Tenneco, Inc. v. United States

301 F. Supp. 598, 34 Oil & Gas Rep. 337, 23 A.F.T.R.2d (RIA) 1123, 1969 U.S. Dist. LEXIS 12681
CourtDistrict Court, S.D. Texas
DecidedFebruary 27, 1969
DocketCiv. A. No. 65-H-206
StatusPublished
Cited by3 cases

This text of 301 F. Supp. 598 (Tenneco, Inc. v. United States) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tenneco, Inc. v. United States, 301 F. Supp. 598, 34 Oil & Gas Rep. 337, 23 A.F.T.R.2d (RIA) 1123, 1969 U.S. Dist. LEXIS 12681 (S.D. Tex. 1969).

Opinion

Memorandum and Order

SINGLETON, District Judge.

This is a civil action brought by Tenneco, Inc. (Tenneco) against the United States of America (Government) for recovery of federal income taxes alleged to have been overpaid for the years 1959 and 1960. Jurisdiction has been stipulated and agreed to by the parties.

Tenneco brought this suit on behalf of itself and Midwestern Gas Transmission Company, a wholly owned subsidiary of Tenneco and an affiliated corporation [599]*599within the meaning of the Internal Revenue Code. Tenneco and the Government have agreed that the legal position of Tenneco and Midwestern are identical and for convenience the facts applicable to Tenneco only will be set forth with the understanding that the decision of the Court as to such facts will control in the disposition of the claim of Midwestern.

For all purposes unless otherwise indicated, the facts found by the Court are those existing as of December 31, 1960, the last year involved in this suit.

Tenneco is and has been engaged in the business of purchasing, transporting via pipeline, and selling natural gas in interstate commerce to utility companies for resale and directly to industries for their own use; and is a natural gas company as defined in the Natural Gas Act and subject to the jurisdiction of the Federal Power Commission.

Tenneco uses a number of large diameter (24 inch to 30 inch) long distance pipelines (“mainlines”), together with an integrated network of gathering and latteral lines, compressor stations, meter devices and stations and related buildings and equipment (“the transmission system”).

The mainlines run from sources of supply, principally in Texas and Louisiana, to natural gas marketing areas, principally in the Northeastern section of the United States. As of December 31, 1960, Tenneco had constructed approximately 8,524 miles of mainlines at a total cost of $713,527,731.

Tenneco’s initial transmission system (the “100 series”) was comprised of a mainline running from south Texas into West Virginia. Its second series of mainlines extended its mainlines from West Virginia into Massachusetts. Its third series of mainlines (the “300 series”) extended its mainlines from northern Pennsylvania into New York. A fourth series of mainlines (the “800 series”) extended from gas gathering areas running from south Texas into southern Louisiana and tied into the earlier constructed mainlines in northern Tennessee. A fifth series of mainlines (the “500 series”) extended from gas gathering areas running from southwestern Louisiana to the Mississippi River Delta region south of New Orleans, and from such gathering areas northeasterly across Mississippi to tie into the earlier constructed mainlines in northern Tennessee.

Natural gas is transported in these mainlines by compression which causes it to move from the point of higher pressure to a lower pressure. Friction slows movement and causes the pressure of the gas to decrease. To restore compression, compressor stations are located along the mainlines at periodic intervals of approximately 90 miles and are tied into the mainlines by valves (“mainline valves”). Tenneco’s mainlines comprising each of mainline systems are tied together by such mainline valves at intervals of approximately 15 miles.

Tenneco has from the inception of its business, operated its mainlines at their full rated capacity in order to derive the greatest possible revenues therefrom, and to maintain the transportation cost of a unit of gas at the lowest possible level. Tenneco will not willingly permit any break in the throughput capacity of its mainlines except as a result of some emergency not affecting any substantial distance along a mainline.

For purposes of analysis, Tenneco’s mainlines may be classified as either primary lines or loop lines. A primary line is the first mainline laid from one geographical point to another. A loop line is a mainline which ties into two or more mainline valves of an existing primary line. A loop line is placed in service in relatively short discontinuous sections constructed from time to time as requirements for additional gas transmission capacity are experienced. For safety reasons, a loop line is generally located at least 50 feet from an existing primary line. Moreover, because of topography, technological developments, and other factors affecting the economics of pipeline construction, loop lines most frequently spread apart and [600]*600then come back together, and are often as far away as a quarter of a mile from an existing mainline. Loop lines usually are not laid parallel to an existing line for any appreciable distance. As of December 31, 1960, Tenneco had constructed two loop lines over substantially the entirety of the area traversed by its 100 series, a third loop line over the greater part of the 100 series, and a fourth loop line over a 195-mile section of the 100 series. Two loop lines had been constructed over more than one-fourth of the distance of the 200 series.

The construction of loop lines is the standard method used by Tenneco in increasing its gas delivery capability, and in the past Tenneco has looped its lines primarily to increase the gas throughput capacity. However, the evidence also shows that upon the expiration of the useful life (whether for reason of deterioration, required increase in tensile strength of line because of change in population density, or other reason) of any substantial segment of an existing mainline, Tenneco will replace the gas delivery capacity of such portion by looping the old line with a new line and then abandoning the old line in place. Although it is physically possible to remove the pipe from an existing line and lay new pipe in the same trench, this is not done except to make emergency repairs to short segments of Tenneco’s lines. The reason for this is threefold: (a) First, the construction cost involved in removing the old pipe and relaying the new pipe in the same ditch is more expensive than looping the old line with a new line; (b) second, the developments in the technology of pipeline construction and changes in population and the use of the land since the first line was laid and other facts often make it impractical to remove the old line and lay a new line in the same trench; and (c) most importantly, the removing of the old pipe and laying a new pipe in the same trench would result in an extended interruption in the transmission of Tenneco’s gas deliverability which at best would result in an economically prohibitive loss of revenue and in some cases would make it impossible for Tenneco to fulfill its contractual requirements for the supply of gas.

For depreciation purposes, Tenneco has maintained a single composite account for its transmission system. For all years up to and including the years involved in this suit, the Government has consented to and approved the use of Tenneco’s composite method of computing depreciation, but the Commissioner of Internal Revenue has continually held that the portion of Tenneco’s investment in its mainlines which Tenneco has classified as right-of-way costs must be excluded from such account and is not otherwise entitled to an allowance for depreciation or amortization. For the years 1959 and 1960 the average composite economic life for tax purposes was 28% years, and such average economic life was claimed by Tenneco and accepted by the Commissioner upon the examination of Tenneco’s United States income tax returns for such years.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burlington Northern Inc. v. United States
676 F.2d 566 (Court of Claims, 1982)
Spartanburg Terminal Co. v. Commissioner
66 T.C. 916 (U.S. Tax Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
301 F. Supp. 598, 34 Oil & Gas Rep. 337, 23 A.F.T.R.2d (RIA) 1123, 1969 U.S. Dist. LEXIS 12681, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tenneco-inc-v-united-states-txsd-1969.