Terrebonne Concrete, LLC v. CEC Enterprises, LLC

76 So. 3d 502, 2010 La.App. 1 Cir. 0072, 2011 La. App. LEXIS 977, 2011 WL 3610424
CourtLouisiana Court of Appeal
DecidedAugust 17, 2011
DocketNos. 2011 CA 0072, 2011 CA 0073, 2011 CA 0074, 2011 CA 0075, 2011 CA 0076, 2011 CA 0077, 2011 CA 0078, 2011 CA 0079
StatusPublished
Cited by32 cases

This text of 76 So. 3d 502 (Terrebonne Concrete, LLC v. CEC Enterprises, LLC) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Terrebonne Concrete, LLC v. CEC Enterprises, LLC, 76 So. 3d 502, 2010 La.App. 1 Cir. 0072, 2011 La. App. LEXIS 977, 2011 WL 3610424 (La. Ct. App. 2011).

Opinion

GAIDRY, J.

l-jThe corporate president of a construction contractor appeals a judgment rendered in favor of his company’s customer and against him personally based upon his alleged fraud in delaying payment to subcontractors after receiving progress payments from the customer. For the following reasons, we reverse the judgment against the appellant.

FACTUAL BACKGROUND AND PROCEDURAL HISTORY

These consolidated actions arise from a contract of January 18, 2007, between the appellee, CEC Enterprises, L.L.C. (CEC), and Terri Matthews, Inc. (TMI), a construction contractor, for the construction of a restaurant building for CEC in Hou-ma, Louisiana. The appellant, Terri Matthews, is the president and a substantial shareholder of TMI, an Oklahoma-based corporation licensed to do business in Louisiana. At the time of the execution of the contract, Mr. Matthews owned 35.1% of the TMI’s corporate stock; his wife, Carolyn Matthews, owned 34.9%; Ron Mittel-stedt, TMI’s vice-president of operations, [506]*506owned 20%; and Jason Elkins, its senior project manager, owned 10%.1

TMI was the lower of two bidders for the construction contract. Its original bid was for the fixed amount of $901,471.00. The contract was a standard AIA (American Institute of Architects) form agreement between an owner and a contractor. It provided that for the stated amount, TMI would substantially complete the work no later than 115 days from the date of commencement established in a “notice to proceed.” During the course of the project, regular periodic progress payments would be made to TMI after application to the supervising architect, Carl P. Blum, and certification of |4payment by him. The project manual, forming part of the contract documents, required TMI to “promptly pay each [subcontractor, upon receipt of payment by the [o]wner,” an appropriate amount from the progress payments, based upon each subcontractor’s portion of the work done up to that time.

The contract further provided that TMI and its surety would be liable for liquidated damages of $500.00 per day for each day of delay in substantial completion and that TMI would receive bonus payments of $500.00 per day for each day for which substantial completion was completed in advance of the scheduled date. Clint Col-gin, CEC’s owner, was designated as the project owner’s representative and executed the contract on CEC’s behalf. Carl Blum was listed in the contract as the supervising architect for CEC. Ron Mit-telstedt was designated as the contractor’s representative in the contract, and Jason Elkins executed the contract on behalf of TMI.

The supervising architect sent TMI the “notice to proceed” on February 5, 2007, with an effective date of February 7, 2007. The corresponding completion date was June 2, 2007. TMI contracted with various subcontractors and material suppliers for the project. Mr. Matthews, as TMI’s president, initially was not actively involved in the daily operations of the project and did not sign any of the subcontracts, either in a representative or personal capacity.

Because TMI’s low bid was higher than CEC’s construction budget, the parties negotiated a change order reducing the amount of the contract by $123,601.00 to $777,870.00. TMI was represented by Mr. Mittelstedt in those negotiations. The change order was effective on February 8, 2007, the date it was signed by Mr. Elkins on behalf of TMI. Work commenced, and |fiCEC made an initial progress payment to TMI in the net amount of $92,673.00 on March 15, 2007. On April 25, 2007, a second progress payment in the net amount of $209,989.80 was made.

In March 2007, Mr. Mittelstedt left TMI’s employment to start his own competitive business, having recruited 50-70% of TMI’s employees and acquiring 60-70% of TMI’s customer base. That circumstance and the status of other projects undertaken by TMI disrupted TMI’s financial situation and liquidity and forced Mr. Matthews to assume a more active role in corporate management and operations.

