Equitable Surety Co. v. Mosher Mfg. Co.

202 S.W. 788, 1918 Tex. App. LEXIS 326
CourtCourt of Appeals of Texas
DecidedMarch 23, 1918
DocketNo. 7902.
StatusPublished
Cited by2 cases

This text of 202 S.W. 788 (Equitable Surety Co. v. Mosher Mfg. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Equitable Surety Co. v. Mosher Mfg. Co., 202 S.W. 788, 1918 Tex. App. LEXIS 326 (Tex. Ct. App. 1918).

Opinion

TALBOT, J.

This suit was brought by the appellee, Mosher Manufacturing Company, against M. P. Kelley, as principal, and the appellant, Equitable Surety Company, as surety, on a bond for the erection of a courthouse for Anderson county, Tex. The case was tried on an agreed statement of facts. It was alleged and proved, in substance, that about May 20, 1913, the defendant Kelley entered into a contract in writ--ing with Anderson county to construct the Anderson county courthouse at Palestine, Tex., and complete the same at a contract price of $148,438; that on the 6th day of June, 1913, the defendant Kelley, as principal; .and defendant Equitable Surety Company, as surety, entered into a contract bond payable to Anderson county in the penal sum of $74,219, and conditioned upon Kelley’s faithful performance of the contract and payment of all claims for material and labor used in the building; that under contracts between plaintiff and Kelley the plaintiff had furnished material for the building, and the defendant Kelley was indebted to plaintiff therefor in the sum of $4,879.25 and interest, which materials were furnished Kelley by plaintiff prior to the time the county took over the completion of the work from Kelley; that thereafter Kelley became insolvent and abandoned the work and left the'state, and the building was completed by the county at a net loss to the county of $4,100.86 over and above the contract price agreed to be paid to Kelley, for which amount the county had been reimbursed by the defendant surety company and upon which payment the county had released the surety company from any further liability to Anderson county on the bond; and that, by reason of the premises, Kelley as principal', and the Equitable Surety Company as surety, were obligated to pay plaintiff’s claim. The defendant Equitable Surety Company answered, in effect, denying all material allegations in plaintiff’s petition except such as were confessed. The case was dismissed as to M. P. Kelley, whose whereabouts were uilknown. The bond recites the award of the contract, and that:

“As part of said award M. P. Kelley is required to enter into contract in writing as per draft thereof hereto attached and execute this bond.”

The defeasance clause of the bond reads thus:

“Therefore, should the said Kelley faithfully and fully perform, discharge and carry out all the things by him agreed to be done in his said contract within the time and in manner and form as therein set out and pay all claims for labor and material used in the construction of said building and fully indemnify and save the said Anderson county, Tex., harmless against all loss, damages and costs which he may suffer or incur by reason of the failure of the said M. P. Kelley to carry out and perform said contract, then this obligation shall become void; otherwise it shall remain in full force and effect.”

Article 1 of the contract stipulates that:

“The contractor shall and will provide all materials and perform all the wozk for the building of the Anderson county courthouse at Palestine, Tex., with basement and three stories and dome *789 as shown by the drawings and described in the specifications prepared by O. H. Page & Bro., of Austin and Houston, Tex., architects.”

And article 5 provides that:

“Should the contractor at any time refuse or neglect to supply a suificiency of properly skilled workmen or materials of proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the architects, the owner shall be at liberty after three days’ written notice to the contractor to provide such labor or materials and to deduct the cost thereof from any money then due or thereafter to become due to the contractor under this contract; and if the architects shall certify that such refusal, neglect or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractor for said work and * * * take possession for the purpose of completing the work, etc.”

The said contract contains no promise by tiie contractor, Kelley, to pay claims for labor and material. In an addenda to the contract there is a provision that:

“In case of the death or mental or physical incapacity of the contractor, the county of Anderson may complete the building, for and on account of the contractor, settlement to be made in accordance with an estimate to be made by the architect; that in making the estimate” the architect shall deduct and pay any lawful items for material or labor due by the said Kelley and charge the same to his account.

Anderson county took over the work and proceeded under said article 5 of the contract to complete the building. At the time Kelley abandoned the work, the county had paid to him $6,359 on account of material furnished by the appellee, and by contract with the county the appellee agreed to furnish the rest of the material called for by its contract with Kelley, “understanding that $6,359, which has been paid to Mr. Kelley on this work, is to be deducted from the amount of our contract, and we will complete the work for $3,600, and that the said $6,359 is to be paid after the completion of the building, if there is a sufficient fund to do so; otherwise, this amount will have to be collected from either Mr. Kelley or his bondsmen.”

The case was tried without a jury, the court filing conclusions of fact and law, and judgment rendered in favor of the appellee against the appellant for the sum of $5,571.-10. From this judgment the appellant perfected an appeal.

The first assignment of error, which is submitted as a proposition, is as follows:

“The bond sued on herein, given to indemnify the owner of the building against the breach of the original builder’s contract, being by its terms a bond of indemnity to the owner alone, no cause of action exists thereon in favor of subcontractors or persons who furnished material to the contractor, and the court erred in holding that such materialmen and subcontractors were beneficiaries thereunder and entitled to judgment against this surety for their claims against the original contractor.”

The question is whether the bond sued on was a bond of indemnity to the county of Anderson alone, or one securing to material-men the payment of their claims and upon which they have a right of action in their own names. We think it must be held,' under decisions of the appellate courts of this state, that the bond in question is merely one of indemnity to Anderson county against any failure on the part of M. P. Kelley to furnish the labor and materials and to erect and complete the courthouse agreed to be built, in accordance with the terms and provisions of the contract entered into between the parties, and does not give a right of action to the materialmen against the surety upon the bond. Like the cases to which we refer above, there is no affirmative promise by Kelley in the contract entered into between him and the county, nor by him or the surety in the bond under consideration, to pay the claims of materialmen. It is true the defeasance clause of the bond reads that:

“Should the said M. P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Nat. Bank of Hot Springs, N. M. v. Caples
17 F.2d 87 (Fifth Circuit, 1927)
Mosher Mfg. Co. v. Equitable Surety Co.
229 S.W. 318 (Texas Commission of Appeals, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
202 S.W. 788, 1918 Tex. App. LEXIS 326, Counsel Stack Legal Research, https://law.counselstack.com/opinion/equitable-surety-co-v-mosher-mfg-co-texapp-1918.