUPERIOR COURT KENNEBEC, ss Civil Action Docket No. AP-1~-~8 1

~~,"1--- K ( /V -· I/ I ~/~()/L / THANKS BUT NO TANK, et al.,

Petitioners

v. DECISION AND ORDER

MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION,

Respondents

Before the court is the petitioners' Rule SOC appeal of the Maine Department of

Environmental Protection's (DEP) decision. The DEP granted Natural Resources

Protection Act (NRP A) and Site Location of Development Act (Site Law) permits to

DCP Midstream Partners (DCP). 38 M.R.S. § 480-A (2011); 38 M.R.S. § 481 (2011). The

permits allow DCP to construct a liquefied propane gas terminal in Searsport, Maine.

BACKGROUND

In October 2011, the DEP issued a permit pursuant to NRPA and Site Law to

DCP. (R. 99.) DCP proposed "the construction and operation of a liquid propane gas

(LPG) terminal in Searsport, Maine," adjacent to the Mack Point Terminal. 1 (R. 99.) The

DEP Order provides a detailed description of the plan. (R. 99.) The plan is also detailed

in the permit applications (R. 6, 8) and the petitioners' statement of the facts. (Br. of

Pets.' 7-9.) The most critical aspects of the project, as related to this appeal, are

discussed below.

1 "The Mack Point Terminal has an existing Liquid Cargo Pier, an existing Dry Cargo Pier, numerous existing truck load out facilities for products other than LPG, and is serviced by a Montreal, Maine and Atlantic Railroad spur." (R. 99 (from DEP Order).)

1 The project will include building a new bulk storage tank that "will be a vertical,

insulated domed tank with diameter of approximately 202 feet and height above

ground of approximately 138 feet." (R. 6 at 1-4.) The facility, which will operate

continuously, will also utilize the Dry Cargo Pier for ship unloading, a truck loading

station, and a rail car loading station. (R. 6 at 1-1.) Additionally, "the proposed

terminal will include an emergency flare, expected to be approximately 75 feet tall, with

a continuously operating propane pilot light." (R. 6 at 1-5.)

The surrounding area includes residential and commercial development,

including a hotel and restaurant. (R. 6 at 1-6, 10, 13.) Sears Island is just outside of the

one-mile radius. (R. 8 at A. 14A.) A photo-simulated view was provided to

demonstrate the visibility from Sears Island's shore. (R. 8 at 14-4 & A. 14A.) The Maine

Historic Preservation Commission reviewed an Architectural Survey report to review

potential impacts to historic structures in the area. (R. 8 at 14-3.) Three scenic

resources, in addition to the NPHP-listed or NPHP-eligible properties, are also within

the three-mile radius used for the Viewshed Analysis. (Id.) "They are: Long Cove and

Penobscot Bay, which are part of the Atlantic Ocean, Mosman Park, a municipal park

near downtown Searsport, and Moose Point State Park, located near the

Searsport/Belfast town line." (Id.) In its application, DCP claimed that the visual

impact from these locations would be minimal and the "quality of the view is not

significantly diminished." (R. 8 at 14-3, 14-4.)

Ship, truck, and rail traffic to Mack Point Terminal will increase as a result of this

project. The current conditions are as follows:

The existing ship traffic at the two piers totals approximately 136 vessels per year on average with a maximum to date of 166 vessels per year. The number of trucks currently entering and exiting the Mack Point Terminal is approximately 20,000 per year on average with up to approximately 30,000 trucks per year as a maximum. The existing rail traffic is typically

2 approximately 2,500 rail cars per year, averaging about 10 to 15 cars at a time.

(R. 6 at 1-6.) The expected typical loading schedule for this facility is 50-60 trucks per

day and eight rail cars per day, with a maximum of 144 trucks per day. (R. 6 at 1-5.)

DCP submitted applications pursuant to NRP A (R. 8) and Site Laws (R. 6). The

NRP A application included a Visual Impact Assessment (VIA) (R. 8 at 14), which the

plaintiffs found inadequate. Additionally, the Site Law application included a noise

analysis. (R. 6 at § 5.) This analysis estimated the project's noise level at 59.6 dBA,

which is within the applicable MDEP Noise Standard2 of 60 dBA. (R. 6 at 5-8.) The

plaintiffs also found this analysis inadequate.

