Tennessee Valley Authority v. Westinghouse Electric Corp.

69 F.R.D. 5, 18 U.C.C. Rep. Serv. (West) 945, 1975 U.S. Dist. LEXIS 14985
CourtDistrict Court, E.D. Tennessee
DecidedDecember 5, 1975
DocketCiv. No. 3-75-298
StatusPublished

This text of 69 F.R.D. 5 (Tennessee Valley Authority v. Westinghouse Electric Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Valley Authority v. Westinghouse Electric Corp., 69 F.R.D. 5, 18 U.C.C. Rep. Serv. (West) 945, 1975 U.S. Dist. LEXIS 14985 (E.D. Tenn. 1975).

Opinion

MEMORANDUM

ROBERT L. TAYLOR, District Judge.

This action was filed on October 20, 1975, by the Tennessee Valley Authority seeking declaratory and injunctive relief against defendant Westinghouse Electric Corporation for the repudiation of two contracts to supply nuclear fuel for two of T.V.A.’s electrical power plants.1 Before the Court is T.V.A.’s motion for partial summary judgment in its favor on Count II of its complaint on the ground that the complaint and the annexed affidavit of Erik Kvaven, the Contracting Officer on both contracts, demonstrate that there is no genuine issue as to any material fact and that T. V.A. is entitled to judgment as a matter of law. Rule 56, F.R.C.P.

The dispute between the parties is the result of a letter sent by Westinghouse to T.V.A. dated September 8, 1975, in which T.V.A. was informed that Westinghouse considered continuation of the two long-term nuclear fuel supply contracts to be “commercially impracticable.” Exhibit C to the Complaint. Westinghouse informed T.V.A. that certain unforeseeable events which had come about since the contracts were entered into prevented Westinghouse from performing about 80 per cent of its obligation to supply nuclear fuel to T.V.A. and that it was excused from such performance under the provisions of Section 2-615 of the Uniform Commercial Code.

Simply stated, T.V.A.’s motion for partial summary judgment is based on the following two contentions:

1. The Uniform Commercial Code is not applicable to the contracts in question here because there are specific contractual provisions governing the rights of the parties and because there is Supreme Court authority which controls the interpretation of these federal contracts; and,
2. the unforeseen price increases in uranium alleged by Westinghouse (and admitted by T.V.A. for purposes of the motion) do not constitute an excuse for nonperformance under the federal common law [7]*7doctrine of impossibility of performance.

Westinghouse opposes the motion on three grounds. First, that under modern legal principles the Uniform Commercial Code may be applied to federal contract disputes. Second, that the affidavits filed by Westinghouse in opposition to T.V.A.’s motion demonstrate that there are numerous disputed material facts in this case. Finally, that no decision which goes to the merits of the ease should be made by this Court until such time as the Judicial Panel on Multidistrict Litigation acts on its motion pursuant to 28 U.S.C. § 1407 to consolidate this case and some eleven or more similar cases for pretrial.2

T.V.A. relies on certain provisions in the contracts in question which it contends are controlling with regard to whatever right Westinghouse may have to be excused from performance under the contracts. The provisions provide as follows:

“Delays and Remedies. If the Contractor does not complete the contract or any portion thereof within the time specified, or if he assigns or encumbers any interest in it without prior written consent of TVA, or is thrown into receivership adjudicated a bankrupt, or does not prosecute the work, or any separable part thereof, with such diligence as, in the opinion of the Contracting Officer, will insure its completion within the time specified therefor, or fails to carry out any of his other obligations after written notice from TVA, then TVA by written notice to the Contractor may terminate the Contractor’s right to proceed with all or any part of the contract, and prosecute the same to completion by contract or otherwise, and may purchase similar materials or supplies in the open market or secure their manufacture and delivery by contract or otherwise, charging against the Contractor any excess cost occasioned TVA thereby; provided, that if the Contractor within 30 calendar days from the beginning of any delay notifies the Contracting Officer in writing of the causes of delay, the right of the Contractor to proceed shall not be terminated when all of the Contractor’s delay is due to causes beyond the Contractor’s control and without his fault, such as acts of God or of the public enemy, acts or omissions on the part of TVA, fires, unforeseeably severe weather or floods, epidemics, quarantines, strikes, freight embargoes, priorities ordered by the United States Government, or any act, delay, or failure to act by the Atomic Energy Commission in the issuance of permits and licenses, but excluding delays in issuance of AEC permits or licenses resulting from faulty designs by Contractor or submission of faulty information . . .”

The parties have directed their briefs primarily to the question of whether the common law doctrine of impossibility of performance or the Uni-, form Commercial Code doctrine of commercial impracticability should be considered the controlling federal common law rule.3 These efforts have been misdirected if the terms of the contract can be considered to have delineated the rights and liabilities of the parties in [8]*8the present controversy as contended by T.V.A. The threshold issue in this case, as the Court perceives it, is whether the “Delays and Remedies” provision of each contract is controlling. Neither the common law doctrine of impossibility of performance nor UCC § 2-615 will be applicable if the parties can be considered to have bargained for a greater or lesser liability. See, e. g., Carnegie Steel Co. v. United States, 240 U.S. 156, 36 S.Ct. 342, 60 L.Ed. 576 (1916); UCC § 2-615, Official Comment 8. For this reason, a determination of which rule represents the federal common law rule would be premature. We think that any analysis of the issues presented in this case must necessarily begin with the “Delays and Remedies” provision of each contract.

T.V.A. contends that the provision rejects the doctrine of commercial impracticability because Westinghouse “is excused only if ‘all’ its inability to perform is ‘. . . due to causes beyond the Contractor’s (Westinghouse) control and without his fault . . . ’ ” Thus, says T.V.A. the contracts adopt as the sole ground of excuse the federal common law test of impossibility of performance.

This interpretation of the “Delays and Remedies” provisions is not without difficulty. It appears from a careful examination of these provisions that they may be susceptible to a different interpretation. Specifically, the provisions state that if the Contractor fails to perform in a timely manner, is adjudicated a bankrupt, etc., then T.V.A. may terminate the Contractor’s right to proceed with all or any part of the contract. They further provide that if such a termination occurs, then T.V.A. may purchase the nuclear fuel on the open market and charge the Contractor with any excess cost occasioned thereby. T.V.A.’s right to terminate and cover on the open market, however, is qualified by an excuse clause. This clause essentially provides that T.V.A. will not have the right to terminate and cover when the delay is due to causes beyond the Contractor’s control and without its fault. Phrased another way, the excuse clause permits Westinghouse, under specified circumstances, to stay in the contract even though performance has been delayed.

It appears that the factual situation presented in this case may not be within the purview of these provisions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carnegie Steel Co. v. United States
240 U.S. 156 (Supreme Court, 1916)
Clearfield Trust Co. v. United States
318 U.S. 363 (Supreme Court, 1943)
Adickes v. S. H. Kress & Co.
398 U.S. 144 (Supreme Court, 1970)
In Re Four Seasons Securities Laws Litigation
362 F. Supp. 574 (Judicial Panel on Multidistrict Litigation, 1973)
Ross v. Great Northern Railway Co.
375 U.S. 823 (Supreme Court, 1963)
Ohio Turnpike Commission v. S. J. Groves & Sons Co.
375 U.S. 824 (Supreme Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
69 F.R.D. 5, 18 U.C.C. Rep. Serv. (West) 945, 1975 U.S. Dist. LEXIS 14985, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-valley-authority-v-westinghouse-electric-corp-tned-1975.