delivered the opinion of the court.

On December 10, 1909, J. C. Crowdus contracted in writing with J. D. Turner, a contractor, to build for him a two-story brick building in the City of Fort Worth, Tarrant County, Texas, for the sum of $8905. Turner was to furnish all material. He gave a bond binding himself - and his surety, the Adams-Simpson Lumber Company, unto-J. C. Crowdus, as well as to all persons who might become entitled to liens under the builder’s contract, which was executed at the same time between said Turner and said Crowdus in the sum of $4452.50, to be paid to said J. C. Crowdus and to said parties who may be entitled to liens, their executors, administrators or assigns. The bond which Turner gave was as follows:

“Know all men by these presents:

“That we, J. D. Turner and Adams-Simpson Lumber Company of the City of Fort Worth, County of Tarrant, and State of Texas, are held and firmly bound unto J. C. Crowdus of said county and State, as well as to all persons who may become entitled to liens under the contract hereinbefore mentioned, in the sum of $4452.50, lawful money of the United States of America, to be paid to the said J. C. Crowdus, and to said parties who may be entitled to liens, their executors and administrators, or assigns, for which payment, well and truly to be made, we bind ourselves, one and each of our heirs, executors and administrators, jointly and severally firmly by these presents.

“Sealed with our seals, dated this 10th day of December, 1909.

“The condition of this obligation is such that if the above bounden J. D. Turner, his executors, administrators, or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions and agreements in the above mentioned contract, entered into by and between the said J. D. Turner and the said J. C. Crowdus, dated on the 10th of December, 1909, for the construction of work or works on the lot mentioned on the foregoing contract, and shall duly and promptly pay and discharge all indebtedness that may be incurred by the said J. D. Turner in carrying out the said contract, and complete the same free of all mechanics’ liens and shall truly keep and perform the covenants and agreements in said contract and in the within instrument contained, on his part to be kept and performed, at the time and in the manner and form therein specified, as well as all costs, including attorney’s fees, in enforcing the payment and collection of any and. all indebtedness incurred by the said J. D. Turner in carrying out the said contract, then the above obligation shall be void, else to remain in full force and effect.

“This bond is made for the use and benefit of all persons who may

*349 become entitled to liens under the said contract, according to the provisions of law in such cases made and provided, and may be sued upon by them as if executed to them in proper person.” The Southwestern Iron Company, one of the plaintiffs in error, sold to Turner a quantity of material aggregating in value the sum of $536. This material was delivered to Turner about the 1st of February, 1910, construction of the building having been begun on January 4, 1910. The sale of this material was evidenced by a written contract which mentioned no date of payment, but by parol evidence it was shown to have been agreed that payment was to be made within thirty and sixty days after delivery. The Southwestern Iron Company filed with the county clerk of Tarrant County, with the view of fixing a lien upon the building, its written contract, with an itemized statement of the material sold to Turner. While the building was being constructed, and prior to March, 1910, the Adams-Simpson Lumber Company also furnished Turner material to be used in the construction of the building. On March 12, 1910, Turner made a written assignment to the Adams-Simpson Lumber Company of all that might be or become due to him from Crowdus under the contract for the construction of the ■ building. On that day Turner owed the Adams-Simpson Lumber Company a sum exceeding $1100. The said assignment was presented to and accepted by the agent of Crowdus. On February 2, 1910, Turner purchased from the Texas Glass & Paint Company, one of the plaintiffs in error, for use in the construction of the building material aggregating in value $308.76, to be paid for on delivery. The Texas Glass & Paint Company did not attempt to fix any lien by filing its account with the county clerk. When Turner completed the building there was due him by Crowdus $1086.15, but the claims of these three creditors were unpaid.

