Spartanburg Terminal Co. v. Commissioner

66 T.C. 916, 1976 U.S. Tax Ct. LEXIS 54
CourtUnited States Tax Court
DecidedAugust 30, 1976
DocketDocket No. 3475-73
StatusPublished
Cited by23 cases

This text of 66 T.C. 916 (Spartanburg Terminal Co. v. Commissioner) is published on Counsel Stack Legal Research, covering United States Tax Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spartanburg Terminal Co. v. Commissioner, 66 T.C. 916, 1976 U.S. Tax Ct. LEXIS 54 (tax 1976).

Opinion

Irwin, Judge:

Respondent has determined the following deficiencies in petitioner’s Federal income tax:

Year ended Deficiency Year ended Deficiency
12/31/64_ $28,688.42 12/31/66_ $64,236.63
12/31/65_ 71,531.50 12/31/67_ 40,641.82

The parties have made several concessions, leaving for our resolution only the issues: whether petitioner is entitled to depreciation deductions with respect to certain costs of constructing a railroad tunnel; whether an investment credit is allowable with respect to these costs; and whether an investment credit is allowable with respect to the costs of installing fences and gates to prohibit trespassers from entering the tunnel or upon the tracks.

FINDINGS OF FACT

Some of the facts have been stipulated and, except as noted in footnote 5 infra, are so found. The stipulation of facts, together with the exhibits attached thereto, are incorporated herein by this reference.

Petitioner Spartanburg Terminal Co. is a South Carolina corporation with its principal office in Jacksonville, Fla. For the taxable years 1964 through 1967, petitioner filed its Federal corporate income tax returns with the District Director of Internal Revenue in Jacksonville, Fla.

Petitioner was organized in September 1953 for the purpose of constructing and operating a railroad tunnel and connecting tracks in Spartanburg, S.C. The tunnel and connecting tracks connected existing lines belonging to Atlantic Coast Line Railroad (now Seaboard Coast Line Railroad), Clinchfield Railroad Co., and Piedmont & Northern Railroad Co. Previously, such connections had been made over nearby tracks belonging to the Southern Railway Co. The tunnel was constructed underneath the Southern Railway Co. tracks and surface streets in downtown Spartanburg, S.C., and formed an important link in the Atlantic Coast Line (now Seaboard Coast Line) rail system. Construction of the tunnel made use of the Southern Railway tracks (and the costs incident thereto) no longer necessary.

Atlantic Coast Line Railroad Co. owned 75 percent of petitioner’s outstanding stock with the remaining 25 percent being owned by Louisville & Nashville Railroad Co. for all the years relevant to this litigation. Atlantic Coast Line Railroad also owned a controlling stock interest in the Louisville & Nashville Railroad Co. during all relevant years.

Petitioner’s tunnel was in the planning stage for many years (possibly since 1908) before construction commenced in 1962. Construction was completed in July 1963 and the tunnel placed in service at that time. The total cost of the tunnel project was $2,637,508.71.

The tunnel was constructed on an easement acquired from the Southern Railway Co. after extended litigation and condemnation proceedings. The record does not indicate the length of time over which the easement extends.

Construction began by first clearing and grading the approach sections at each end of the tunnel. The northern approach section is approximately 2,000 feet long and the southern approach section approximately 1,400 feet long. The tunnel itself is just under 800 feet long.

The approaches were constructed by the “cut and fill” method of excavation whereby earth was removed to create a gradually descending roadbed from the original ground level down to the tunnel floor. Some of the earth removed was used to “fill” in portions of the natural ground line which fell below the desired roadbed level, but most of the excavated dirt was hauled away from the construction site altogether.

The tunnel itself was constructed by using both the “cut and cover” and “driven” methods of construction. The “cut and cover” method of construction consisted of driving sheet metal into the ground to form a rectangular cell. Earth was then removed from the rectangular cell down to the desired level of the tunnel floor. A reinforced concrete floor was laid and a railroad car, with a form the shape of the tunnel bore mounted on it, was moved into the excavated rectangular cell. Reinforcing steel was set in place and concrete poured over the form and between the sheet piling walls of the rectangular cell. After the concrete had properly cured, the form car was moved into a new excavation section. Earth was then “backfilled” on top of the completed concrete and steel tunnel structure to bring the ground level above the tunnel back to its original condition prior to the time construction began. Approximately 450 feet of the tunnel were constructed by this “cut and cover” method.

