Ted Jacob Engineering Group, Inc. v. THE RATCLIEF ARCHITECTS

187 Cal. App. 4th 945, 114 Cal. Rptr. 3d 644, 2010 Cal. App. LEXIS 1463
CourtCalifornia Court of Appeal
DecidedAugust 23, 2010
DocketA122932
StatusPublished
Cited by11 cases

This text of 187 Cal. App. 4th 945 (Ted Jacob Engineering Group, Inc. v. THE RATCLIEF ARCHITECTS) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ted Jacob Engineering Group, Inc. v. THE RATCLIEF ARCHITECTS, 187 Cal. App. 4th 945, 114 Cal. Rptr. 3d 644, 2010 Cal. App. LEXIS 1463 (Cal. Ct. App. 2010).

Opinion

Opinion

BRUINIERS, J.

The Ratcliff Architects (Ratcliff) provided design services under contract with the County of San Mateo (the County) for a hospital renovation and expansion project. Ratcliff subcontracted with Ted Jacob Engineering Group, Inc. (TJEG), for mechanical and electrical engineering services. The scope of the project increased over time. TJEG submitted claims for additional fees based on the increased basic scope of work and for additional services it alleged it was directed to perform by Ratcliff. Ratcliff paid some, but not all, of TJEG’s claims. TJEG sued Ratcliff and prevailed in a jury trial. The trial court awarded prejudgment interest on TJEG’s recovery and awarded TJEG its attorney fees and costs. Ratcliff argues the judgment must be reversed because the instructions to the jury were contradictory and confusing, and because TJEG’s claims were not sufficiently certain to support an award of prejudgment interest. We affirm.

In the published portion of this opinion we hold that, in the absence of a negotiated agreement upon price, and assuming no contrary contractual provision applies, a subcontractor may still pursue a claim seeking a judicial determination of additional fees when it performs work demanded of it by the general contractor constituting a material change in the scope of work defined under the contract. If good faith negotiation between the parties fails to result in agreement on price, the subcontractor is not required to elect between abandoning the job and forfeiting its right of recovery if it elects to perform the required work.

*948 I. Trial Evidence 1

The Project

In about 1992, the County commissioned Kaplan/McLaughlin/Diaz (KMD) to study a potential renovation and expansion of the San Mateo County General Hospital (the Project). The KMD study, which was completed in May 1992, included a design with an estimated construction cost of $45,808,424 without cost escalation or a 10 percent contingency (concept A-8). The KMD study concluded that the central plant of the hospital would have to be replaced.

The County then directly commissioned TJEG to further study the central plant issue. TJEG’s study (the Central Plant Study), completed in July 1992, concluded that the cost of the central plant replacement would be much higher than had been originally estimated by KMD.

The County began hiring a design team for the Project. Consistent with custom and practice in the industry, the County intended to contract directly with an architectural firm, which would in turn contract with consultants to assist in the design of the Project. The architectural firm and its consultants collectively would comprise the design team. Ratcliff asked TJEG for a proposal for the mechanical (including HVAC [heating, ventilating, air conditioning] and plumbing) and electrical design work on the Project.

Notwithstanding the conclusion of TJEG’s Central Plant Study, Ratcliff told TJEG to base its fee proposal on concept A-8 from the KMD study and TJEG did so. At an August 17, 1992 meeting with Ratcliff and the County, TJEG principal Ted Jacob asked how TJEG’s fees would be adjusted if the Project scope exceeded what was anticipated in the KMD study. He received “strict instructions to base [his] fee on the KMD scheme A-8 on the hospital and the central plant, and . . . [was told that] at the end of the design development they [would] make the adjustment” based on estimated construction costs at that time. Jacob memorialized this understanding as to the scope of work included in TJEG’s proposal in an August 17, 1992 letter to Ratcliff.

*949 Based on concept A-8, Jacob proposed a fee of $1,072,270 for mechanical and electrical design work. Its fee proposal stated: “The following items are not outlined in the KMD Master Plan but must be performed as recommended in the Central Plant Study and per our meeting with Fred Countryman. It is agreed that the additional fees will be allocated to us after design development.” A list of additional tasks and fees followed. Shortly thereafter, Ratcliff directed TJEG to commence work on the Project.

