TDM America, LLC v. United States

83 Fed. Cl. 780, 2008 U.S. Claims LEXIS 266, 2008 WL 4291214
CourtUnited States Court of Federal Claims
DecidedSeptember 17, 2008
DocketNo. 06-472C
StatusPublished
Cited by4 cases

This text of 83 Fed. Cl. 780 (TDM America, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TDM America, LLC v. United States, 83 Fed. Cl. 780, 2008 U.S. Claims LEXIS 266, 2008 WL 4291214 (uscfc 2008).

Opinion

ORDER REGARDING SUBJECT MATTER JURISDICTION

WHEELER, Judge.

In this patent case, Plaintiff TDM America, LLC (“TDM”) claims that the United States Army Corps of Engineers (“USACE”) and other federal agencies, through their contractors, including Third-Party Defendant Donjon Marine Company, Inc. (“Donjon”), infringed four patents owned by TDM for the processing and treatment of dredged material removed from navigable waterways. There are many contracts potentially at issue, and indeed much of TDM’s discovery has been aimed at determining the identity of federal contracts that may have infringed TDM’s patents.

On November 8, 2007, Defendant filed a pleading styled as a “motion for partial summary judgment for lack of subject matter jurisdiction” as to eighteen USACE contracts awarded by the agency’s New York District. Defendant asserts that the Authorization and Consent clause in these eighteen contracts, set forth in Federal Acquisition Regulation (“FAR”) ¶ 52.227-1, did not authorize contractors to infringe TDM’s claimed methods of processing unless specifically directed by the contract or the Contracting Officer. Therefore, Defendant argues that the Court lacks subject matter jurisdiction under 28 U.S.C. § 1498(a) (2006) to decide infringement claims against the United States where such direction is lacking. Following a period of discovery to allow review of contract provisions, TDM filed an opposition and cross-motion for partial summary judgment on February 28, 2008. Thereafter, the parties filed their responses and replies with accompanying declarations and exhibits. Together, the parties submitted 11,395 pages of exhibits for the Court’s review. The Court heard oral argument on July 30,2008.

In considering Defendant’s motion based upon a lack of government authorization un[782]*782der 28 U.S.C. § 1498(a), that statute acts as an affirmative defense rather than a jurisdictional bar. See e.g., Toxgon Corp. v. BNFL, Inc., 312 F.3d 1379, 1381-82 (Fed.Cir.2002) (citing Manville Sales Corp. v. Paramount Sys., Inc., 917 F.2d 544, 554 (Fed.Cir.1990)). Accordingly, Defendant’s motion should be resolved by summary judgment under Rule 56 of the Court of Federal Claims (“RCFC”) rather than as a motion to dismiss under RCFC 12(b)(1).

For the reasons explained below, Defendant’s motion for partial summary judgment is DENIED, and Plaintiffs cross-motion for partial summary judgment is GRANTED.

Background1

USACE is responsible for maintaining and improving the nation’s waterways for navigation. To that end, USACE employs contractors to dredge and process contaminated materials from navigation channels throughout the United States. TDM owns patents for the processing and treatment of dredged materials. TDM’s patents include U.S. Patent No. 6,293,731, issued September 25, 2001, entitled “Method for Treatment for Dredged Materials to Form a Structural Fill”; U.S. Patent No. 5,794,862, issued August 18, 1998, entitled “Processing of Waste Material”; U.S. Patent No. 5,542,614, issued August 6, 1996, entitled “Processing of Waste Material”; and U.S. Patent No. 5,007,590, issued April 16, 1991, entitled “Apparatus and Method for Mixing Solid or Semi-Solid Wastes with Additives.” On June 21, 2006, TDM filed suit against the United States in this Court alleging that USACE contractors, including Donjon, infringed its patented methods of processing dredged material during performance of USACE contracts. TDM seeks to hold the Government liable for the contractors’ actions under 28 U.S.C. § 1498.

During discovery, Defendant identified all USACE contract awards since 2000 that involved the processing of dredged material prior to disposal. Eighteen of these contracts were awarded by the USACE’s New York District, which covers the Port of New York and New Jersey and surrounding areas. It is these eighteen contracts that are at issue in Defendant’s motion for partial summary judgment.

Thirteen of the contracts at issue contain section 800, entitled “Special Contract Requirements.” Section 800 requires the contractor to submit to USACE a detailed description of the proposed process for treating dredged material, all applicable state regulatory permits necessary for the processing of dredged materials, and the name and location of the facility.2 The contractor must submit and receive USACE approval of the proposed process prior to contract award. (See, e.g., Pl.’s Ex. 2 at 9-17). Contractors for eleven of the thirteen contracts provided this mandatory information.

Nine of the contracts at issue include a Technical Provision in section 2900, entitled “Dredging and Disposal.” Among other things, section 2900 identifies sites for the processing and disposal of dredged material.3 Five contracts contain language expressly re[783]*783quiring the contractor to process and dispose of dredged material at USACE’s pre-approved OENJ (Cherokee) Processing Group site in Bayonne, New Jersey. (See, e.g., Pl.’s Ex. 58 at 3133-34). An additional four contracts listed OENJ as the approved processing facility but allowed the contractor to use an alternate facility upon USACE’s approval. Of these four, two contractors operated out of the pre-authorized OENJ facility (Def.’s Reply, at 9-10), and two received USACE approval for an alternate facility following submission of the site location and a description of the proposed treatment process.

On November 8, 2007, Defendant filed its motion for partial summary judgment, arguing that USACE did not provide authorization and consent for its contractors to infringe any of TDM’s patents in performing the New York District dredging contracts, and therefore, the Court has no jurisdiction to hear TDM’s infringement claims under 28 U.S.C. § 1498(a). Defendant argues that each of the eighteen contracts includes a narrow authorization and consent clause set forth in FAR ¶ 52.227-1, waiving liability only in the following circumstances:

(a) The Government authorizes and consents to all use and manufacture, in performing this contract or any subcontract at any tier, of any invention described in and covered by a United States patent (l)[e]m-bodied in the structure or composition of any article the delivery of which is accepted by the Government under this contract or; (2)[u]sed in machinery, tools, or methods whose use necessarily results from compliance by the Contractor or a subcontractor with (i) specifications or written provisions forming a part of this contract or (ii) specific written instructions given by the Contracting Officer directing the manner of performance.

FAR ¶ 52.227-1 (emphasis added).

On June 20, 2008, TDM filed its opposition and cross-motion to Defendant’s motion for partial summary judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Saint-Gobain Ceramics & Plastics, Inc. v. Ii-Vi Inc.
369 F. Supp. 3d 963 (C.D. California, 2019)
TDM America, LLC v. United States
92 Fed. Cl. 761 (Federal Claims, 2010)
Vermont Yankee Nuclear Power Corp. v. United States
84 Fed. Cl. 339 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
83 Fed. Cl. 780, 2008 U.S. Claims LEXIS 266, 2008 WL 4291214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tdm-america-llc-v-united-states-uscfc-2008.