The remaining portion of the tunnel (approximately 350 feet) was constructed by the “driven” method. This method, in essence, was equivalent to burrowing a hole through the earth. That is, not all of the earth above the tunnel was removed during construction. Only the earth from the tunnel bore plus enough to leave room for the tunnel lining was removed. Once all of the earth was removed from the tunnel bore a concrete floor was poured and reinforcing steel erected along the tunnel walls. Again the form car, previously described, was moved into the tunnel. Concrete was then pumped into the space between the form and the steel lining along the walls. When the concrete had cured, the form car was moved forward and the process repeated until all the walls in the “driven” section of the tunnel were lined with concrete and steel.

At each end of the tunnel a concrete “portal” was constructed consisting of a concrete archway over the entrance and concrete retaining walls stretching out from the archway. The purpose of the retaining walls was to retain the earth above the tunnel from falling into the approach sections.

Since the approach sections at each end of the tunnel descended below the original surrounding ground level, the earth sides of the approaches had to be sufficiently sloped to prevent dirt from sliding onto the roadbed. As a further protection against earth slides, short concrete retaining walls, or, in some cases, “cribs”1 were placed at the foot of each side of the approach to retain the earth. Additionally, hand-placed stones, grass seed, and a light asphalt spray were used to help stabilize the slopes until the natural vegetation had grown sufficiently.

After the tunnel was constructed and slope stabilization completed, a permanent track structure was constructed through the tunnel.

During construction of the “cut and cover” sections of the tunnel, various sewer, water, and utility lines had to be temporarily relocated. Once these sections of the tunnel were completed, these utility lines, etc., were replaced in their original position. In addition, a surface street and sidewalk above the tunnel had to be torn up, a temporary bridge constructed, and then the street rebuilt once construction was completed. Similarly, a parking lot had to be torn up and rebuilt and certain railroad tracks relocated.

Upon completion of the tunnel, track, and related facilities, petitioner prepared a final roadway completion report which includes all of the costs incurred in the tunnel construction project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fed. Home Loan Mortg. Corp. v. Comm'r
2006 T.C. Memo. 153 (U.S. Tax Court, 2006)
New England Electric System v. United States
28 Fed. Cl. 720 (Federal Claims, 1993)
Texas Instruments v. Commissioner
1992 T.C. Memo. 306 (U.S. Tax Court, 1992)
Colorado Nat'l Bankshares, Inc. v. Commissioner
1990 T.C. Memo. 495 (U.S. Tax Court, 1990)
Banc One Corp. v. Commissioner
84 T.C. No. 35 (U.S. Tax Court, 1985)
Austin v. Commissioner
1985 T.C. Memo. 22 (U.S. Tax Court, 1985)
Wheeler v. Comm'r
1984 T.C. Memo. 425 (U.S. Tax Court, 1984)
Burlington Northern Inc. v. United States
676 F.2d 566 (Court of Claims, 1982)
Kansas City S. R. Co. v. Commissioner
76 T.C. 1067 (U.S. Tax Court, 1981)
Southern Pacific Transp. Co. v. Commissioner
75 T.C. 497 (U.S. Tax Court, 1980)
Greenway v. Commissioner
1980 T.C. Memo. 97 (U.S. Tax Court, 1980)
Seaboard C. L. R. Co. v. Commissioner
72 T.C. 855 (U.S. Tax Court, 1979)
Adams v. Commissioner
71 T.C. 477 (U.S. Tax Court, 1978)
Spalding v. Commissioner
66 T.C. 1017 (U.S. Tax Court, 1976)
Spartanburg Terminal Co. v. Commissioner
66 T.C. 916 (U.S. Tax Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
66 T.C. 916, 1976 U.S. Tax Ct. LEXIS 54, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spartanburg-terminal-co-v-commissioner-tax-1976.