Tessier's, Inc. v. Secretary of Labor

6 F.4th 777
CourtCourt of Appeals for the Eighth Circuit
DecidedJuly 22, 2021
Docket20-2359
StatusPublished

This text of 6 F.4th 777 (Tessier's, Inc. v. Secretary of Labor) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tessier's, Inc. v. Secretary of Labor, 6 F.4th 777 (8th Cir. 2021).

Opinion

United States Court of Appeals For the Eighth Circuit ___________________________

No. 20-2359 ___________________________

Tessier’s, Inc.

lllllllllllllllllllllPetitioner

v.

Secretary of Labor

lllllllllllllllllllllRespondent ____________

Petition for Review of an Order of the Occupational Safety & Health Review Commission ____________

Submitted: May 13, 2021 Filed: July 22, 2021 ____________

Before COLLOTON, WOLLMAN, and KOBES, Circuit Judges. ____________

WOLLMAN, Circuit Judge.

Tessier’s, Inc. employee Cameron Puepke was modifying a hole cover on the roof of an unfinished building when the cover collapsed, causing Puepke to fall twenty-two feet to the floor below. The Occupational Safety and Health Administration (OSHA) issued a citation against Tessier’s under 29 C.F.R. § 1926.501(b)(4)(i), for failing to protect its employees from falling through holes. An Occupational Safety and Health Review Commission administrative law judge (ALJ) affirmed the citation, which the Commission declined to review. Tessier’s filed a petition for review of the resulting final order, arguing, among other things, that the ALJ erred in finding that Tessier’s employees removed a one-foot-by-three- foot section of the cover before it collapsed. We deny the petition.

Layton Construction and Gustafson Construction Corporation (Layton- Gustafson) together served as the general contractor for the construction of an orthopedic and sports medicine facility in Rapid City, South Dakota. A Layton- Gustafson subcontractor hired Tessier’s to install the dry-side mechanical systems, i.e., air handling units, roof curbs, and ductwork for the HVAC systems.

Three air handling units were to be installed in Area C of the roof, in which five holes had been created to accommodate the units. The holes were framed by L- shaped bent steel plates, which were attached to the building’s I-beams. Layton- Gustafson carpenter Paul Garcia measured the holes, assembled two-by-four wood frames in the shape of a box, and then screwed pieces of plyform (a type of sturdy plywood) or plywood on top of each box to complete the covers, which were thereafter placed over the holes. The two-by-four frames rested outside the bent steel plates and were affixed to the structure with deck screws.

Garcia was instructed to rebuild the covers so that they would not interfere with the pouring of the roof’s concrete floor. He disassembled the covers, rebuilt the frames so that they would fit tightly inside the steel plates, and reattached the plywood. The plywood of the rebuilt covers served as the load-bearing surfaces, with one-half inch to one inch of plywood extending over the plates framing the holes. The frames themselves were not affixed to the structure. The word “hole” was emblazoned on each cover in florescent spray paint.

-2- Tessier’s began installing roof curbs—pieces of galvanized tin—in Area C on March 8, 2018. The curbs were designed to fit around the holes where the air handling units would be installed. While placing the curbs, the Tessier’s crew discovered that the covers’ excess plywood overhang prevented the curbs from sitting flush against the bent steel plates.

To remedy the plywood-overhang problem, Puepke and fellow Tessier’s employee Jason Fenner decided to trim the covers’ edges while the covers were still in place. They believed that the covers’ frames were affixed to the building’s structural steel, but did little to investigate and thus did not discover that the plywood alone constituted the load-bearing surface of each cover. After relaying the cover- modification plan to the foreman, Fenner used a reciprocating saw to cut a small strip from a short end of the first cover, which stayed in place.

The hole for Air Handling Unit Number 4 was three feet wide and eight feet long. Puepke and Fenner removed a one-inch strip from a short end of the cover to install the curb. The Secretary maintains that they also removed a one-foot-by-three- foot section of the cover, which Tessier’s disputes. Fenner and Puepke thereafter used a screw gun to begin removing screws from a one-and-one-half inch wide strip of plywood on a long side of the cover.

Puepke rested his hand on the middle of the cover. When he leaned onto it, the cover collapsed like “a hinge” or “a tripod with only two legs,” causing Puepke to fall to the floor below. He suffered serious injuries, including skull fractures, broken bones, and a fractured pelvis. Fenner was pulled to safety by coworkers and was not injured.

The workers who witnessed the fall completed incident reports and made a diagram of the incident. Their reports did not indicate whether the one-foot-by-three- foot section of plywood had been removed. A Layton-Gustafson supervisor reported

-3- that “[p]art of the cover was removed and while attempting to remove more plywood, the hole protection gave out.” A Layton-Gustafson project manager made a computer-generated version of the diagram, which suggested that a one-foot-by-three- foot section had been removed.

OSHA Compliance Safety and Health Officer Anthony Castillo inspected the worksite during his investigation of Puepke’s fall. Most of the collapsed cover was located on the second floor, where it had landed after falling through the hole. A one- foot-by-three-foot section of the cover remained on the roof, however. It was found on the roof itself, outside the curb and next to the one-inch strip of trim that Puepke and Fenner had removed. The frame beneath that section revealed a “volcano effect” on some screw holes, indicating that the screws may have been forcibly ripped out of the frame and not removed by a screw gun.

As earlier stated, Tessier’s was cited for failing to protect its employees from falling through holes. Following a three-day trial, the ALJ found that Tessier’s had committed the violation. The ALJ’s decision became the Commission’s final order in light of its declination of review. See 29 U.S.C. § 661(j).

On petition for review, we uphold the Commission’s factual findings that are “supported by substantial evidence on the record considered as a whole.” Omaha Paper Stock Co. v. Sec’y of Lab., 304 F.3d 779, 782 (8th Cir. 2002) (quoting 29 U.S.C. § 660(a)). “Substantial evidence is relevant evidence that a reasonable person might accept as adequate to support a conclusion.” Id. We uphold “the Commission’s legal conclusions unless they are ‘arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.’” Id. (quoting 5 U.S.C. § 706(2)(A)).

Tessier’s contends that the citation was not validly issued. To establish that the citation was validly issued, the Secretary was required to prove by a preponderance

-4- of the evidence that, among other things, the cited standard applied to the condition. Astra Pharm. Prods., Inc., 9 BNA OSHC 2126, 2129 (No. 78-6247, 1981); see 29 U.S.C. § 654(a)(2) (requiring employers to “comply with occupational safety and health standards promulgated under this chapter”). The standard here provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Omaha Paper Stock Company v. Secretary of Labor
304 F.3d 779 (Eighth Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
6 F.4th 777, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tessiers-inc-v-secretary-of-labor-ca8-2021.