T & M PROPERTIES v. ZVFK Architects and Planners

661 P.2d 1040, 1983 Wyo. LEXIS 304
CourtWyoming Supreme Court
DecidedApril 14, 1983
Docket5786
StatusPublished
Cited by25 cases

This text of 661 P.2d 1040 (T & M PROPERTIES v. ZVFK Architects and Planners) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T & M PROPERTIES v. ZVFK Architects and Planners, 661 P.2d 1040, 1983 Wyo. LEXIS 304 (Wyo. 1983).

Opinion

BROWN, Justice.

Appellee entered into a contract with Miracle Enterprises dated February 9,1977, and contracts with appellant T & M Properties dated February, 1977 (day of month blank in this contract) and September 1, 1977. The Miracle Enterprises contract was signed by Tim C. Miracle, owner, president. The T & M Properties contracts were signed by Tim C. Miracle, owner, partner. The three contracts were for architectural and planning services to be rendered by appellee. Each contract contained a provision for arbitration. The basic language read:

“All claims disputes and other matters in question arising out of, or relating to, this Agreement or the breach thereof shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law.”

Appellee invoked the arbitration clauses in the contracts and initiated arbitration when a dispute arose regarding the amount of fees owed. Appellee caused to be prepared and executed a demand for arbitration. 1 This demand was directed to T & M Properties, Tim C. Miracle and Marilyn Krueger, 630 East First, P.O. Box 2160, Casper, Wyoming 81601. In the demand, reference was made to contracts dated “2/9/77, 2/9/77 [sic] 9/1/77.” Attached to the demand was the contract entered into February, 1977, between appellee and T & M Properties.

On May 22, 1981, the tribunal administrator for the American Arbitration Association wrote a letter to the parties giving notice that they had received a copy of the demand for arbitration. This letter told appellants of their right to counterclaim and the rule regarding site of the arbitration hearing. A former attorney for appellants entered into correspondence with the *1042 tribunal administrator and participated in the selection of an arbitrator and the place of the hearing. 2

The arbitration hearing was held October 22, 1981. Appellants elected not to attend, although notified. The award was rendered November 2, 1981, in favor of appel-lee in the sum of $17,726.50, plus $5,870.78 interest. On November 6, 1981, appellants were mailed a copy of the award. On January 28, 1982, appellee filed a petition for recognition of award and judgment in the district court. Appellants answered on April 23,1982, alleging defenses and asking that the award be vacated. Appellee’s motion for a summary judgment was granted August 20, 1982. The appeal is from this judgment.

The issues are:

1. Are the appellants’ defenses raised in their answer to appellee’s petition for recognition of award and judgment barred by the provisions of § 1-36-114(b), W.S.1977, because they were not made within 90 days of receipt of the arbitration award?
2. Did appellants receive adequate notice of what issues were arbitrated?
3. Did the arbitrator have the power to award interest on appellee’s claims?

We will affirm.

I

Section 1-36-113, W.S.1977, provides:

“Upon application of a party the court shall confirm the award unless within the time limits allowed grounds are urged for vacating or modifying the award.”

Section l-36-114(b), W.S.1977, provides:

“An application for vacating an award shall be made within ninety (90) days after delivery of a copy of the award to the applicant, or if predicated upon corruption, fraud or other undue means it shall be made within ninety (90) days after the grounds are known or should have been known.”

On November 6, 1981, appellants were mailed a copy of the award. On January 28, 1982, appellee filed a petition for recognition of award and judgment in district court under § 1-36-113, supra. Appellants contend that since appellee filed a petition under § 1-36-113, supra, then they are allowed to assert affirmative defenses regardless of the 90-day time proscriptions of § l-36-114(b), supra. Appellee argues that the time limits of this statute apply.

Courts have ruled differently on this issue, but we think the better reasoned rule is that the time limits set out in § 1-36-114(b), supra, are applicable. It seems that the majority of jurisdictions which have adopted the Uniform Arbitration Act (7 Uniform Laws Annotated, 1978) follow this rule. In Chauffeurs, Teamsters, Warehousemen and Helpers, Local Union No. 135 v. Jefferson Trucking Company, Inc., 628 F.2d 1023 (7th Cir.1980), the court decided the question under an Indiana statute which provided:

“ ‘Confirmation of an award.' — Upon application of a party, but not before ninety [90] days after the mailing of a copy of the award to the parties, the court shall confirm an award, unless within the time limits hereinafter imposed grounds are urged for vacating or modifying or correcting the award, in which case the court shall proceed as provided in sections 13 and 14 of this act. * * * ’ ” 628 F.2d at 1026.

The fact that a party opposing an award delays in complying with it and effectively forces the other party into court to enforce the award should not accrue to the delaying party’s benefit.

“ * * * As the district court observed, this policy [of requiring a motion to vacate or an answer filed within the original 90-day period] would seem to condemn the conduct of the defendant who ignored an award disfavorable to it, failed to move to vacate the award, and then sought to be given its day in court when the plaintiff brought its suit in frustration to have the arbitration award enforced. If the defendant’s defenses were of such vital importance to it, the *1043 defendant nevertheless had an opportunity to raise them in the manner contemplated by statute.” Chauffeurs, Teamsters, Warehousemen and Helpers, Local Union No. 135 v. Jefferson Trucking Company, Inc., supra, at 1027.

Arbitration provides for voluntary settlement of disputes in an inexpensive and expeditious manner without resort to a tribunal and conducted without the rigid formality of strict rules of law. Riverton Valley Electric Association v. Pacific Power and Light Company, Wyo., 391 P.2d 489 (1964). Arbitration is embedded in the public policy of Wyoming and is favored by this court. Matter of Town of Greybull, Wyo., 560 P.2d 1172 (1977). 3 The short time period set out in § l-36-114(b), supra, gives the arbitration award finality by forcing a party who opposes to petition the courts within 90 days.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James Valley Grain, LLC v. David
2011 ND 160 (North Dakota Supreme Court, 2011)
State ex. rel. Schlect v. Wolff
2011 ND 164 (North Dakota Supreme Court, 2011)
Vogt v. MBNA America Bank
2008 WY 26 (Wyoming Supreme Court, 2008)
Welty v. Brady
2005 WY 157 (Wyoming Supreme Court, 2005)
Wallace v. Hayes
2005 MT 253 (Montana Supreme Court, 2005)
Simon v. Teton Board of Realtors
4 P.3d 197 (Wyoming Supreme Court, 2000)
Fernandez v. Farmers Ins. Co. of Arizona
857 P.2d 22 (New Mexico Supreme Court, 1993)
United Technology & Resources, Inc. v. Dar Al Islam
846 P.2d 307 (New Mexico Supreme Court, 1993)
JBC of Wyoming Corp. v. City of Cheyenne
843 P.2d 1190 (Wyoming Supreme Court, 1992)
Jackson State Bank v. Homar
837 P.2d 1081 (Wyoming Supreme Court, 1992)
Walter A. Brown, Inc. v. Moylan
509 A.2d 98 (District of Columbia Court of Appeals, 1986)
Jaffe v. Nocera
493 A.2d 1003 (District of Columbia Court of Appeals, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
661 P.2d 1040, 1983 Wyo. LEXIS 304, Counsel Stack Legal Research, https://law.counselstack.com/opinion/t-m-properties-v-zvfk-architects-and-planners-wyo-1983.