Tennessee Valley Authority v. United States

13 Cl. Ct. 692, 1987 U.S. Claims LEXIS 213, 1987 WL 4266
CourtUnited States Court of Claims
DecidedNovember 12, 1987
DocketNo. 513-87C
StatusPublished
Cited by11 cases

This text of 13 Cl. Ct. 692 (Tennessee Valley Authority v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Valley Authority v. United States, 13 Cl. Ct. 692, 1987 U.S. Claims LEXIS 213, 1987 WL 4266 (cc 1987).

Opinion

ORDER

NETTESHEIM, Judge.

After this case was transferred from the United States District Court for the Eastern District of Tennessee, defendant moved to dismiss plaintiff’s contract claim for lack of subject matter jurisdiction. Plaintiff has opposed, and argument has been held.

FACTS

The following facts are undisputed. Plaintiff Tennessee Valley Authority (“plaintiff” or “TVA”) and the Atomic Energy Commission entered into two contracts, AT-(40-l)-3760 and AT-(40-l)-3761, on December 1, 1967. For purposes of this order, the Department of Energy (“DOE”), a successor to the Atomic Energy Commission, will be referred to as the cognizant federal agency.1 Both contracts bound TVA to supply electric power to DOE’s uranium enrichment facilities. AT-(40-l)-3760 corresponded to DOE’s facility at Oak Ridge, Tennessee (the “Oak Ridge contract”), and AT-(40-l)-3761 covered the Paducah, Kentucky facility (the “Paducah contract”). The contracts are otherwise identical.

[694]*694Each contract, as amended,2 provides a contract term through June 1990, thereafter continuing on a year-to-year basis through June 1995. However, an early termination clause permits either party, upon eight years notice of an aggregate power reduction, to rescind the contract. The contract also provides that such reductions must be made in successive steps of less than 1,000,000 kilowatts (kw) per year, beginning after the eight-year notice date.

DOE sent TVA a series of reduction notification letters dated December 24, 1981, December 20, 1982, December 23, 1983, December 24, 1984, and March 7, 1986, in order to reduce the amount of power available under both contracts from 4,485,000 kws to zero. The reduction was to take place by successive 1,000,000-kw increments in December 1989, 1990, 1991, and 1992 with a final 485,000-kw reduction in March 1994.

Section 6 of the Oak Ridge and Paducah contracts memorializes the parties’ rate schedule. Essentially, DOE’s monthly rate includes two charges: 1) a capacity charge (a fee for making potential energy available), and 2) an energy charge (a fee for actual energy used).3 Since the capacity charge is tied to the amount of potential power being made available, this fee must be paid during both the eight-year notice period and the ensuing reduction period until a zero potential power level is realized.

The rate section also contains a clause for future modification:

It is recognized that the above rates for power and energy and the adjustments thereto are based on TVA’s prevailing General Power Rate — Schedule C-2 (July 31, 1967) which may be modified or replaced by TVA from time to time. TVA shall have the right, after discussion with ... [DOE], to revise the rates, charges, and adjustments provided for herein to reflect modifications or replacements of said prevailing rate schedule from time to time.

TVA’s most recent rate schedule, General Power Rate Schedule GP-11, became effective on October 2, 1986.

DOE discontinued making full monthly payments in June 1987 by resisting the scheduled capacity charge, advising plaintiff by letter of June 10, 1987:

We have concluded that a fairer estimate of an appropriate total demand charge through 1994 is less than $1 billion. Because we have already paid more than our fair share, we believe that DOE would be justified in withholding the entire amount of the remaining FY 1987 demand charges. However, we have decided in the spirit of good faith negotiations not to take such action. Instead, we will gradually reduce our FY 1987 payments related to unused contract demand charges in DOE’s arrangement with TVA, in accordance with the following schedule:
Month Percent To Be Paid Approximate Amount To Be Paid (Millions of Dollars)
June 90% $38.25
July 80% $34.00
August 70% $29.75
September 60% $25.50
October 50% $21.25
Beginning with the October 1987 payment, DOE will pay 50 percent of the monthly demand charges identified in your letter of April 7, 1987, until a mutually satisfactory resolution of this matter can be reached. This schedule should avoid sudden, adverse consequences to TVA and its ratepayers while at the same time providing a more equitable arrangement for the ratepayers of other utilities that purchase DOE enrichment services. We will, of course, continue to pay in full the appropriate charges for power actually used at the Oak Ridge, Tennessee, complex.