The Southwestern Iron Company, one of the plaintiffs in error, instituted this suit in the District Court of Tarrant County, Texas, against J. D.-Turner, the Adams-Simpson Lumber Company and J. C. Crowdus, in July, 1910. By amended petition it sought a judgment for the full amount of its debt and $100 at attorney’s fees, the foreclosure of its lien against the building and lot upon which it was situated, and a personal judgment against the Adams-Simpson Lumber Company. Later the Texas Glass & Paint Company, one of the plaintiffs in error, intervened and sued upon its said claim for the value of the material which it had furnished Turner, and prayed for similar relief to the extent of its debt. The Adams-Simpson Lumber Company answered by exceptions and denials, and in addition filed a cross-bill containing two counts. In the first count it set up the assignment, from Turner by which the balance due on the contract was transferred to it and asked judgment against Crowdus for that sum. In the second count it set up the contract by which it furnished material in the value of $1841.25 used in the construction of the building, and alleged compliance with the statute in fixing its lien. It also set up an account which had been assigned to it, amounting to $294.77, for material fur-

*350 nislied by other parties, and this, too, it alleged, was secured by lien on the building. It asked for judgment against Turner, and for a foreclosure of its lien against the building and lot.

During the progress of the trial Crowdus was permitted, by agreement among the parties, to pay into court, and be discharged from any further liability, the balance due by him to Turner on the contract price of $1086.15. The case was tried before the court without a jury. The trial court rendered judgment dismissing C. D. Simpson and T. J. Adams, two of the defendants who had not been cited to appear, giving judgment in favor of the Texas Glass & Paint Company against the defendant, J. D. Turner, in the sum of $308.73, with six per cent interest from the date of the judgment, and denied a lien against the property of said J. C. Crowdus, or a foreclosure thereof. It rendered judgment in favor of the Southwestern Iron Company against the defendant, J. D. Turner, in the sum of $536, with six per cent interest from March 28, 1910, and the further sum of $50 attorney’s fees, and further ordered that it recover one-half of the amount of judgment rendered in its favor against Turner, to wit: the sum of $2fi8, with six per cent interest from March 28, 1910, and $50 attorney’s fees, out of said $1086.15, which had been 'deposited in the registry of the court by Crowdus as the amount still owing by him to Turner, and directed the clerk of the court to pay said two sums out of said fund.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robert Burns Concrete Contractors, Inc. v. Norman
561 S.W.2d 614 (Court of Appeals of Texas, 1978)
Lebo v. Dochen
310 S.W.2d 715 (Court of Appeals of Texas, 1958)
Tezel & Cotter v. Roark
301 S.W.2d 179 (Court of Appeals of Texas, 1957)
Watson Co. v. Shaw
47 S.W.2d 474 (Court of Appeals of Texas, 1932)
Globe Indemnity Co. v. West Texas Lumber Co.
34 S.W.2d 896 (Court of Appeals of Texas, 1930)
Natkin Engineering Co. v. Ætna Casualty & Surety Co.
22 S.W.2d 717 (Court of Appeals of Texas, 1929)
Oak Cliff Lumber Co. v. American Indemnity Co.
266 S.W. 429 (Court of Appeals of Texas, 1924)
Huffman v. McDonald
261 S.W. 146 (Court of Appeals of Texas, 1924)
Foust v. Bibb
258 S.W. 921 (Court of Appeals of Texas, 1924)
Atkinson v. Jackson Bros.
259 S.W. 280 (Court of Appeals of Texas, 1923)
Gilbert Mfg. Co. v. Connellee
253 S.W. 551 (Court of Appeals of Texas, 1923)
Equitable Surety Co. v. Stemmons
239 S.W. 1037 (Court of Appeals of Texas, 1922)
Burk Burnett-Mann Oil Co. v. Robertson
240 S.W. 1046 (Court of Appeals of Texas, 1922)
Koehler v. Standard Sanitary Mfg. Co.
230 S.W. 785 (Court of Appeals of Texas, 1921)
First National Bank v. Lyon-Gray Lumber Co.
217 S.W. 133 (Texas Supreme Court, 1919)
Burns & Hamilton Co. v. Denver Inv. Co.
217 S.W. 719 (Court of Appeals of Texas, 1919)
Hicks v. Faust
212 S.W. 608 (Texas Supreme Court, 1919)
Fennell v. Trinity Portland Cement Co.
209 S.W. 796 (Court of Appeals of Texas, 1919)
Equitable Surety Co. v. Mosher Mfg. Co.
202 S.W. 788 (Court of Appeals of Texas, 1918)
Gordon-Jones Const. Co. v. Welder
201 S.W. 681 (Court of Appeals of Texas, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
193 S.W. 1072, 108 Tex. 346, 1917 Tex. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/texas-glass-paint-co-v-crowdus-tex-1917.