Texas Co. v. Alamo Cement Co.

168 S.W. 62, 1914 Tex. App. LEXIS 1110
CourtCourt of Appeals of Texas
DecidedApril 8, 1914
DocketNo. 5249.
StatusPublished
Cited by4 cases

This text of 168 S.W. 62 (Texas Co. v. Alamo Cement Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Texas Co. v. Alamo Cement Co., 168 S.W. 62, 1914 Tex. App. LEXIS 1110 (Tex. Ct. App. 1914).

Opinion

MOURSUND, J.

We adopt appellant’s ■statement of the case:

“On June 4, 1912, appellant filed suit against appellee on a verified account, seeking to recover of appellee $336, the price of three car loads of fuel oil alleged to have been sold and delivered by appellant to appellee at the special instance and request of appellee, one car load on July 6th, one on July 9th, and one •on July 12th, all in the year 1910.
“On June 19, 1912, appellee filed its original answer in the suit, consisting of a general demurrer and general denial.
“On July 2, 1912, appellee filed its first amended original answer, consisting of a general demurrer, a general denial, and a counterclaim. The special answer setting up the counterclaim alleged, in substance, that on or about July 1, 1910, appellant and appellee made a ■contract, by the terms of which appellant bound itself to furnish to appellee all the fuel oil that appellee would need for a period of six months beginning on July 6, 1910, free on board the cars at the Galveston, Harrisburg & San Antonio tracks in San Antonio, Texas, and ap-pellee was to pay for said oil at the price of $1.05 per barrel; and that, in compliance with said contract, appellant delivered the said three car loads of oil; but that appellant refused to ship to appellee any more oil, and, by reason thereof, appellee was compelled to procure the balance of the oil it needed during said period of six months, 28 car loads, from other sources, at $1.09 per barrel, which price, appellee alleged, was the market price of oil per barrel during the remainder of said period in said city of San Antonio. Appellee attached to its said-amended original answer an itemized statement showing the. dates, quantities, and prices of oil purchased by it during the remainder of said period aggregating 4,741.20 barrels. Appellee alleged that it had been damaged by reason of the premises in the total sum of $237.06, and prayed that said amount be allowed to it as an offset and credit.
“On August 27, 1913, appellee filed its second amended original answer in the suit, which also consisted of a general demurrer, a general denial, and a special answer setting up a counterclaim. This counterclaim was substantially in most respects the same as that contained in its first amended original answer, but claimed that the quantity of oil it had been compelled to purchase from other sources during said period of six months was 30 ear loads, aggregating 5.088.58 barrels, and averred its damages to be the sum of $254.42; and said special answer contained additional allegations to the effect that, at the time the contract was made, appellee owned and operated a Portland cement factory; that in operating said plant it was necessary to have a car load of fuel oil every third day, or shut down the operation of the plant; and that, when the plant was shut down, the ‘expenses of employed help would still have to be paid, as the employed help could not be laid off without entirely disorganizing the force and occasioning it greater loss’; all of which appellee alleged appellant was informed of and knew when the contract was made. Appellee alleged that it used due diligence to procure oil from other sources as soon as appellant refused to ship any more oil, but, notwithstanding this, appellee was compelled to shut down its plant for want of a supply of fuel oil for a period of eight days from July 17, 1910, until July 25, 1910, and it was compelled to pay its said employed help while they were thus idle the sum of $170.10; and appellee further alleged that it was making a profit of $50 a day operating its said plant when the same was thus shut down, and would have continued to- make said profit during said eight days had appellant furnished it oil as it had bound itself to do. Appellee sought to recover of appellant all of said alleged damages aggregating $854.52.
“Appellant, in reply to the second amended original answer of appellee, filed its first supplemental petition on September 11, 1910, specifically denying that any such contract as that alleged by appellee had ever been made by the parties; pleading the statute of limitations of two years in bar; specifically denying that appellee had ever suffered the special damages alleged by it; and pleading the statute of limitations of two years in bar of said special damages.
“Appellee, on September 13, 1913, filed its first supplemental answer, specifically denying that its said counterclaims were barred by the statute of limitations.
“A verdict was rendered by the jury on special issues submitted by the court; and, on October 25, 1913, a judgment was rendered by the court on this verdict awarding to appellee a recovery against appellant of the net sum of $43.92, with interest from that date at the rate of 6 per cent, per annum -and all costs.”

n,2] By the first assignment of error appellant contends that the item of $170, allowed appellee as damages caused by having to pay salaries of employés during the time the cement works were shut down on account of having no fuel oil, was barred by limitation. To this contention appellee answers that the contract breached by appellant was a written contract. It does not appear that the question was submitted to the jury whether a written contract was entered into by the parties. Appellee, it seems, did not feel that such question could result in any benefit, because no request was made for its submission. However, the following question was submitted:

Question 5: “After the written instrument, dated July 5, 1910, was signed by the Alamo Cement Company, was such written instrument accepted and acted on as a binding written agreement by the Texas Company?”
This was answered, “Yes.”

Question No. 5, requested by appellant, was also submitted, readifig as follows:

“The undisputed evidence shows that the Tex- ■ as Company shipped to the Alamo Cement *65 Company three car loads of fuel oil. "Were these car loads of ‘fuel oil shipped by the Texas Company to the Alamo Cement Company in recognition of the verbal agreement, iE any, or were they shipped to supply the immediate demands of the Alamo Cement Company in the belief upon the part of the Texas Company that the Alamo Cement Company would execute a written contract?”

This was answered: '“One car on verbal contract; two cars on written contract.”

This answer cannot be taken as a finding that the last two cars were shipped in acceptance of the written contract. The question did not call for any such answer, and, construing the answer in connection with the question, it must be found that the jury decided that one car was shipped in recognition of a verbal contract, and two in the belief that the Alamo Cement Company would execute a written contract. The question first stated, however, directly presents the question whether the written instrument was accepted and acted upon by appellee as a binding contract, and appellee contends that the affirmative answer thereto is equivalent in law to a finding that a written contract was made. Appellant excepted to this issue on several grounds, one of which is that the same does not submit the ultimate fact whether a written contract was made, but merely an evidentiary fact.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stevenson v. Wilson
130 S.W.2d 317 (Court of Appeals of Texas, 1939)
Keen & Woolf Oil Co. v. Fulenwider
284 S.W. 322 (Court of Appeals of Texas, 1926)
El Paso Times Co. v. Fuller
215 S.W. 113 (Court of Appeals of Texas, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
168 S.W. 62, 1914 Tex. App. LEXIS 1110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/texas-co-v-alamo-cement-co-texapp-1914.