In late April 2007, CEC began to receive complaints of nonpayment from various subcontractors and material suppliers. Upon learning of TMI’s failure to pay subcontractors and suppliers following the progress payments, Mr. Blum, the supervising architect, contacted representatives [507]*507of TMI to discuss the situation. The parties mutually agreed that in order to facilitate the completion of the stalled project, CEC would pay various subcontractors and suppliers directly in lieu of making further progress payments to TMI. The project was eventually completed some 240 days after its original scheduled date of substantial completion.

Terrebonne Concrete, L.L.C., a supplier of ready-mix concrete for the project, filed suit against CEC on April 25, 2008, for an open account and recognition of its materi-alman’s privilege on the property. Six other civil actions were instituted against CEC and TMI by various subcontractors and suppliers involved in the project, resulting in liens being recorded against the property. CEC also eventually filed suit against TMI and Mr. Matthews for damages based upon breach of contract, including liquidated damages, and based upon their alleged fraud. All of the actions were consolidated for trial.

|fiThe trial of the consolidated actions was conducted on January 26, 27, and 28, 2010. At the conclusion of the trial, the trial court issued its ruling and oral reasons for judgment. In addition to rendering judgment in favor of the various subcontractors and material suppliers, the trial court rendered a separate judgment in the action filed by CEC against TMI and Mr. Matthews, finding both defendants liable to CEC. The trial court’s judgment in that regard was signed on March 1, 2010, holding TMI liable to CEC for (1) $120,000.00 in liquidated damages for construction delay, per the terms of the contract; (2) $50,000.00 in statutory civil penalties for failure to apply progress payments to settle the claims of material suppliers and laborers, baséd upon the provisions of La. R.S. 9:4814; (3) $60.00 for the cost of recordation of the certificate of substantial completion; (4) $25,000.00 for attorney fees; (5) $24,000.00 for the cost of settlement with one subcontractor, who assigned its rights against TMI to CEC; (6) judgment for indemnity for all of the cross-claims and third-party demands asserted by CEC in the other consolidated actions; and (7) all costs and legal interest. The court also rendered judgment in favor of CEC and against Mr. Matthews for the sum of $100,000.00, based upon “a finding of fraud on the part of Terri Matthews as shareholder of Terri Matthews, Inc.”

Mr. Matthews appeals the judgment award rendered against him personally.2

ASSIGNMENTS OF ERROR

Mr. Matthews assigns the following error by the trial court:

Because the evidence does not demonstrate that Terri Matthews misrepresented the corporation’s financial condition to CEC, the trial court erred in finding that Matthews committed fraud.

Additionally, because CEC failed to demonstrate that Matthews commingled his personal funds with that of TMI, the trial court erred in piercing the corporate veil.

DISCUSSION

A corporation, as a juridical person, is separate and distinct from its members or shareholders. See La. C.C. art. 24 and Riggins v. Dixie Shoring Co., Inc., 590 So.2d 1164, 1167 (La.1991).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Petrucci v. Christina
E.D. Louisiana, 2023
Robert Webb Digirolamo
M.D. Louisiana, 2020
Vince ex rel. Southland Express, LLC v. Metro Rediscount Co.
259 So. 3d 1221 (Louisiana Court of Appeal, 2018)
Lloyd's Syndicate 457 v. Am. Global Mar. Inc.
346 F. Supp. 3d 908 (S.D. Texas, 2018)
TMJ Grp. LLC v. IMCMV Holdings Inc.
311 F. Supp. 3d 834 (E.D. Louisiana, 2018)
Monroe v. McDaniel
207 So. 3d 1172 (Louisiana Court of Appeal, 2016)
Simmons v. Luba Workers' Comp.
206 So. 3d 397 (Louisiana Court of Appeal, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
76 So. 3d 502, 2010 La.App. 1 Cir. 0072, 2011 La. App. LEXIS 977, 2011 WL 3610424, Counsel Stack Legal Research, https://law.counselstack.com/opinion/terrebonne-concrete-llc-v-cec-enterprises-llc-lactapp-2011.