Taunton Municipal Light Plant Commissioon v. Paul L. Geiringer & Assocs.

560 F. Supp. 1249, 1983 U.S. Dist. LEXIS 18125
CourtDistrict Court, D. Massachusetts
DecidedMarch 30, 1983
DocketCiv. A. 82-695-N
StatusPublished
Cited by4 cases

This text of 560 F. Supp. 1249 (Taunton Municipal Light Plant Commissioon v. Paul L. Geiringer & Assocs.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taunton Municipal Light Plant Commissioon v. Paul L. Geiringer & Assocs., 560 F. Supp. 1249, 1983 U.S. Dist. LEXIS 18125 (D. Mass. 1983).

Opinion

MEMORANDUM AND ORDER

DAVID S. NELSON,. District Judge.

On February 24, 1982, Taunton Municipal Light Plant Commission (Taunton) commenced this cause of action in the Superior Court for the Commonwealth of Massachusetts pursuant to Mass.G.L. c. 251, § 12(a)(3). Taunton moved the Superior Court to vacate paragraph 1(a) Claim No. 9 of an arbitral award rendered by the American Arbitration Association in favor of Paul L. Geiringer & Associates (Geiringer). Thereafter, the defendant filed a petition for removal to federal court based upon diversity of citizenship and also sought the confirmation of the arbitral award. The petition for removal was granted in accordance with the law. 28 U.S.C. § 1332; 28 U.S.C. § 1441. All jurisdictional prerequisites have been met, 1 and review of the arbitrators’ decision is properly before this court. See Mass.G.L. c. 251, §§ 11 and 15.

The gravamen of the plaintiff’s complaint is that the arbitrators, acting as “contemporary Solomon[s],” disregarded the governing contractual agreement, “and dispensed their own brand of industrial justice” in adjudicating the claims of the parties. I must disagree: A recitation of the facts of the case will illuminate the erroneousness of the plaintiff’s averments. This dispute involves a design and construction contract entered into by Geiringer with Taunton. The Agreement for Consulting Engineering Services, dated December 15, 1982, provides for the utilization of Geiringer’s consulting engineering services in connection with the expansion of Taunton’s power plant facilities. Paragraph 5, page 13 of the contract provides, inter alia:

All questions which may be disputed under this agreement shall be submitted to arbitration by the American Arbitration Association, Boston, Massachusetts, at the choice of either party of this contract according to the rules applicable to the construction industry.

Following the completion of the project, Taunton presented a demand to the American Arbitration Association for the arbitration of certain claims which had arisen between the parties during the performance of the contract. The defendant filed a counterclaim demanding that Taunton pay the monetary balance due under the agreement.

On February 3, 1982, the Award of Arbitrators was issued disposing of the demands submitted by the parties. The source of Taunton’s consternation is the arbitral disposition of Claim No. 9 which concerns “as-built drawings.” Claim No. 9 of the decision states:

As Built Drawings: Monetary damages are denied, however[,] it is determined that Taunton Municipal Lighting Plant shall be responsible for obtaining all required as-built drawings (original tracings and 9 sets of prints) from all [of] the prime contractors for delivery to Paul L. Geiringer Associates by May 1, 1982, for assembly with their own as-built drawings in accordance with Scope of Work Item (w) for delivery to Taunton Municipal Lighting Plant by August 1, 1982. It is incumbent upon both parties to perform this duty. 2

The Consulting Agreement between the parties required that Geiringer “provide 8 *1251 sets of as-built prints and the as-built original tracings to become the property of Taunton Municipal Light Plant Commission together with associated reports.” Consequently, Taunton argues that this court should overturn paragraph 1(a) Claim No. 9, since it is incongruous with and violative of the specific provision set forth in the contract. 3

Furthermore, Taunton has refused to release certain funds placed in escrow by the parties to this dispute. To insure payment of any potential judgment against one of the parties to the arbitral proceeding, Taunton and Geiringer jointly purchased a Money Market Certificate (Jumbo Certificate No. 18000002-8). This certificate was purchased from the Taunton Savings Bank in the sum of $164,449.32, and held in escrow by the bank. The purpose of the certificate is revealed in paragraph 6 of the Stipulation:

The principal amount together with any accrued interest shall be held pending a decision in the case of Taunton Municipal Light Commission v. Paul L. Geiringer & Associates pending before the American Arbitration Association, No. 1110-0008-78, and said amount shall satisfy any award made by the American Arbitration Association against Paul L. Geiringer & Associates in said case, [emphasis mine]. The principal amount, together with accrued interest, not used to satisfy any award as aforesaid shall be paid over to Paul L. Geiringer & Associates within (5) days after the delivery of any award to the parties to said arbitration proceeding.

By the very terms of the preceding provision, if no (money award resulted from the arbitral proceeding, the funds in escrow were to be turned over to Geiringer within 5 days. No money award resulted from the arbitral proceeding. Yet, the funds remain in escrow. Allen Ross, attorney for Geiringer, has made a demand on the Taunton Savings Bank (February 12, 1982); the demand was repudiated.

Taunton alleges that the arbitrators exceeded the scope of their authority. Therefore, they have refused to comply with paragraph 1(a) Claim No. 9 of the award. Taunton insists that Geiringer obtain all as-built drawings from prime contractors. Geiringer is fully prepared to comply with paragraph 1(a) Claim No. 9 of the arbitral award. Attorney Allen Ross, by a letter dated May 12, 1982, offered assistance to Taunton. He wrote:

Notwithstanding Geiringer’s clear and unambiguous' legal position concerning the Commission’s continuing efforts to damage Geiringer by refusing to release the escrow deposit, without waiver of or prejudice to Geiringer’s legal position or any rights related thereto, Geiringer is prepared to cooperate with the Commission and to assist in obtaining the necessary as-built drawings, etc.

Thus, the litigants are before the court praying for the resolution of this conflict. I am therefore legally constrained to conclude that the arbitrators neither exceeded their powers or authority in the disposition of the claims presented, nor did they violate the terms of the submission presented for arbitration. The decision of the arbitrators unquestionably comported with the requirements of law, the arbitral agreement, fundamental notions of justice and fairness. I am obliged to confirm the arbitral award.

The law governing the confirmation or vacation of arbitral decisions is settled in Massachusetts. The Uniform Arbitration Act mandates the confirmation of arbitral awards save in a few well-established circumstances. See Mass.G.L. c. 251, § 12(a)(l-5). 4 It is an immutable principle of law that arbitration awards are viewed *1252 with great deference; this judicial deference extends to the area of remedies. Courier-Citizen Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vernon Vu Luong v. Circuit City Stores, Inc.
356 F.3d 1188 (Ninth Circuit, 2004)
Advest, Inc. v. Patrick McCarthy
914 F.2d 6 (First Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
560 F. Supp. 1249, 1983 U.S. Dist. LEXIS 18125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taunton-municipal-light-plant-commissioon-v-paul-l-geiringer-assocs-mad-1983.