Tennessee Gas Pipeline Co. v. Federal Energy Regulatory Commission

824 F.2d 78, 262 U.S. App. D.C. 351, 1987 U.S. App. LEXIS 9885
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 24, 1987
DocketNos. 85-1644, 85-1710
StatusPublished
Cited by1 cases

This text of 824 F.2d 78 (Tennessee Gas Pipeline Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Gas Pipeline Co. v. Federal Energy Regulatory Commission, 824 F.2d 78, 262 U.S. App. D.C. 351, 1987 U.S. App. LEXIS 9885 (D.C. Cir. 1987).

Opinion

WILLIAMS, Circuit Judge:

Tennessee Gas Pipeline Company (“Tennessee”) and Columbia Gulf Transmission Company (“Columbia Gulf”) challenge two conditions imposed by the Federal Energy Regulatory Commission (“FERC”) in certificates of public convenience and necessity under § 7(c) and (e) of the Natural Gas Act (“NGA”), 15 U.S.C. § 717f(c), (e) (1982). The certificates authorize the companies to provide transportation service through an offshore pipeline, but limit the transporters in two respects. First, they deny Tennessee’s request for incremental pricing. Second, they authorize firm service for two shippers at a level far below those to which the shippers agreed in contracts with the transporters. For the reasons explained below, we uphold the Commission on the incremental pricing issue but not on the firm service issue.

[353]*353I. Background

At issue is a 26-mile-long pipeline running from an offshore platform to Plaque-mines Parish, Louisiana, known as SP77. Construction of SP77 was approved by FERC in 1980, Tennessee Gas Pipeline Co., 12 F.E.R.C. (CCH) ¶ 61,307 (1980) (the “1980 Order”), and undertaken by Tennessee and Columbia Gulf, with financial participation from Gulf Oil Corporation.1 Tennessee and Columbia Gulf planned to transport gas both for their own accounts and for the accounts of other companies with reserves in the area.

Tennessee and Columbia Gulf made arrangements with four such companies to transport gas and filed applications under § 7 for certificates of public convenience and necessity to authorize such service. In Tennessee Gas Pipeline Co., 30 F.E.R.C. (CCH) 1161,166 (1985) (the “1985 Order”), FERC authorized some, but not all, of the service sought and imposed various conditions. Tennessee and Columbia Gulf sought rehearing, see Columbia Gulf Transmission Co., 32 F.E.R.C. (CCH) 1161,407 (1985) (the “Order Denying Hearing”), and then petitioned for review in this court. After oral argument, we requested supplementary briefing; on receipt of the briefing, we ordered the record remanded to the Commission for additional factfinding and explanation. FERC responded to our order on March 11, 1987, Tennessee Gas Pipeline Co., 38 F.E.R.C. (CCH) 1161-238 (1987) (the “Order on Remand”), and the parties filed responses to it.

II. Incremental v. Average-Cost Pricing

Both Tennessee and Columbia Gulf sought permission from FERC to charge the shippers using SP77 on an incremental cost-of-service basis. In other words, they proposed to base charges for SP77 transportation on the cost of the offshore facility alone, rather than an average of the transportation costs of their entire systems. This would yield a higher rate than if pricing were done on a system-wide basis, as the unit costs of SP77 were higher than the transporters’ average costs. FERC allowed Columbia Gulf to adopt incremental pricing, but refused to allow Tennessee to do so. It explained that Tennessee, unlike Columbia Gulf, had already included its share of the costs of SP77 in its system-wide rates under a settlement agreement and that permitting incremental pricing would result in double recovery.

Tennessee originally resisted the proposition that its system-wide rates included SP77 costs, but in the face of FERC’s explanation in its Order on Remand conceded the point. Response of Tennessee Gas Pipeline Company to Order on Remand at 3. It now argues that this inclusion of these rates provides no assurance that it will actually recover its costs, since cost recovery depends on actual service levels. Id. at 4. This is, of course, also true of rates established under §§ 4 and 5 of the Natural Gas Act, 15 U.S.C. §§ 717c, 717d (1982), but it in no way undermines the validity of those rates.

Of course, business may have been disappointing for Tennessee since the last general rate case. But nothing in the structure of the NGA suggests that the Commission should use § 7 as a device for mid-course corrections of rates established under §§ 4 and 5, as Tennessee appears to suppose. Indeed, in Panhandle Eastern Pipe Line Co. v. FERC, 613 F.2d 1120 (D.C.Cir.1979), cert. denied, 449 U.S. 889, 101 S.Ct. 247, 66 L.Ed.2d 115 (1980), the Commission attempted such a mid-course correction, conditioning certification of new service on the pipeline’s crediting the resulting revenues (less out-of-pocket costs) to other customers, effectively reducing their rates. FERC sought to justify the condition by assertions that otherwise the pipeline would enjoy overrecovery. This court invalidated the condition, explaining that such tampering suffered a variety of defects, including that it wrongly disturbed the rate stability that Congress sought to [354]*354establish by means of §§ 4 and 5. 613 F.2d at 1129-30. See also Northern Natural Gas Co. v. FERC, 780 F.2d 59 (D.C. Cir. 1985) (vacated in pertinent part pending reconsideration en banc). Putting aside the question (obviously not before us) of whether the Commission could use § 7 to remedy underrecoveries stemming from disappointing volume, it seems clear that the Commission is not obliged to do so.

Ironically, Tennessee invokes Panhandle and Northern Natural in attacking FERC’s decision as unlawful ratemaking. Its argument appears to be that because a concern to prevent double recovery animated the Commission in those cases, it must not be allowed to rely on such a concern here. But neither of those cases laid down some general rule that concern for double recovery could never play a role in imposition of rate conditions under § 7. In those cases, the Commission sought to adjust rates previously found just and reasonable for service as to which no § 7 certificate was being sought; here, it is simply establishing rate conditions for the service to be certificated. We agree with FERC that Tennessee’s argument stands Panhandle on its head.

In its most recent submission, Tennessee invokes two recent Commission decisions, Panhandle Eastern Pipe Line Co., 39 F.E. R.C. (CCH) II 61,101 (1987), and Trunkline Gas Co., 39 F.E.R.C. (CCH) ¶ 61,100 (1987), apparently to support the proposition that rate conditions imposed in § 7 certificates may not derive in any way from data developed in prior settlements. In both cases the Commission was reviewing proposed rates for transportation service to be offered under Order No. 436, 50 Fed.Reg. 42,408 (1985) (codified at scattered sections of 18 C.F.R.), partially reversed and remanded, Associated Gas Distributors v. FERC, 824 F.2d 981 (D.C.Cir.1987). That Order dramatically revamped the rules under which pipelines might offer transportation under § 311 of the Natural Gas Policy Act, 15 U.S.C. § 3371 (1982), or “blanket certificate” transportation under § 7.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
824 F.2d 78, 262 U.S. App. D.C. 351, 1987 U.S. App. LEXIS 9885, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-gas-pipeline-co-v-federal-energy-regulatory-commission-cadc-1987.