Stephanie Bartos, Ratcliff’s manager on the Project until January 1995, testified that she believed “there was a discrepancy between the work defined in the KMD study and what actually had to be done ... to complete the work according to code and good design practice.” 2 (Original ellipsis.) She testified that the County’s representative on the Project, Fred Countryman, had insisted that Ratcliff base its fee on concept A-8 and promised that the fee would change if the scope of work changed.

Ratcliff/County Contract

On August 25, 1992, Ratcliff and the County executed an Agreement for Architectural Services (Ratcliff/County Contract). The contract defined the Project scope to be “as described in the Facility Program and Conceptual Design Report, Volumes 1 and 2, prepared by Kaplan/McLaughlin/Diaz, dated May 1992, and the Central Plant Feasibility Study prepared by Ted Jacob Engineering Group, Inc., dated July 1992, with any subsequent revisions agreed upon by Owner and Architect.” (Italics added.) A fixed fee of $4,076,949 covered Ratcliff’s performance of “Basic Services” on the Project, which included programming verification, schematic design, design development, preparation of construction documents, and construction contract administration. (Par. 5.01.) From this fee, Ratcliff was responsible for payment of its subcontracting consultants. (Par. 5.06.)

Paragraph 5.05 of the Ratcliff/County Contract provided, “Substantial changes in the Project’s scope shall provide sufficient basis for renegotiation of [Ratcliff’s] fee.” Ratcliff was also entitled to additional compensation if it performed services that were not encompassed in Basic Services. (Extra Services; par. 5.03.) Paragraph 5.03 of the contract provided that: “Extra Services shall not be rendered by [Ratcliff] under this Agreement unless they are first authorized in writing by [the County], The Payment to [Ratcliff] for Extra Services shall be at the [hourly] rates set forth” in an exhibit to the contract.

*950 Ratcliff/TJEG Contract

Although Ratcliff directed TJEG to start work on the Project in August 1992, Ratcliff and TJEG did not sign a written contract until August 1993. In February 1993, Ratcliff sent TJEG a draft contract, which incorporated by reference the Ratcliff/County Contract and required TJEG to perform services in accordance with that contract. TJEG had by that time received an executed copy of the Ratcliff/County Contract. TJEG’s fee for Basic Services in the draft Ratcliff/TJEG contract was set at $1,212,800.

By February 1993, the defined scope of the Project had already changed, as described in greater detail post. TJEG refused to sign the February 1993 contract as drafted without clarification that its fee was based on the KMD study scope of work alone. A revised version of the draft contract prepared in March 1993 changed the fee to $1,197,270, but it also was not signed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Steiger v. Alameda Health System CA1/2
California Court of Appeal, 2025
Quintero v. Weinkauf
California Court of Appeal, 2022
Quintero v. Weinkauf CA1/4
California Court of Appeal, 2022
Hernandez v. K.B. Ins. Co. CA1/1
California Court of Appeal, 2021
Vita Planning & Landscape Architecture, Inc. v. HKS Architects, Inc.
240 Cal. App. 4th 763 (California Court of Appeal, 2015)
American Master Lease v. Idanta Partners
California Court of Appeal, 2014
American Master Lease LLC v. Idanta Partners, Ltd.
225 Cal. App. 4th 1451 (California Court of Appeal, 2014)
American Master Lease v. Idanta Partners CA2/7
California Court of Appeal, 2014
Veronese v. Lucasfilm Ltd.
212 Cal. App. 4th 1 (California Court of Appeal, 2012)
Mize-Kurzman v. Marin Community College District
202 Cal. App. 4th 832 (California Court of Appeal, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
187 Cal. App. 4th 945, 114 Cal. Rptr. 3d 644, 2010 Cal. App. LEXIS 1463, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ted-jacob-engineering-group-inc-v-the-ratclief-architects-calctapp-2010.