The DEP issued a draft order and allowed public comments. 3 (R. 61.) They

received substantial public comments, primarily voicing concern about the project. (R.

36-60, plus others.) The DEP issued the final order in October 2011. (R. 99.)

Thanks But No Tank, an association, and some of those individuals who voiced

concerns about this project filed this appeal. They argue that

(1) DCP did not demonstrate compliance with the NRP A and the Site Law;

(2) the respondent did not consider the impact of accidents;

(3) the respondent did not consider the impact to air quality;

(4) the respondent's conclusion that the project will meet hourly sound standards

is erroneous and unsupported by the evidence;

(5) the respondent did not consider noise from tanker trucks; and

(6) the respondent did not consider the effect of the project on natural resource-

based businesses in the region.

2 "The applicable MDEP noise standard for the project is 70 dBA during the day and 60 dBA at night at any protected location in a commercial zone. Since the facility will operate 24 hours per day, the nighttime noise limit of 60 dBA is the controlling standard." (R. 6 at S-2.) 3 No request for a public hearing was received. (R. 99.)

3 DISCUSSION

1. Standard of Review

This appeal is permitted pursuant to 38 M.R.S. § 346(1) (2011) and is controlled

by the Maine Administrative Procedure Act, 5 M.R.S. § 11001 et seq., and Rule SOC.

When reviewing administrative orders, the court may reverse the decision if the

findings, inferences, conclusions or decisions are, among other things, "unsupported by

substantial evidence on the whole record; or [a]rbitrary or capricious or characterized

by abuse of discretion." 5 M.R.S. § 11007(4)(C)(5),(6) (2011). The court shall not

"substitute its judgment for that of the agency on questions of fact." 5 M.R.S. § 11007(3)

(2011).

Under the "substantial evidence" standard, the court examines the record to

determine whether the agency could "fairly and reasonably find the facts as it did."

Rangeley Crossroads Coal. v. Land Use Reg. Comm'n, 2008 ME 115,

Even if the record contains evidence inconsistent with the result, or a different

conclusion could be drawn from the evidence, the court must uphold the agency's

factual findings "if a reasonable mind might accept the relevant evidence as adequate to

support the [agency's] conclusion." Town of Vienna v. Kokernak, 612 A.2d 870, 872

(Me. 1992).

Additionally, the court defers to the agency's interpretation of its own internal rules,

regulations, and procedures "unless the rules or regulations plainly compel a contrary

result." Rangeley Crossroads Coal., 2008 ME 115,

2. Standing

DCP asserts that 19 of the 21 named individual petitioners as well as the

association Thanks But No Tank do not have standing in this case. (Br. of DCP 10.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ricci v. Superintendent, Bureau of Banking
485 A.2d 645 (Supreme Judicial Court of Maine, 1984)
Sahl v. Town of York
2000 ME 180 (Supreme Judicial Court of Maine, 2000)
Rangeley Crossroads Coalition v. Land Use Regulation Commission
2008 ME 115 (Supreme Judicial Court of Maine, 2008)
Uliano v. Board of Environmental Protection
2009 ME 89 (Supreme Judicial Court of Maine, 2009)
Gaynor v. McEachern
437 A.2d 867 (Supreme Judicial Court of Maine, 1981)
Town of Vienna v. Kokernak
612 A.2d 870 (Supreme Judicial Court of Maine, 1992)
Wells v. Portland Yacht Club
2001 ME 20 (Supreme Judicial Court of Maine, 2001)
Tisdale v. Rawson
2003 ME 68 (Supreme Judicial Court of Maine, 2003)
In re International Paper Co.
363 A.2d 235 (Supreme Judicial Court of Maine, 1976)
Nergaard v. Town of Westport Island
2009 ME 56 (Supreme Judicial Court of Maine, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
Thanks But No Tank v. Maine Dep't of Envtl. Protection, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thanks-but-no-tank-v-maine-dept-of-envtl-protection-mesuperct-2012.