Ten Hoeve Bros., Inc. v. City of Hartford, No. Cv93-0704020s (May 8, 1996)

1996 Conn. Super. Ct. 4213, 17 Conn. L. Rptr. 173
CourtConnecticut Superior Court
DecidedMay 8, 1996
DocketNo. CV93-0704020S
StatusUnpublished

This text of 1996 Conn. Super. Ct. 4213 (Ten Hoeve Bros., Inc. v. City of Hartford, No. Cv93-0704020s (May 8, 1996)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ten Hoeve Bros., Inc. v. City of Hartford, No. Cv93-0704020s (May 8, 1996), 1996 Conn. Super. Ct. 4213, 17 Conn. L. Rptr. 173 (Colo. Ct. App. 1996).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION ON MOTION FOR SUMMARY JUDGMENT OF PLAINTIFFAND CROSS MOTION FOR SUMMARY JUDGMENT BY DEFENDANT CITY OF HARTFORD On or about September 31, 1991 defendant Stack Contracting, Inc. ("Stack") was issued purchase order No. 111264 by the defendant City of Hartford ("City") for soil excavation, and the removal and replacement of an underground gas storage tank ("UST") at the City's public works yard at 40 Jennings Street, Hartford, Connecticut ("Project"). As part of its contract with the City, Stack agreed to supply all materials necessary to remove and replace the defective UST.

On or about September 4, 1990 Stack entered into a contract with the plaintiff, Ten Hoeve Bros., Inc. ("Ten Hoeve") whereby Stack was able to purchase materials from Ten Hoeve on an open account. Among the materials sold to Stack on this open account were materials to be used by Stack at the Project. Stack failed to pay for $24,301.74 worth of materials and equipment it had purchased from Ten Hoeve for use at the Project.

On or about June 29, 1992, Ann Del Mastro, Ten Hoeve's Credit Manager, gave oral and written notice to Raymond Miller of the City's Public Works Department that Stack had failed to pay for $24,301.74 worth of materials and equipment used by Stack at the Project and requested payment from the city.

The City refused to pay Ten Hoeve for the materials used by Stack at the Project, even though purchase order No. 111264 had a $99,547.74 balance when it received Del Mastro's letter on July 1, 1992.

At least $20,000 remained in purchase order No. 111264 until February, 1993. This action was commenced on April 7, 1993. The CT Page 4213-A plaintiff seeks partial summary judgment on the first count of its Amended Complaint (Equitable Lien). The defendant city of Hartford has filed a cross motion for summary judgment as to this count and also as to the seventh and eighth counts of the complaint. The rules regarding motions for summary judgment are well-known. The dispute between the parties is not so much a factual as a legal dispute.

1.

I believe the defendant City should prevail on its motion for summary judgment as to counts seven and count eight.

Count seven of the amended complaint alleges the city breached its statutory duty (§ 49-41) by not requiring a payment bond. The city had no such duty — the language of the statute requires the contractor not the governmental agency to obtain a payment bond.O G v. Town of New Milford, 229 Conn. 303, 311 (1994).

The eighth count must similarly fail. In that count the plaintiff claims the city was negligent since it failed to ensure that the general contractor secured a payment bond. There can be no cause of action. For negligence without a duty and fault in the performance of that duty. As just indicated no such duty was owed to the plaintiff by the city in the procurement of the payment bond.

2.

The plaintiff has brought an equitable lien action based on and directed to the fact that at the time it notified the city that Stack had not paid the plaintiff, funds existed in a purchase order created by the city so that Stack could complete the project.

Equitable liens are well-known to the courts though their use and thus litigation surrounding them has declined over the years with the creation of statutory liens of various sorts. Such liens are generally discussed in The Law of Restitution. Palmer Vol. I, § 1.5 (1978), Pomeroy's Equity Jurisprudence, Vol. I, § 165 et seq., 51 Am.Jur.2d § 22 et seq., Restatement of Restitution, § 161; an ALR article deals with a topic related to the issue now before the court, "Building and Construction Contracts: Contractor's Equitable Lien Upon Percentage of Funds Withheld by Contractee or Lender", 54 ALR 3d 848 (1973). Connecticut courts have recognized the concept of equitable liens, Witaker v. Williams, 20 Conn. 527, 531 (1850), CT Page 4213-BHansel v. Hartford-Connecticut Trust Co., 133 Conn. 181, 194 (1976), Employers' Liability Assurance Corp. v. Crandall,22 Conn. Sup. 404, 406 (1961).

