Taunton Municipal Lighting Plant v. Enron Corp. (In Re Enron Corp.)

354 B.R. 652, 2006 U.S. Dist. LEXIS 59389, 2006 WL 2463658
CourtDistrict Court, S.D. New York
DecidedAugust 23, 2006
Docket05 Civ. 10164(JGK)
StatusPublished
Cited by6 cases

This text of 354 B.R. 652 (Taunton Municipal Lighting Plant v. Enron Corp. (In Re Enron Corp.)) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taunton Municipal Lighting Plant v. Enron Corp. (In Re Enron Corp.), 354 B.R. 652, 2006 U.S. Dist. LEXIS 59389, 2006 WL 2463658 (S.D.N.Y. 2006).

Opinion

OPINION AND ORDER

KOELTL, District Judge.

The appellant, Taunton Municipal Lighting Plant (“Taunton”), appeals from an *654 order of the United States Bankruptcy Court for the Southern District of New York (Arthur J. Gonzalez, J.) disallowing and expunging Taunton’s proof of claim filed against the debtors/appellees, Enron Corporation and certain of its affiliates (collectively “Enron”). The Bankruptcy Court’s decision is published at 330 B.R. 387 (Bankr.S.D.N.Y.2005) under the title In re Enron Corp. For the reasons explained below, the order of the Bankruptcy Court is affirmed.

I.

When reviewing an order of the Bankruptcy Court, this Court acts as an appellate court. Accordingly, this Court reviews the Bankruptcy Court’s conclusions of law de novo but accepts that court’s findings of fact unless they are “clearly erroneous.” See Fed. R. Bankr.P. 8013; see also In re Halstead Energy Corp., 367 F.3d 110, 114 (2d Cir.2004).

II.

The Bankruptcy Court made the following findings of fact, which this Court accepts because they are supported by the record and no party has argued that they are clearly erroneous.

Taunton is a Massachusetts municipal public power utility licensed by the Commonwealth of Massachusetts to provide electricity to the residents of the city of Taunton, Massachusetts, and several neighboring towns. In re Enron Corp., 330 B.R. at 388. On November 2, 2001, Taunton entered into a contract with a subsidiary of Enron that provided for Enron to sell electricity to Taunton from January 1, 2002 until December 31, 2007. Id. at 387-88. On December 2, 2001, one month after entering into this contract, Enron commenced the bankruptcy action in which Taunton’s current claim arose. Id. at 388. Despite Enron’s filing of a bankruptcy petition, Taunton honored the contract and bought electricity from Enron at the price established in the contract, although electricity was available to Taun-ton from other sources at a lower price in early 2002. Id.

During 2002 the parties discussed soliciting replacement suppliers to provide electricity to Taunton but Enron continued to deliver electricity to Taunton during those negotiations. Id. On December 17, 2002, after electricity prices had risen higher than the price established in its contract with Taunton, Enron rejected the contract and ceased delivering electricity to Taunton on December 31, 2002. Because the contract specified that damages in the event of breach would be calculated based on the actual economic loss to the non-breaching party at the time of the breach, Taunton requested bids from other power providers and, based on the bids received, calculated that it had sustained damages of $6,658,885.00 (including $64,000 in costs). On November 24, 2003, Taunton filed its claim against Enron in that amount with the Bankruptcy Court, and Enron filed an objection to Taunton’s claim on February 16, 2005. On September 21, 2005, the Bankruptcy Court issued its decision sustaining Enron’s objection. On October 7, 2005, the Bankruptcy Court entered the order disallowing the claim. As explained in greater detail below, the Bankruptcy Court concluded that the plain language of Section 502(g) of the Bankruptcy Code required that damages resulting from the rejection of the contract be calculated as of the last business day before the filing of the bankruptcy petition on December 2, 2001, and that, using that date, there were no damages to Taunton. See In re Enron, 330 B.R. at 389 & nn. 3 & 4, 392.

On this appeal, Taunton does not dispute that it suffered no damages from Enron’s breach of its contract to supply Taunton with electricity for the duration of the contract, if those damages are determined *655 on the last business day before Enron filed its bankruptcy petition. Taunton contends that the date of rejection of the contract should be the appropriate measuring date for determining damages from the breach. The Bankruptcy Court correctly concluded that damages should be measured from the last business day before filing the petition and not on the day the debtor rejected the contract.

III.

A.

The effective date of Enron’s rejection of its contract with Taunton is established by Section 365(g)(1) of the Bankruptcy Code, which provides that the rejection of an executory contract “constitutes a breach of such contract ... immediately before the date of the filing of the petition” in the Bankruptcy Court. 11 U.S.C. § 365(g)(1). This provision is intended to allow a debtor, after filing a bankruptcy petition, to reject a contract rather than continue to abide by the contract.

Section 502(g) of the Bankruptcy Code, in the version in force at the time of Taunton’s claim, further provided that a

“claim arising from the rejection, under section 365 of this title ... of an execu-tory contract ... shall be determined, and shall be allowed under subsection (a), (b), or (c), of this section or disallowed under subsection (d) or (e) of this section, the same as if such claim had arisen before the date of the filing of the petition.”

11 U.S.C. § 502(g). 1

It is clear that this version of Section 502(g) “cause[d] a rejection damage claim to be classified as a pre-bank-ruptcy claim,” such that the other party to the contract has a claim equal to those of other creditors having unsecured claims against the debtor at the time the petition was filed. In re American HomePatient, Inc., 414 F.3d 614, 618 (6th Cir.2005). Taunton argues that Section 502(g) was intended to do no more, and that the Bankruptcy Court misinterpreted the statute when it concluded that Section 502(g)’s text also required calculating damages resulting from a rejection claim based on what the damages would have been on the last business day before the date of the petition. Taunton asserts that the purpose of Sections 365(g) and 502(g) of the Bankruptcy Code was to create a legal fiction that ensures that claims arising from exec-utory contracts rejected by the debtor are treated the same as claims arising before the petition. Taunton further asserts that this goal could be accomplished without using the last business day before the petition was filed for calculating damages under such a claim, and that there is no support in the legislative history of either section for also using that date to calculate damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

47 Hops LLC
E.D. Washington, 2020
In re Lehman Bros. Holdings Inc.
602 B.R. 564 (S.D. New York, 2019)
Heller v. Emanuel (In Re Emanuel)
450 B.R. 1 (S.D. New York, 2011)
TSIC Inc. v. Thalheimer (In Re TSIC, Inc.)
428 B.R. 103 (D. Delaware, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
354 B.R. 652, 2006 U.S. Dist. LEXIS 59389, 2006 WL 2463658, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taunton-municipal-lighting-plant-v-enron-corp-in-re-enron-corp-nysd-2006.