Texas Eastern Transmission Corp. v. Barnard

285 F.2d 536
CourtCourt of Appeals for the Sixth Circuit
DecidedDecember 15, 1960
DocketNo. 14057
StatusPublished
Cited by7 cases

This text of 285 F.2d 536 (Texas Eastern Transmission Corp. v. Barnard) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Texas Eastern Transmission Corp. v. Barnard, 285 F.2d 536 (6th Cir. 1960).

Opinion

McALLISTER, Chief Judge.

Appellant, an interstate pipe-line company, entered into a contract with appellee owners of real estate, for a right-of-way over the latter’s property for the purpose of constructing a pipe-line thereon, and repairing and inspecting it. The contract provided that in case of differences between the parties, any controversy between them should be submitted to arbitration; that if either party should demand arbitration, and the other party should fail and refuse to designate an arbitrator within thirty days after writ[537]*537"ten request therefor, then the arbitrator ■designated by the party requesting arbitration should have the right to make an •ex parte determination.

Appellees, on August 7, 1958, following claims of damage to their property .as a result of excavations by the pipeline company, made a written request for .arbitration and gave notice of such request to appellant company, which received the notice on August 11, 1958. Appellees did not, however, publicly designate or identify the arbitrator they had •chosen until thirty days had expired after the date of their request. After receiving the notice of request for arbitration, .appellant delayed naming an arbitrator or replying to the request, while awaiting ■further notice from appellees indicating the name of the arbitrator they had selected. Appellant did not thereafter receive any notice from appellees identifying their arbitrator. However, on September 12, 1958, appellant company received notice from E. A. Crooks, informing it that he was the arbitrator for •appellees, and that he would hear the controversy on September 16, 1958, four •days thereafter. This notice had been mailed to appellant within three days of the expiration of the thirty-day period ■provided for designation of arbitrator "by the party receiving notice of request for arbitration — in this case, appellant company.

On the same day on which it had received notice from E. A. Crooks that he had been appointed arbitrator for appellees, and that he would hear the controversy four days thereafter, appellant company notified appellees of its appointment of Henry L. Jones as its arbitrator, and stated that Mr. Jones would meet with the arbitrator for appellees at the time and place specified by him for the purpose of designating a third arbitrator, such designation of a third arbitrator being provided for in the agreement for arbitration. On the day following .-appellant’s designation of its arbitrator .-and its oifer to meet with the arbitrator •of appellees in order to appoint a third arbitrator, counsel for appellees informed appellant that appellant’s letter appointing its arbitrator came too late. At the time that counsel for appellees sent this letter refusing to consider appellant’s appointment of its arbitrator, the thirty-day period for such selection by appellant had expired only seven days before. Appellees’ arbitrator, however', had not, at that time, proceeded to hear the controversy, and, according to his notice to appellant, was not going to do so for another three days, that is, on September 16, 1958. Appellant immediately proceeded to prepare a complaint in the District Court under Section 4 of the United States Arbitration Act, Title 9 U.S.C.A. § 1 et seq., seeking an order that the arbitration proceed as appellant claimed, in accordance with the contract of arbitration, rather than ex parte, as resolved upon by appellees.

However, appellees’ arbitrator, on September 16, 1958, proceeded to hear and dispose of the controversy without any participation therein by appellant’s arbitrator, or by appellant’s arbitrator and a third arbitrator, whom appellant wanted to appoint in agreement with appellees’ arbitrator. On the same day, by order dated September 16, 1958, and subscribed and sworn to on September 17, 1958, appellees’ arbitrator adjudged appellant to be liable for damages caused to appellees in the amount of $81,233.63 with interest at 6% to run from September 16, 1958, until paid.

At the hearings by the sole arbitrator, counsel for appellant company appeared and protested the procedure adopted by appellees as arbitrary and further objected to the holding of the hearing on the grounds, among others, that appellees, in giving notice of the arbitration, had failed to name their own arbitrator; that Mr. Crooks, as appellees’ arbitrator, had failed to notify appellant of the hearing on September 16, 1958, in time to permit adequate preparation by appellant; and that appellees had refused to permit appellant to appoint its arbitrator. Mr. Crooks, undeterred by these arguments, overruled all objections and proceeded to the hearing as above set forth. Appel[538]*538lant, accordingly, refused, at that time, to recognize the validity of the proceeding and declined to participate in the hearing, to avoid the charge, that might be made in the future, that it had waived the claimed irregularities.

After the findings of Mr. Crooks were made, appellant amended the complaint it had filed prior to the hearing before the sole arbitrator, seeking an order directing the arbitration to proceed in accordance with the agreement, instead of before a single arbitrator. In the amendment to its complaint, appellant set forth the proceedings held by Mr. Crooks, and sought to vacate them for various reasons, among them that Mr. Crooks refused to permit it to appoint an arbitrator; in failing to notify it of the hearing in time to permit adequate preparation ; in further refusing to permit, or to conduct, the arbitration in accordance with the terms of the arbitration agreement; and in conducting the hearing under the conditions above mentioned.

In answer to the amended complaint, appellees moved to dismiss, and upon motion by both parties for summary judgment, the District Court denied appellees’ motion to dismiss, and both motions for summary judgment. Thereafter, upon submission of the case on the pleadings, affidavits, and exhibits accompanying them, the District Court filed an opinion and, in a judgment in accordance therewith, denied all the claimed relief to appellant, and entered judgment on a counterclaim of appellees, which was based upon the September 16, 1958 awards of Mr. Crooks as sole arbitrator, which resulted in the entry of judgments in favor of appellees against appellant in the aggregate amount of $81,233.63 with interest to run from September 16, 1958.

The basis of the judgment of the District Court, in so far as here relevant, was that appellant had not appointed its arbitrator, in accordance with the terms of the contract of arbitration, within thirty days after it had received from appellees notice of demand for arbitration; that because of its default in not appointing its arbitrator within the thirty-day period, it was not entitled to appoint one-thereafter; and that the sole arbitrator appointed by appellees acted properly in: proceeding to a hearing and disposition of the controversy, without permitting-the participation of the arbitrator appointed by appellant after the thirty-day period, but which appointment had been-made before the hearing.

Appellant submits that it complied! with the arbitration contract, and that the arbitrator wrongfully refused to permit its arbitrator to participate in the-selection of a third arbitrator and to engage in the hearing. It claims that while-it may have failed to appoint its arbitrator within thirty days of appellees’ written request for arbitration, it did not. refuse to do so, and that the arbitration-agreement only provides: “If either party shall demand arbitration and the other-party shall fail and refuse

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carter v. Cathedral Avenue Cooperative, Inc.
658 A.2d 1047 (District of Columbia Court of Appeals, 1995)
Employers Insurance of Wausau v. Jackson
505 N.W.2d 147 (Court of Appeals of Wisconsin, 1993)
In MATTER OF ARBITRATION BETWEEN EMPLOYERS INS. OF WAUSAU v. Jackson
505 N.W.2d 147 (Court of Appeals of Wisconsin, 1993)
John M. King, and v. Ben T. Stevenson, And
445 F.2d 565 (Seventh Circuit, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
285 F.2d 536, Counsel Stack Legal Research, https://law.counselstack.com/opinion/texas-eastern-transmission-corp-v-barnard-ca6-1960.