Taylor Group, Inc. v. Johnson

915 F. Supp. 295, 40 Cont. Cas. Fed. 76,931, 1995 U.S. Dist. LEXIS 20297, 1995 WL 810337
CourtDistrict Court, M.D. Alabama
DecidedNovember 27, 1995
DocketCA 94-D-1254-S
StatusPublished
Cited by4 cases

This text of 915 F. Supp. 295 (Taylor Group, Inc. v. Johnson) is published on Counsel Stack Legal Research, covering District Court, M.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taylor Group, Inc. v. Johnson, 915 F. Supp. 295, 40 Cont. Cas. Fed. 76,931, 1995 U.S. Dist. LEXIS 20297, 1995 WL 810337 (M.D. Ala. 1995).

Opinion

MEMORANDUM OPINION AND ORDER

DE ME NT, District Judge.

Before the court is Plaintiff The Taylor Group, Inc.’s application filed November 14, 1994, for fees, expenses and costs under the Equal Access to Justice Act, 28 U.S.C. § 2412. The United States responded in opposition on December 12, 1994. For the reasons stated herein, the court will reserve ruling on the plaintiffs application for attorney fees.

BACKGROUND

The plaintiff filed the above-styled action on September 29, 1994, against agents of the Environmental Protection Agency (“EPA”) and the General Services Administration (“GSA”). The complaint sought declaratory and equitable relief under the Competition in Contracting Act, 31 U.S.C. §§ 3551-3556. As the incumbent contractor, the plaintiff challenged the GSA’s proposed award of a three-month emergency procurement contract for security guard services at the EPA headquarters at the Waterside Mall in Washington, D.C. The plaintiff had been providing these services for the EPA under a contract that included a base period of three months plus four concurrent one-year options. When this dispute arose, the plaintiff was performing under the first option, which ran from October 1, 1993, to September 30, 1994.

In sum, the complaint alleged that the EPA sought to terminate the plaintiffs contract due to a dispute between it and the EPA regarding an error in the solicitation regarding wage rate adjustments for the one-year contract term commencing October 1, 1994. According to the plaintiff, the EPA stated that it would correct the solicitation error during contract performance. The plaintiff asserts that based upon this representation, it did not file a protest and bid as instructed by the EPA.

The plaintiff further asserted that the EPA did not honor its representation and that after being forced to pay the disputed wage increase, the EPA notified the plaintiff that its option would not be exercised despite the EPA’s previous preliminary notice of intent to do so. The plaintiff alleged that even though its services were satisfactory, the EPA engaged the GSA to issue a three-month emergency services procurement contract to begin October 1, 1994, so that the EPA could re-write the solicitation and oust the plaintiff from the project.

By letter dated August 30,1994, 1 the plaintiff filed a protest with the General Accounting Office (“GAO”) challenging the necessity of an “emergency” contract and the award of the contract to Mid-Atlantic Security Ser *297 vices, Inc. 2 Under 31 U.S.C. § 3553(c)(1), the plaintiff’s timely-filed protest imposed an automatic stay against the award and performance of the contract pending the GAO’s resolution of the plaintiffs protests. In its protests, the plaintiff requested, in part, that the Comptroller General recommend to the GSA to cancel the award and performance of the contract to Mid-Atlantic Security Services, Inc., and to exercise the plaintiffs option in its current contract. The plaintiff alleged that the GSA never responded to its protests and that, subsequently, the GSA informed the plaintiff that it was overriding the stay pursuant to the statutory provision that allows such an override if the agency determines that urgent and compelling circumstances exist. See 31 U.S.C. § 3553(c)(2).

The plaintiff then commenced this action. The next day, on September 30, 1994, the plaintiff filed a motion for a temporary restraining order and preliminary injunction, requesting the court to compel the GSA and the EPA to stay the award of the contract pending resolution of the plaintiffs protests. The plaintiff argued that “urgent and compelling circumstances” did not necessitate the emergency procurement since it was ready, willing and able to perform the services.

By order entered September 30, 1994, the court issued a temporary restraining order and enjoined for twenty days the performance of the contract by Mid-Atlantic Security Services, Inc. Thereafter, on October 12, 1994, the parties entered into a settlement agreement, which is part of the record. Pursuant to the terms of the settlement agreement, the GSA and the EPA terminated the contract aWarded to Mid-Atlantic Security Services, Inc., canceled the solicitation and extended the plaintiffs contract for an additional six months from October 1, 1994, through March 31, 1995. Having received the relief requested and in accordance with the terms of the settlement agreement, the plaintiff filed a Notice of Dismissal of the above-styled cause. The court dismissed the lawsuit without prejudice on October 13, 1994. The plaintiffs motion for attorneys fees followed.

DISCUSSION

The Equal Access to Justice Act (“EAJA”), 28 U.S.C. § 2412, governs the award of fees in this case and provides that in a lawsuit against the United States, the “prevailing party in any civil action” may seek payment for costs, reasonable fees and expenses of attorneys incurred in the litigation. 28 U.S.C. § 2412(a)(1) & (b). The award of fees is mandatory unless the court “finds that the position of the United States was substantially justified or that special circumstances make an award unjust.” 28 U.S.C. § 2412(d)(1)(B). The court’s award, denial or reduction of fees will not be overturned absent an abuse of discretion. Pierce v. Underwood, 487 U.S. 552, 559, 108 S.Ct. 2541, 2547, 101 L.Ed.2d 490 (1988). The United States argues that an award is inappropriate because the position of the United States was substantially justified and that, in the alternative, special circumstances existed for denying an award under the EAJA

Before addressing the United States’ contentions, the court must determine whether the plaintiff is a “prevailing party” within the meaning of the EAJA. A party can qualify as a “prevailing party,” not only by obtaining a favorable judgment after a trial on the merits, but also through a successful termination of the litigation by a consent decree or out-of-court settlement. Martin v. Heckler, 773 F.2d 1145, 1149 (11th Cir.1985) (citation omitted); 28 U.S.C. § 2412(d)(2)(H). All that is required is that the party obtain some relief on the merits of his or her claims. In other words, the plaintiffs lawsuit merely must act as a “‘catalyst’ ” in causing the United States to satisfy some of the benefit sought by the plaintiff in bringing the lawsuit. See Citizens Coalition for Block Grant Compliance v. City of Euclid,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Aisenberg
247 F. Supp. 2d 1272 (M.D. Florida, 2003)
S.J. Thomas Co. v. United States
47 Fed. Cl. 272 (Federal Claims, 2000)
Ramcor Services Group, Inc. v. United States
42 Cont. Cas. Fed. 77,327 (Federal Claims, 1998)
Taylor Group, Inc. v. Johnson
919 F. Supp. 1545 (M.D. Alabama, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
915 F. Supp. 295, 40 Cont. Cas. Fed. 76,931, 1995 U.S. Dist. LEXIS 20297, 1995 WL 810337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taylor-group-inc-v-johnson-almd-1995.