Texas Eastern Transmission Corp. v. Garber Brothers, Inc.

494 F. Supp. 832, 1980 U.S. Dist. LEXIS 9249
CourtDistrict Court, E.D. Louisiana
DecidedJuly 19, 1980
DocketCiv. A. 78-3490
StatusPublished
Cited by4 cases

This text of 494 F. Supp. 832 (Texas Eastern Transmission Corp. v. Garber Brothers, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Texas Eastern Transmission Corp. v. Garber Brothers, Inc., 494 F. Supp. 832, 1980 U.S. Dist. LEXIS 9249 (E.D. La. 1980).

Opinion

CHARLES SCHWARTZ, Jr., District Judge.

This suit, which arises out of damage done to an offshore pipeline, was taken under submission at the conclusion of a five day non-jury trial. Upon consideration of the record, the evidence adduced at trial, the briefs and memoranda of counsel, and the law, the Court finds as follows. 1

*833 FINDINGS OF FACT

In September, 1978, Texas Eastern Transmission Corporation (Texas Eastern) owned a ten and three-quarter inch pipeline, on which construction was not quite complete, in Block 280 of the West Cameron area of the Gulf of Mexico. The pipeline connected platforms B and C, both of which were owned by Union Oil Company of California (Union); platform B lay to the northeast of platform C. The pipeline was approximately 8000 feet long and at all times here relevant was neither buried nor entrenched.

In order to construct the pipeline, Texas Eastern was required to apply for a permit from the United States Army Corps of Engineers, which granted that permit on May 11, 1978. Texas Eastern was also required to obtain right of way approval from the Bureau of Land Management of the Department of the Interior. Such an application was made on March 31, 1978, and was granted on July 17, 1978. The J. Ray McDermott Company (McDermott) laid Texas Eastern’s pipeline during July of 1978; Odom Offshore Services, Inc., provided surveying and other services related to the pipeline construction.

Union used its C platform for oil drilling. Fluor Drilling Services, Inc. (Fluor), conducted the drilling activity, which began after the laying of the pipeline which is the subject of this case. Fluor used the MR. GUS II, a jack-up rig, for this drilling. In order to allow the MR. GUS II to proceed with its work, it had been necessary to relocate the Texas Eastern pipeline. This relocation was undertaken in conjunction with a relocation of risers connected to the southeast corner of the C platform. A six hundred foot section of the pipeline was repositioned by McDermott’s DERRICK BARGE 17, which completed that work on September 8, 1978.

Union employed Jack M. Holt, an independent contractor, as its petroleum engineer to monitor operations on C platform. He arrived at the platform on September 6, 1978. Mr. Holt also ordered supplies and equipment as a part of his duties.

The M/V BLUE FIN is a steel vessel owned and operated at all times relevant by Garber Brothers, Inc. (Garber). The BLUE FIN is 157 feet long, 36 feet broad, and twelve feet deep. Diesel engines power her twin screws, and she is fitted with anchor chains and two Danforth bow anchors, each of 1000 pounds’ weight. Each anchor is raised and lowered by means of an electrically powered windlass at the bow. Union, in conjunction with its oil-drilling operations, took a time charter on the BLUE FIN to supply, among others, the MR. GUS II. The vessel first visited the MR. GUS II at the C platform location on August 20, 1978.

Around noon on September 12, 1978, the BLUE FIN arrived in the vicinity of the C platform to deliver supplies. The BLUE FIN’s captain, Jesse Pierre, radioed those on the platform; he was given no specific instructions as to whether to drop anchor on one side or the other of the platform. Captain Pierre came alongside the rig at approximately 1300 hours, mooring on the east side. The vessel let out some seven or so shots of chain (one shot equals 90 feet) in the process of dropping anchor; after mooring it took in some slack on the chain. The BLUE FIN put out port and starboard stern lines.

At 1830 hours, the port stern mooring line broke and was caught in the port propeller. Captain Pierre then decided to move to the west side of the platform due to the difficulties and the rough weather conditions. He notified those on the rig of his plan and proceeded to the position at which he assumed his anchor to be directly beneath him. The crew there attempted to raise the anchor. The effort failed. The anchor would not budge, and only about ten feet of chain were taken in. The crew attempted to pull up the anchor a total of three times; there was no give after taking in the initial ten feet of chain, and each time an attempt was made to lift the anchor the windlass circuit breaker kicked out. *834 Captain Pierre noted in his log: “1830. While swinging around & picking up anchor to move around to west side of Rig w/o engine (stb) Hung anchor in pipeline. Hang off lines broke from Rig Port Line in wheel (Port side) sea’s 4' to 6'.”

At 0830 hours the next morning (September 13), divers from the DIANNE McCALL, which had been notified of the trouble, arrived and freed the BLUE FIN’s port wheel. They were unable, however, to go to the bottom to inspect the anchor and determine the obstruction on which it was caught. However, the BLUE FIN once again attempted to raise its anchor at 1430 hours on September 13, and that attempt was successful.

The pipeline was inspected on September 16 and 17, 1978. Damage was noted, and a videotape of the pipeline was made on September 19. Some photographs were also taken.

Texas Eastern sued Garber, the BLUE FIN, and Union for the damage done to the pipeline. It alleged that the anchor of the BLUE FIN had caused that damage and that Union had been negligent in failing to warn the crew of the location or existence of the pipeline. Union filed a third-party complaint against Holt and his insurer, the Continental Insurance Company (Continental), claiming a duty on Holt’s part to indemnify Union against plaintiff’s claim. Union also filed a third-party complaint against Fluor, asserting that Fluor owed it a duty to protect plaintiff’s pipeline and that Fluor should therefore indemnify Union were Union found liable. Garber filed crossclaims against Union, Holt, Continental, and Fluor. Each party denied liability to any other party.

At the conclusion of the plaintiff’s case in chief, the Court dismissed all claims against Holt and Continental.

CONCLUSIONS OF LAW

This Court has jurisdiction over the subject matter of this litigation and all parties to it. 28 U.S.C. § 1333; 46 U.S.C. § 740.

Texas Eastern, as plaintiff, must at a minimum establish by a preponderance of the evidence that the anchor of the BLUE FIN caused the damage to the pipeline which is the subject of this litigation. Grace Line, Inc. v. United States Lines Company, 302 F.2d 933 (2d Cir. 1962), adopting opinion at 193 F.Supp. 664 (S.D. N.Y.1969) (Friendly, J.), citing Commercial Molasses Corporation v. New York Tank Barge Corporation, 314 U.S. 104, 62 S.Ct. 156, 86 L.Ed. 89 (1941). If evidence shows that there are other possibilities as to the cause of the damage which are equally consistent with that damage, no single one of these possibilities may be considered proved. Dreijer v. Girod Motor Company, 294 F.2d 549, 556 (5th Cir. 1961) (Wisdom, J.).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

South Central Bell Telephone Co. v. Merritt Dredging Co.
726 F. Supp. 1061 (S.D. Mississippi, 1989)
In re Nantucket Inc.
677 F.2d 95 (Customs and Patent Appeals, 1982)
Texas Eastern v. Garber Bros, Inc
677 F.2d 114 (Fifth Circuit, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
494 F. Supp. 832, 1980 U.S. Dist. LEXIS 9249, Counsel Stack Legal Research, https://law.counselstack.com/opinion/texas-eastern-transmission-corp-v-garber-brothers-inc-laed-1980.