Plaintiff originally filed an action in the United States District Court for the Eastern District of Tennessee seeking, inter [695]*695alia, a declaratory judgment that DOE was required to follow TVA’s rate schedule and a writ of mandamus requiring that DOE pay the rates established by the contracts. See Charles H. Dean, Jr., et al. v. John S. Herrington, et al., Civ. No. 3-87-436 (E.D. Tenn., filed June 16, 1987).4 By order of August 4, 1987, the district court transferred the case to this court pursuant to 28 U.S.C. § 1631 (1982). Dean v. Herrington, 668 F.Supp. 646 (E.D.Tenn.1987). TVA filed an amended complaint on August 20, 1987, seeking the actual amount due TVA under its contracts with DOE, which totaled $124,141,461.62 as of August 7,1987.5

DISCUSSION

Defendant argues, much as it did before the district court, that plaintiff’s claim is not justiciable since it amounts to a dispute between two Executive branch agencies. Defendant’s current argument takes three tacts: 1) The judicial branch cannot resolve interagency disputes; 2) Exec. Order No. 12,146, 3 C.F.R. 409 (1979), requires submission of TVA’s claim to the Attorney General before proceeding in court;6 and 3), a new argument, the Oak Ridge and Paducah contracts are not “true contracts.” The district court rejected the first two arguments, Dean, 668 F.Supp. at 650-53, and plaintiff seeks to enforce these rulings in this court as law of the case. Although it asked the district court to rule on justiciability and the application of Exec. Order No. 12,146, defendant argues that the district court’s analysis on these issues of law should be given no deference.

1. Law of the case

The purpose of the law of the case doctrine was summarized by the Federal Circuit in Gindes v. United States, 740 F.2d 947, 949 (Fed.Cir.) (quoting Messenger v. Anderson, 225 U.S. 436, 444, 32 S.Ct. 739, 740, 56 L.Ed. 1152 (1912)), cert. denied, 469 U.S. 1074, 105 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Council for Tribal Employment Rights v. United States
112 Fed. Cl. 231 (Federal Claims, 2013)
Connecticut v. American Elec. Power Co., Inc.
582 F.3d 309 (Second Circuit, 2009)
Aldridge v. United States
67 Fed. Cl. 113 (Federal Claims, 2005)
Tennessee Valley Authority, Georgia Power Company, Intervenor v. United States Environmental Protection Agency, John H. Hankinson, Jr., Regional Administrator, Alabama Power Company, Duke Energy Corporation, Georgia Power Company, Intervenor v. United States Environmental Protection Agency, John H. Hankinson, Jr., Regional Administrator, Tennessee Valley Authority, Georgia Power Company, Intervenor v. United States Environmental Protection Agency, John H. Hankinson, Jr., Regional Administrator, Tennessee Valley Authority, Georgia Power Company, Intervenor v. United States Environmental Protection Agency, John H. Hankinson, Jr., Regional Administrator, Alabama Power Company, Duke Energy Corporation, Georgia Power Company, Intervenor v. United States Environmental Protection Agency, John H. Hankinson, Jr., Regional Administrator, Tennessee Valley Authority, Georgia Power Company, Intervenor v. United States Environmental Protection Agency, John H. Hankinson, Jr., Regional Administrator, Tennessee Valley Authority v. Christine Todd Whitman, Administrator, United States Environmental Protection Agency, United States Environmental Protection Agency, Alabama Power Company v. Christine Todd Whitman, Administrator, United States Environmental Protection Agency, United States Environmental Protection Agency, Tennessee Valley Public Power Association, Memphis Light, Gas & Water Division, Electric Power Board of Chattanooga v. Christine Todd Whitman, Administrator, United States Environmental Protection Agency, United States Environmental Protection Agency, Duke Energy Corporation v. Christine Todd Whitman, Administrator, United States Environmental Protection Agency, United States Environmental Protection Agency
278 F.3d 1184 (Eleventh Circuit, 2002)
Tennessee Valley Authority v. United States
51 Fed. Cl. 284 (Federal Claims, 2001)
State v. CNA Ins. Companies
779 A.2d 662 (Supreme Court of Vermont, 2001)
Crane v. United States
41 Fed. Cl. 338 (Federal Claims, 1998)
Massachusetts Bay Transportation Authority v. United States
36 Cont. Cas. Fed. 75,912 (Court of Claims, 1990)
Atlas Corp. v. United States
35 Cont. Cas. Fed. 75,578 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
13 Cl. Ct. 692, 1987 U.S. Claims LEXIS 213, 1987 WL 4266, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-valley-authority-v-united-states-cc-1987.