T. Towles & Co. v. County Court of Summers County

121 S.E. 93, 95 W. Va. 310, 1924 W. Va. LEXIS 2
CourtWest Virginia Supreme Court
DecidedJanuary 9, 1924
StatusPublished
Cited by2 cases

This text of 121 S.E. 93 (T. Towles & Co. v. County Court of Summers County) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T. Towles & Co. v. County Court of Summers County, 121 S.E. 93, 95 W. Va. 310, 1924 W. Va. LEXIS 2 (W. Va. 1924).

Opinion

MeRedith, President :

Plaintiffs sued in assumpsit to recover tbe balance of the contract price on a contract for road work. Tbe amount claimed was $10,306.88, with certain interest. The jury returned a verdict in their favor for $67.54, which the court refused to set aside on plaintiff’s motion, and they assign error.

On July 18, 1919, plaintiffs entered into a written contract with defendant County Court for the permanent improvement of 26,400 lineal feet of what is known as the Pipestem Road. They completed 9750 feet of it and were relieved from the remainder. No question arises as to the quality of the work; the completed portion was accepted and defendant claims that it was fully paid for, except the small amount found by the jury, due to error in calculation of the county engineer. The road was not to be hard-surfaced, but to be put on a grade, certain concrete work was to be done and certain metal drain pipe was to be furnished and put in place. All this was done. All work was to be done and all materials furnished at specified unit prices. The concrete work and metal drain pipe have been paid for. The sole controversy now arises over the amount of grading or yardage. The excavation was the chief item under the contract, as other items amount to only about $2000.00. Plaintiffs were to be paid 67 cents per cubic yard for the excavation and they claim that the total amount done was 68,708.8 cubic yards; defendant originally claimed the total yardage was *313 53,325.4, and that it had paid for that amount. During the trial, defendant admitted an error in its account of 100.8 cubic yards, and it was for this that plaintiffs obtained a verdict and judgment. The 53,325.4 yards and the 100.8 yards, or a total of 53,426.2 yards, is what defendant now contends is the correct yardage. The present difference in their figures is 15,282.6 cubic yards. This does not arise upon mere calculation of the actual amount of excavation, as plaintiffs clearly proved that they moved 68,708.8 cubic yards of material and this is not denied by defendant; but defendant shows plaintiffs have been paid for 53,325.4 yards, have judgment for the 100.8 yards, and presents the following defenses to their claim for the 15,282.6 yards: — (1) that the extra yardage, if any, was excavated for the convenience of the plaintiffs, by their going off or changing the designated route; (2) that it was due to plaintiffs’ carelessness in shooting too heavy charges, thus causing unnecessary breakage and slides; and (3) that the estimates of the yardage made by defendant’s engineer are binding and conclusive, and that he has found against this contention.

The contract is the standard form used at that time by the State Road Commission. The following sections of it are material upon this inquiry:

“32. Unauthorized work. Work done without lines and grades being given, work done beyond the lines and grades shown on the plan or as given, except as herein provided, or any extra work done without written authority will be considered as unauthorized and at the expense of the contractor and will not be measured or paid for by the county. Work so done may be ordered removed and replaced at the contractor’s expense.”
“41. Use of explosives. Where the use of explosives is necessary for the prosecution of the work, the contractor shall use the utmost care, so as not to endanger life or property, and whenever directed the number and size of the charges shall be reduced.”
“52. Line, Grade and Measurement Stakes. The Engineer will furnish and set all original grade, slope and line stakes. The contractor shall furnish, free of charge, all additional stakes, all templets and other ma *314 terials necessary for marking and maintaining points and lines given, and shall furnish the inspector such assistance as he may require in giving points and lines necessary to the prosecution of the work. The contractor shall be held responsible for the preservation of all stakes and marks and if in the opinion of the engineer, any of the survey stakes or marks have been carelessly or wilfully destroyed or disturbed by the contractor, the cost to the court of replacing them shall be charged against him and shall be deducted from the payment for the work. Finished surfaces, in all cases, shall conform with the lines and grades given as shown on the approved plans. ’ ’
“55. Engineer to• be referee. To prevent misunderstanding and litigation, the engineer shall decide any and all questions which may arise as to the quality and acceptability of materials furnished and work performed and as to the manner of performance and rate of progress of said work and shall decide all questions which may arise as to the interpretation of any or all plans relating to the work and of the specifications, and all questions as to acceptable fulfillment of the contract on the part of the contractor; and the engineer shall determine the amount and quantity of the several kinds of work performed and materials furnished which are to be paid for under the contract, and such decision and estimate shall be final and conclusive, and such estimates, in case any question shall arise, shall be a condition precedent to the right of the Contract to receive any money duq under the contract. Any doubt as to the meaning of or any obscurity as to the working of these specifications and contract will be explained by, and all directions and explanations requisite or necessary to complete, explain or make definite any of the provisions of the specifications or contract and to give them due effect, will be given by the engineer.”
“66. Partial Payments. The Engineer will make current estimates in writing, once each month on or before the date set by the Engineer at the time of starting the work, or from time to time as the work progresses, of the materials in place complete and the work performed in accordance with the contract, during the preceding month or period and the value thereof figured at the unit prices contracted. From the total of the amounts so ascertained will be deducted an amount equivalent to ten (10%) per centum of the whole, to *315 be retained by the court until after the completion of the entire contract in an acceptable manner, and the balance, or a sum equivalent to ninety (90) per centum of the whole, shall be certified by the engineer to the county court for payment, except when such balance amounts to less than five hundred dollars ($500.00). * # «> >
“67. Acceptance and final payment. Whenever, in the opinion of the engineer, the contractor shall have completed the roadway in an acceptable manner in accordance with the terms of the contract, the engineer and the county court shall make a final inspection of the entire roadway and, upon completion of all necessary repairs or renewals, the county court shall enter an order accepting the completed roadway. The final estimate shall then be made by the engineer within 30 days of the date of the said order of acceptance or as soon thereafter as practicable, and the contractor paid the full amount due.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Henderson Development Co. v. United Fuel Gas Co.
3 S.E.2d 217 (West Virginia Supreme Court, 1939)
Monto v. Gillooly
147 S.E. 542 (West Virginia Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
121 S.E. 93, 95 W. Va. 310, 1924 W. Va. LEXIS 2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/t-towles-co-v-county-court-of-summers-county-wva-1924.