An equitable lien differs from a so-called common law lien because the latter lien involves the right to retain property until a debt or demand due the party retaining the property is satisfied; under an equitable lien possession remains with the debtor or the person against whom the demand is made; Forster v. Thornton,179 So. 882, 892 (Fla. 1937).

An equitable lien can be based on an express or implied contract but as one case said: "The trend of modern decisions is to hold that in the absence of an express contract, a lien based upon the fundamental maxims of equity may be implied and declared by a court of equity out of general considerations of right and justice as applied to the relationship of the parties and the circumstances of their dealing", Calaurcio v. Levson, et al.,215 N.E.2d 839, 841 (Ill, 1966). Other courts have used similar broad language in a variety of different factual situations, Caldwell v.Armstrong, 342 F.2d 485, 490 (CA 10, 1965). Equitable liens are said to be based on doctrines of unjust enrichment, Caldwell v.Armstrong, supra. Although deception of fraud may be involved wrongdoing is not an essential element for the imposition of such a lien, Gulf Shore Dredging Co. v. Ingram, 193 So.2d 232, 234 (Fla, 1966). There must be some ground for equitable intervention including the absence of an adequate remedy at law, Id. at p. 234,Architectonics Inc. v. Salem-American Ventures, 350 So.2d 581, 584 (1977) and it has been held that there must be some superior right vis-a-vis other creditors by the party asserting the lien, CentralContractors Services Inc. v. Ohio County Ston. Co., 255 S.W.2d 17,21 (Ky, 1952).

As the above referenced ALR article indicates equitable lien doctrine has been applied in litigation by various parties arising out of disputes over various claims for failure to pay under construction contracts. There is authority for allowing an equitable lien to suppliers in factual situations similar to the one now before the court. In the case of Active Fire SprinklersCorp. v. US Postal Service, 811 F.2d 747 (CA 2, 1987) a subcontractor asserted equitable rights to a discrete fund referred to in the case as "the Contract Balance" held by the Postal Service at the time the subcontractor brought its lien action. The court referring to Henningsen v. USFG,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Ansonia Brass & Copper Co.
218 U.S. 452 (Supreme Court, 1910)
Peninsular Supply Co. v. CB Day Realty of Fla., Inc.
423 So. 2d 500 (District Court of Appeal of Florida, 1982)
American Masons' Supply Co. v. F. W. Brown Co.
384 A.2d 378 (Supreme Court of Connecticut, 1978)
ARCHITECTONICS, INC. v. Salem-American Ventures
350 So. 2d 581 (District Court of Appeal of Florida, 1977)
Skorpios Properties, Ltd. v. Waage
374 A.2d 165 (Supreme Court of Connecticut, 1976)
Roy v. Mulcahy
288 A.2d 64 (Supreme Court of Connecticut, 1971)
Robinson v. Robinson
429 N.E.2d 183 (Appellate Court of Illinois, 1981)
Calacurcio v. Levson
215 N.E.2d 839 (Appellate Court of Illinois, 1966)
Hansel v. Hartford-Connecticut Trust Co.
49 A.2d 666 (Supreme Court of Connecticut, 1946)
Employers' Liability Assurance Corp. v. Crandall
173 A.2d 926 (Connecticut Superior Court, 1961)
Foster v. Thornton
179 So. 882 (Supreme Court of Florida, 1937)
Clements v. Holmes
120 S.W.2d 988 (Court of Appeals of Tennessee, 1938)
Nelson v. Nelson Neal Lumber Co.
17 P.2d 626 (Washington Supreme Court, 1932)
Central Contractors Service, Inc. v. Ohio County Stone Co.
255 S.W.2d 17 (Court of Appeals of Kentucky, 1952)
Whitaker v. Williams
20 Conn. 527 (Supreme Court of Connecticut, 1850)
Ryszkiewicz v. City of New Britain
479 A.2d 793 (Supreme Court of Connecticut, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
1996 Conn. Super. Ct. 4213, 17 Conn. L. Rptr. 173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ten-hoeve-bros-inc-v-city-of-hartford-no-cv93-0704020s-may-8-1996-connsuperct-1996.