Terral v. Bearden
This text of 338 So. 2d 141 (Terral v. Bearden) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Thomas R. Terral, Jr. d/b/a Omega Engineering, Plaintiff-Appellee,
v.
Oscar BEARDEN, Defendant-Appellant.
Court of Appeal of Louisiana, Second Circuit.
*142 Kidd, Katz & Strickler by Paul H. Kidd, Monroe, for defendant-appellant.
Baker, Culpepper & Brunson, Jonesboro by Joseph A. Cusimano, Jr., Farmerville, for plaintiff-appellee.
Before HALL, MARVIN and JONES, JJ.
MARVIN, Judge.
Defendant appeals from a judgment awarded plaintiff under quantum meruit for a survey made in 1974 by plaintiff on verbal orders of defendant. Defendant contends the trial court erred because plaintiff brought suit on the oral contract and did not alternatively seek recovery under quantum meruit, contrary to the holding of Edington Drilling Company v. Yearwood, 239 La. 303, 118 So.2d 419 (1960).
The survey of defendant's lands arose out of three telephone conversations between the parties litigant. Plaintiff contends he quoted defendant hourly prices of $15 for preparatory (office) work and $21 for field work, assuming that the lands were in one tract and had an established corner on which to base the survey, and estimating that it would take two and one-half days to do the job.
Defendant admits he directed plaintiff to make the survey, but only after plaintiff "guaranteed" to do the work for a fixed price figured on the basis of two and onehalf days at $156 per day, or $390.[1]
As it turned out, defendant's property was not one tract, but two separate tracts, one of twenty acres and the other of eight acres. The terrain of the properties was not uniform or even and there was no established corner. Plaintiff and his crew spent four and one-half hours in preparation work and 63 hours in the field. Plaintiff and his crew worked one and one-half or two days traversing rough terrain and cutting through thickets to reach one of defendant's corners from an established corner some two thousand feet away. Defendant's tracts were in an isolated area. The survey began on Friday, August 23, and was completed on Thursday, August 29, at which time plaintiff telephoned defendant about the completion. On Wednesday, August 28, defendant walked around the surveyed lines with one of plaintiff's crew. Almost 10,000 linear feet were surveyed and staked. The lower court also considered plaintiff's expenses for stakes, measuring tape and general overhead, in approving as reasonable the hourly rates mentioned.
Plaintiff testified that when he obtained a copy of defendant's deed and learned there were two tracts involved, he informed defendant that it was going to take longer than two and one-half days to make the survey. Plaintiff said defendant responded by telling him to proceed with the survey and to report his progress to defendant on a daily basis.
The defendant admitted he learned from plaintiff that his property was in two tracts; that he heard from the plaintiff after the survey started and before the surveyors reached defendant's corner; that defendant knew the survey started on a Friday (August 23) and that defendant walked the lines on the following Wednesday (August 28). Defendant admits receiving telephone calls from plaintiff on the nights of Saturday (August 24), Sunday (August 25), Monday (August 26), and Tuesday (August 27) about the progress of the survey team. Defendant also admits knowing on Wednesday (August 28) how many days the surveyor had been working.
The lower court said:
". . . [I]t is understandable that, based upon preliminary discussions and *143 the hypothetical situation posed by plaintiff, defendant might justifiably have assumed that the surveying work would take no longer than 2½ days. However, if this was his understanding, it defies logic that he did not raise this issue when informed that plaintiff's crew took two full days just to reach a corner on defendant's property from which they could run his lines." Opinion, p. 3.
The lower court noted plaintiff's testimony that he told defendant before the survey was begun ". . .in surveying you can't contract [at a fixed price] because it depends on what kind of terrain you run into and how far you have to run and everything else." (Material in brackets supplied). The defendant was or should have been aware that the two and one-half days mentioned was only an estimate and that he was going to be charged on the basis of how long it would take for the survey to be completed. It is not shown that time was of the essence to defendant for the survey to be completed and we can only conclude that the two and one-half days was interjected into the parties negotiations merely as an estimate. As the survey progressed, defendant became aware by telephone and visual inspection that it was taking longer than two and one-half days.
The trial court concluded there was "no meeting of the minds . . . as to the total cost of the survey . . ." We do not dispute this conclusion because the surveying was not yet begun. We find, however, that before the work began, there was a meeting of the minds that the total cost would be computed on a time or hourly basis after the survey was completed unless defendant ordered the surveyors to cease working before completion. Otherwise, there would have been no necessity for the nightly telephone calls from plaintiff to defendant.
Even assuming arguendo, that there was no meeting of the minds on the hourly rate or rates to be charged does not avail defendant. Here, the plaintiff staked at 100 foot intervals the boundaries of defendant's two tracts and defendant, with knowledge of plaintiff's efforts, has benefited thereby. The circumstances here are appropriate for application of the doctrines of quasi contract and quantum meruit notwithstanding the absence of a plea therefor. In this respect defendant relies on Edington Drilling Company, cited supra (1960), and Josey v. Howard Lbr. & Supply Company, 232 So.2d 119 (La.App. 2d Cir. 1970).
Other cases which should be considered are National Crankshaft Co. v. Natural Gas Industries, Inc., 246 La. 395, 165 So.2d 1 (1964); Brooks v. Britnell, 183 So.2d 434 (La.App. 2d Cir. 1966); and Duggan Machine Co. v. Consolidated Well Servicing Co., Inc., 187 So.2d 124 (La.App. 2d Cir. 1966).
Edington arose before the Code of Civil Procedure became effective. It said:
"This plea cannot be granted because plaintiff seeks recovery only under its contract and not on a quantum meruit basis. The law is well settled that, when a plaintiff sues on a contract which is shown to have been breached by him, recovery may not be had in that action on a quantum meruit . . ., unless he has pleaded for such relief in the alternative." 118 So.2d 422. (citations omitted). Next came National Crankshaft in 1964. It said:
"[1]Although plaintiff's suit is based on the contract of sale of January 11, under the authority of Article 2164 of the Code of Civil Procedure the appellate court may render any judgment which is just, legal, and proper on the record on appeal." 165 So.2d 3, footnote 1.
Brooks and Duggan Machine Co., by this court in 1966, said:
"Under the provisions of the Louisiana Code of Civil Procedure an appellate court may grant relief on the basis of quantum meruit under a quasi contractual theory although such relief is not prayed for in an alternative demand. LSA-C.C.P. 2164; National Crankshaft Company v. Natural Gas Industries, Inc., supra; Brooks v. Britnell, La.App., 183 So.2d 434 (2nd Cir.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
338 So. 2d 141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/terral-v-bearden-lactapp-1976.