Taylor State Bank v. Baumgartner

147 N.W. 385, 27 N.D. 606, 1914 N.D. LEXIS 78
CourtNorth Dakota Supreme Court
DecidedApril 24, 1914
StatusPublished
Cited by2 cases

This text of 147 N.W. 385 (Taylor State Bank v. Baumgartner) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taylor State Bank v. Baumgartner, 147 N.W. 385, 27 N.D. 606, 1914 N.D. LEXIS 78 (N.D. 1914).

Opinions

Goss, J.

This is an action to recover of the principal and surety on a bond given contemporaneously with, and intended to insure the faithful performance of the terms of, a building contract, and which contract the complaint shows has been breached by nonperformance of certain conditions thereof. Both the building contract and the contractor’s bond are a part of the complaint. The demurrer of the surety to the complaint was sustained, and judgment was entered dismissing the suit as to the surety, evidently on the assumption that the complaint could not be so amended as to state a cause of action against the surety on the bond. The order sustaining the demurrer was dated March 2d, 1912, and judgment was entered thereon March 4th, 1912, upon which latter date, on the application of plaintiff an order to show cause why said judgment just entered should not be vacated was issued, returnable March 14th, when arguments were had thereon, and the decision was taken under advisement by the court, in which condition it remained until September 21st following, when, on the surety’s application, another order was issued, returnable four days later, citing plaintiff to show cause why the judgment, concerning the vacation of which no ruling on the motion submitted to vacate the same had been made, should not be confirmed and allowed to stand as the final judgment in (the action as between the plaintiff and the surety, Ewald. Hpon the [608]*608.hearing' had on this second order to show cause, the court, ruling upon both pending motions, granted the application of the plaintiff and vacated the judgment, but sustained its former ruling on the demurrer, and granted plaintiff leave to serve and file an amended complaint within ten days; from which order defendant Ewald, appeals.

Appellant urges that respondent’s omission to serve with the motion to vacate an affidavit of merits and a proposed amended complaint renders irregular and unauthorized the action of the court in vacating the judgment. None of the authorities cited have any application on the record before the court at the time of the vacation of the judgment. No affidavit of merits was necessary, as the plaintiff was not, and could not be, in default, the question being simply that of whether a sufficient cause of action was set forth in the complaint challenged by the demurrer. Upon the court’s sustaining the demurrer, the plaintiff was permitted as of course, under the practice prevailing in this jurisdiction, leave to serve and file an amended complaint, provided the original defective complaint shadowed forth a valid cause of action. If it was reasonably apparent from the matter stated in the complaint, including the building contract and surety bond thereto attached and a part thereof, that by an amendment the complaint could be made to state a valid cause of action against the surety, the action of the court in granting leave to serve and file such an amended complaint was a proper exercise of discretion, to deny which would have been an abuse of discretion. The same rule here applies as in actions to vacate judgments where defendant has wholly defaulted. In case of doubt the court should so rule as to permit a trial on the merits, rather than deny relief. Although it is urged that a six months’ delay ensued between the submission of the merits, with the motion to vacate, in IVIarch, and the final ruling in September, this is not imputable to the parties to the action, and cannot amount to laches on the part of the plaintiff in moving the vacation of this judgment. No authorities cited as sustaining the appellant’s contention are applicable. The only question on this appeal is the propriety of the court’s order granting leave to serve and file an amended complaint, and this is determined by whether it can be reasonably inferred, from the matter-stated in the complaint and attached undertaking and bond, that a cause of action may be stated against the [609]*609surety by an amended pleading. This leads to a brief statement of the contents of the building contract and the bond, as the two must be construed together and as one instrument, both by the terms of the bond itself and the rules of law as to the construction of building contracts and bonds. Bender & Moss, Mechanics’ Liens, § 217; Utah Lumber Co. v. James, 25 Utah, 434, 71 Pac. 986.

The building contract provides for the furnishing of labor and material and all things “necessary for the complete construction of said building strictly in accordance with plans, specifications, and details,” for an agreed consideration of $7,540, to be paid according to the conditions of the contract. The complaint charges a failure on the part of the contractor to pay for building material, resulting in a lien for $2,-673 being filed by materialmen upon said building, and the failure of the contractor and the surety to, after demand, procure the discharge of said lien, and that the principal and surety on the bond have therefore violated the terms of the bond. The plans, specifications, and details referred to are not a part of the complaint and are not before us, although mentioned in both the building contract and the building bond, and are to be construed in connection with them. The bond does not bind the principal to perform, nor does it, considered alone, afford the basis for any liability against either the principal or surety. It is plainly evident that the provisions usual to such bonds, obligating the principal and surety to perform the building contract according to the terms of said contracts, plans, and specifications, were omitted, rendering the bond on its face a nullity. It reads as follows:

Know all Men by these presents, That Heinrich Baumgartner, as principal and C. F. Ewald, as surety, of the County of Stark, and Morton and State of North Dakota, held and firmly bound unto Taylor State Bank of Taylor, Stark County, North Dakota, in the sum of Two Thousand 00 — 100 Dollars lawful money of the United States to be paid to the said Taylor State Bank of Taylor, N. Dak., for which payment well and truly to be made we bind ourselves, our executors and administrators, jointly and severally, firmly by these presents.

Dated this first day of September, A. D. 1908.

The conditions of the above obligation are such that Heinrich Baum[610]*610gartner has been awarded the contract for the construction and erection of a brick building, in the village of Taylor, in a first class and workmanlike manner and to provide all the material for the said building according to drawings and specifications prepared by O. A. Bloom of Dickinson, N. D. and signed by the parties thereto on the 1st day of ¡September, 1908, then the obligation to be void; otherwise to remain in full force and virtue.

Heinrich Baumgartner,

C. E. Ewald.

But it does not necessarily follow that the complaint cannot be so amended as to state a cause of action based on the contract, bond, and breach assigned in the original complaint. The purpose of the bond, and that it was to insure performance of the building contract, are apparent from the instruments themselves. Evidently the omission of the usual stipulation in the bond, insuring the performance of the contract according to its terms, was but the mistake of the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Emick v. Swafford
191 P. 490 (Supreme Court of Kansas, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
147 N.W. 385, 27 N.D. 606, 1914 N.D. LEXIS 78, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taylor-state-bank-v-baumgartner-nd-1914.