Motions for Rehearing Denied, Reversed and Remanded, and Substitute Majority and Dissenting Opinions filed October 4, 2018.

In The

Fourteenth Court of Appeals

NO. 14-16-00474-CV

TEXAS WINDSTORM INSURANCE ASSOCIATION, Appellant V.

DICKINSON INDEPENDENT SCHOOL DISTRICT, Appellee

On Appeal from the 405th District Court Galveston County, Texas Trial Court Cause No. 12-CV-2012

SUBSTITUTE MAJORITY OPINION

The parties’ motions for rehearing are denied.1 We withdraw our May 31, 2018 majority opinion and substitute the following in its stead. Our judgment remains unchanged.

1 Chief Justice Frost would grant in part Dickinson Independent School District’s Motion for Rehearing.

Today we consider whether Dickinson Independent School District (“DISD”)

is entitled to judgment for breach of contract damages against Texas Windstorm Insurance Association (“TWIA”) based on an appraisal award.

DISD sued TWIA in connection with TWIA’s handling of DISD’s Hurricane Ike claims. DISD alleged breach of contract and related claims. During the proceedings, TWIA invoked the insurance policy’s appraisal provisions, and the resulting appraisal award totaled $10.8 million in damages. DISD amended its petition to abandon all claims except breach of contract and, based on the appraisal award, filed traditional motions for partial summary judgment on the elements of causation and damages. TWIA opposed the motions because, among other things, DISD had not conclusively proven that the alleged damages reflected in the appraisal award, or any portion of them, were caused by covered perils. The trial court granted both motions in DISD’s favor. The case proceeded to trial and the sole question put to the jury was whether TWIA breached the policy by failing to pay the appraisal award, which the jury answered affirmatively. The trial court signed a final judgment against TWIA for $9,602,542.82.

TWIA challenges the trial court’s judgment in the following issues:

• In its first issue, TWIA challenges the orders granting partial summary judgment on causation and damages because DISD did not conclusively prove (or TWIA raised genuine issues of material fact) that DISD’s alleged damages were caused by a named peril or covered by the TWIA policy. Further, TWIA asserts that DISD did not meet its burden to prove coverage at trial through expert testimony. As a remedy, TWIA requests rendition of judgment as a matter of law or remand for new trial. • In its second issue, TWIA contends that the trial court reversibly erred in excluding TWIA’s trial evidence supporting its affirmative defenses. • In issue three, TWIA urges that the trial court erred in submitting DISD’s jury question and in refusing to submit TWIA’s proposed question and instructions.

• Finally, in its fourth issue, TWIA contends that legally insufficient evidence supports the jury’s finding that TWIA breached the policy by not paying the appraisal award or that TWIA’s failure to pay the award proximately caused the damages reflected in the judgment.

For the reasons explained below, we sustain TWIA’s first issue in part and hold that the trial court erred in granting DISD’s motions for partial summary judgment on causation and damages because DISD’s evidence, including the appraisal award, did not conclusively prove whether and how much alleged loss was caused by a covered peril and otherwise subject to coverage under the policy terms and conditions. Having sustained this portion of TWIA’s first issue, we further conclude that remand for further proceedings, as opposed to rendition of judgment, is the appropriate remedy under the present circumstances. Given our resolution of TWIA’s first issue, reaching TWIA’s remaining issues is not necessary to final disposition of this appeal. See Tex. R. App. P. 47.1. Accordingly, we reverse the trial court’s judgment and remand for further proceedings consistent with this opinion.

Background

TWIA issued a windstorm and hail commercial policy of insurance to DISD, the named insured. The relevant policy period was from September 1, 2008 to September 1, 2009. As to each covered property, the policy provided for two potential forms of coverage depending on whether a limit of liability for a particular form of coverage was shown in the declarations. The two forms of coverage were identified in the policy as “COVERAGE A (Building)” or “COVERAGE B (Business Personal Property).” The policy provided in relevant part2 as follows:

2 We do not opine on the merits or applicability of any policy exclusions or terms, whether or not quoted in this opinion.

AGREEMENT We will provide the insurance described in this policy in return for the premium and compliance with all applicable provisions of this policy.

***

COVERED CAUSES OF LOSS We insure for direct physical loss to the covered property caused by windstorm or hail unless the loss is excluded in the Exclusions.

EXCLUSIONS The following exclusions apply to loss to covered property: 1. Flood.

We will not pay under any and all circumstances for loss or damage caused by or resulting from flood, surface water, waves, storm surge, tides, tidal water, tidal waves, tsunami, seiche, overflow of streams or other bodies of water, or spray from any of these, all whether driven by wind or not.

***

6. Rain.

We will not pay for loss or damage caused by or resulting from rain, whether driven by wind or not unless wind or hail first makes an opening in the walls or roof of the described building. Then we will only pay for loss in the interior of the building, or the insured property within, caused immediately by rain entering through such openings.

***

CONDITIONS

***

4. Duties After Loss.

a. Your Duties After Loss. In case of a loss to covered property caused by windstorm or hail you must:

(1) Give us prompt written notice. Include a description of the property involved;

(2) Protect the property from further damage;

(3) Make reasonable, necessary, and temporary repairs to protect the property;

(4) Keep an accurate record of repair expenses; (5) Furnish a complete inventory of damaged personal property showing the quantity, description, and amount of loss. Attach all bills, receipts and related documents which you have that justify the figures in the inventory. . . .

***

10.Appraisal. If you and we fail to agree on the actual cash value, amount of loss, or cost of repair or replacement, either can make a written demand for appraisal. Each will then select a competent and independent appraiser and notify the other of the appraiser’s identity within 20 days of receipt of the written demand. The two appraisers will choose a competent and independent umpire. If they cannot agree upon an umpire within 15 days, you or we may request that the choice be made by a judge of a district court of a judicial district where the loss occurred. The two appraisers will then determine the amount of loss, stating separately the actual cash value and loss to each item. If the appraisers fail to agree, they will submit their differences to the umpire. An itemized decision agreed to by any two of these three and filed with us will determine the amount of the loss. Each party will pay its own appraiser and bear the other expenses of the appraisal and umpire equally.

Free access — add to your briefcase to read the full text and ask questions with AI

Texas Windstorm Insurance Association v. Dickinson Independent School District, 561 S.W.3d 263 (Tex. Ct. App. 2018).

561 S.W.3d 263 (Texas Windstorm Insurance Association v. Dickinson Independent School District) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Carmen Aleman v. Standard Casualty Company
Court of Appeals of Texas, 2025
Brandon Chiv v. Ranferi Monge Figueroa
Court of Appeals of Texas, 2025
Garrick D. Brown v. Mathew Robert Stone
Court of Appeals of Texas, 2025
Eric John Ramirez v. Juanita Sanchez
Court of Appeals of Texas, 2023