Teska v. Potlatch Corp.

184 F. Supp. 2d 913, 2002 U.S. Dist. LEXIS 2271, 2002 WL 200224
CourtDistrict Court, D. Minnesota
DecidedJanuary 2, 2002
DocketCiv.00-418(RLE)
StatusPublished
Cited by8 cases

This text of 184 F. Supp. 2d 913 (Teska v. Potlatch Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Teska v. Potlatch Corp., 184 F. Supp. 2d 913, 2002 U.S. Dist. LEXIS 2271, 2002 WL 200224 (mnd 2002).

Opinion

MEMORANDUM ORDER

ERICKSON, United States Magistrate Judge.

I. Introduction

This matter came before the undersigned United States Magistrate Judge pursuant to the consent of the parties, as authorized by Title 28 U.S.C. § 636(c), upon the Defendant’s Motion in limine, and its Motion for Summary Judgment. A Hearing on the Motions was conducted on July 26, 2001, at which time the Plaintiffs George M. Teska, and Darlene Teska, appeared by Robert C. Bell, Esq., and the Defendant Oscar J. Boldt Construction Co. (“Boldt”) appeared by Steven W. Schneider, Esq.

For reasons which follow, we grant the Defendant’s Motion in limine, as well as its Motion for Summary Judgment.

*916 II. Factual and Procedural History

The Plaintiffs commenced this action after George M. Teska (“Teska”) was injured, at work, on October 28, 1999. At that time, Teska was working as a boilermaker foreman on a project for the Pot-latch Corporation (“Potlatch”). 1 Potlatch was modernizing its oriented strand board facility, which is located in Cook, Minnesota, and it had hired Boldt as the general contractor. Boldt then subcontracted with The Jamar Company (“Jamar”) for certain mechanical installations. See, Exhibit 1 to Affidavit of Steven W. Schneider (subcontract agreement between Boldt and Jamar). Teska was employed by Jamar. 2

On October 28, 1999, a column was to be installed in the heat source area of the project. The column was a seventeen foot I-beam, and the installation of the column was Jamar’s responsibility. See, Deposition of Robert Larson, at 14, Exhibit 2 to Affidavit of Steven Schneider (“Larson Deposition”). As the column was to be positioned vertically, it was necessary to employ a crane so as to move the column into place. For that purpose, Jamar requested the use of a large crane that had been maintained on the site by Boldt. Pursuant to the subcontract agreement, Boldt also provided the crane operator, who was Richard A. Fuglie (“Fuglie”), in conjunction with the crane. See, Exhibit 1 to Affidavit of Steven W. Schneider.

The process of securing the column, so that it might be lifted by the crane, is known as “rigging,” and it was the boilermakers’ responsibility to rig the column at issue here. See, Larson Deposition, at 14. According to Robert Larson (“Larson”), who was Jamar’s superintendent on the site, it was his responsibility, as well as that of Teska, to ensure that the rigging was performed properly, and he had discussed the safest way to rig the column, with Teska, at some time prior to October 28, 1999. Id. at 8-9. Larson believed that it would be “advantageous” to rig the column with a shackle inserted in a hole at the top of the beam, and Teska apparently agreed. Id.

Although Teska generally recalls his conversation with Larson, he does not recall communicating Larson’s instruction, concerning the use of a shackle, to the remaining members of the boilermaker crew. See, Deposition of George M. Teska, at 155-56, Exhibit 4 to Affidavit of Steven W. Schneider (“Teska Deposition, Exhibit 4”). Moreover, the boilermaker crew, which was comprised of Timothy Sauter (“Sauter”), and David Kangas (“Kangas”), have testified that they had received no instructions as to how to rig the column. See, Deposition of David Kangas, at 13-14, Exhibit 5 to Affidavit of Steven W. Schneider (“Kangas Deposition”); Deposition of Timothy Sauter, at 15, Exhibit 6 to Affidavit of Steven W. Schneider (“Sauter Deposition”).

Kangas eventually rigged the column for the lift, using a two-inch nylon sling as his primary rigging device. See, Kangas Deposition, at 13. Initially, he attempted to *917 rig the column using a “double-wrap,” but after the nylon sling was extended, it became apparent that the top of the column would come into contact with the “headache ball,” which is a part of the crane-lifting mechanism, id. at 14-15, and would cause problems in placing the column as the column would not hang perpendicular to the ground. He then rigged the column with a “single wrap.” Id. After rigging the column, Kangas consulted Sauter about when they would be ready for the lift, and Sauter questioned whether a shackle should be used for the rigging. See, Sauter Deposition, at 15. The two men then decided, however, that a shackle was not necessary. Id. at 17. Teska has described both Kangas, and Sauter, as well as himself, as being “all experienced journeymen,” Teska Deposition, at 35, who would have known the proper way to rig the column on account of their experience as boilermakers. Id. at 56.

After the column was rigged, Fuglie was called upon to operate the crane so as to lift the column into place. A portion of the lift, that Fuglie had to make, was a “blind lift.” See, Deposition of Richard Fuglie, at 16, Exhibit 7 to Affidavit of Steven W. Schneider (“Fuglie Deposition”). In other words, there was a period of time during the lift when Fuglie was unable to see the column. Id. This “blind” period came at the end of the lift, when he was to position, and place, the column in its designated location. Id. To compensate for Fuglie’s inability to observe the column during the “blind” portion of the lift, the boilermakers, who were Jamar employees, used hand signals to direct Fuglie. Id. Teska located himself at the point where the column was to be positioned, and secured, into place.

Once the column was close to Teska, he then relayed signals to Sauter, see, Deposition of George Teska, at 43, Exhibit S to Affidavit Steven W. Schneider (“Teska Deposition, Exhibit 3”), who had positioned himself where he could see both Teska and Kangas. See, Sauter Deposition, at 20. Sauter and Fuglie could not see each other, however. Id.; Fuglie Deposition, at 17. As a consequence, Sauter relayed his signals to Kangas, who then passed those signals on to Fuglie. See, Sauter Deposition, at 20. Neither Kangas nor Fuglie could see Teska. See, Kangas Deposition, at 21; Fuglie Deposition, at 17. As the column was brought into position above Teska, and just before Fuglie began to lower the column into position, the column slid through the nylon sling, and fell to the ground. In the process of falling, the column caused the scaffolding, on which Tes-ka was standing, to collapse. During the course of that collapse, Teska suffered numerous injuries, for which he initiated this action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lundstrom v. Maguire Tank, Inc.
509 F.3d 864 (Eighth Circuit, 2007)
Hamberg v. Sandia Corp.
2007 NMCA 078 (New Mexico Court of Appeals, 2007)
North Star Mutual Insurance v. Zurich Insurance
269 F. Supp. 2d 1140 (D. Minnesota, 2003)
Medalen v. Tiger Drylac U.S.A., Inc.
269 F. Supp. 2d 1118 (D. Minnesota, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
184 F. Supp. 2d 913, 2002 U.S. Dist. LEXIS 2271, 2002 WL 200224, Counsel Stack Legal Research, https://law.counselstack.com/opinion/teska-v-potlatch-corp-mnd-2002.