T. Equipment v. Mass. Laborers

CourtCourt of Appeals for the First Circuit
DecidedJanuary 20, 1999
Docket98-1148
StatusPublished

This text of T. Equipment v. Mass. Laborers (T. Equipment v. Mass. Laborers) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T. Equipment v. Mass. Laborers, (1st Cir. 1999).

Opinion

United States Court of Appeals For the First Circuit

No. 98-1148

T. EQUIPMENT CORP. and C.R.C. CO., INC.,

Plaintiffs, Appellees,

v.

MASSACHUSETTS LABORERS' DISTRICT COUNCIL,

Defendant, Appellant.

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF MASSACHUSETTS

[Hon. Joseph L. Tauro, U.S. District Judge]

Before

Selya, Circuit Judge, Bownes, Senior Circuit Judge, and Stahl, Circuit Judge.

Theodore T. Green, with whom Michael S. Bearse, Michelle Simon, Laborers' International Union of North America, were on brief for appellant.

James F. Grosso with whom O'Reilly & Grosso, P.C. were on brief for appellees.

January 15, 1999

BOWNES, Senior Circuit Judge. This is an appeal from the district court's grant of summary judgment to plaintiffs-appellees T. Equipment Corporation and C.R.C. Co., Inc. (Contractors) and its denial of defendant-appellant's Massachusetts Laborers' Union District Council (Laborers) motion for summary judgment. The case arises from a jurisdictional dispute between Local 24 of the Carpenters Union (Carpenters) and the Laborers about the allocation of "stripping" work for plaintiffs-contractors. The issue before us has not been directly addressed before by this circuit: What is the consequence of an arbitration award for damages to one union (Laborers) because of the breach of a collective bargaining agreement by the employers of members of that union in the face of an NLRB decision under 29 U.S.C.A. 160(k)(10(k)) awarding the underlying work to another union (Carpenters)? The district court found that the NLRB 10(k) decision nullified the damages award. We affirm. I The facts are not in dispute. The plaintiffs-contractors were subcontractors to J.F. White Contracting Company. White was the main contractor for the construction of new railroad stations and the renovation of railroad bridges to facilitate the extension of commuter rail service on the Old Colony Railway. T. Equipment's subcontract required bridge repair and structural work on the rail system. C.R.C.'s subcontractual work entailed building the substructural concrete foundations for the railroad stations. Both subcontracts involved extensive concrete work. Casting concrete requires the use of wood or metal forms into which the concrete is poured. After the concrete has hardened sufficiently so that it can stand on its own, the forms are "stripped" from the concrete and moved to the site of the next job. There was a long-standing collective bargaining agreement between the Massachusetts Contractors Association and the Laborers to the effect that "stripping" would be done jointly by members of the Carpenters' and Laborers' Unions. The latest manifestation of this agreement was a letter from the Laborers' Union representative to J.F. White dated October 7, 1994, stating: "It was also agreed that the stripping of concrete forms is to be in a manner of equal numbers . . . [equal numbers of members of the Carpenters' and Laborers' Unions]." The portion of the construction project giving rise to the work dispute began in May of 1995 and was completed in May of 1996. The site of the work was a railroad station in Weymouth, Massachusetts. The work for Contractor C.R.C. was mainly that of erecting concrete footings. Its crew for this work consisted of two carpenters and two laborers. The carpenters erected forms for the footings and stripped the forms from the concrete after it had hardened. The laborers cleared and oiled the forms and carried them to the next construction point. On several occasions in June of 1995 the laborers assisted the carpenters in stripping the forms. In late June the Carpenters complained to the C.R.C. labor foreman that the stripping should be done by the carpenters. The Laborers promptly countered that the stripping should be done with at least fifty percent laborers. About the end of June 1995, C.R.C. began pouring concrete for retaining walls which were much larger than the footings it had previously constructed. C.R.C. added two carpenters and two laborers to its crew. The Laborers, through its business manager, demanded that C.R.C. officially assign the stripping of forms to a crew composed equally of carpenters and laborers. The same demand was made of T. Equipment. On June 30, 1995, C.R.C. formally assigned the work of erecting and stripping forms to members of the Carpenters' Union and the work of cleaning, oiling, and moving the forms to the next job site to members of the Laborers' Union. On the next day of work, July 5, carpenters began to strip forms from one retaining wall. Two members of the Laborers' Union climbed the wall and began to assist in the stripping. The job foreman for C.R.C. told the laborers to come down from the wall; they refused to do so. The carpenters stopped stripping and refused to continue. The police were called and removed the laborers from the job site. On July 21, 1995, the Laborers filed a contractual grievance against both C.R.C. and T. Equipment (plaintiffs in this action). The Laborers alleged breach of the collective bargaining agreement between the Union and the main contractor, J.F. White. Arbitration was requested and an arbitration hearing was scheduled for November 14, 1995. On November 9, the Carpenters informed C.R.C. and T. Equipment that if the carpenters were removed from the stripping work, they would be pulled from the site and the Union would no longer refer carpenters to C.R.C. or T. Equipment. On the day of the scheduled arbitration hearing, C.R.C. and T. Equipment filed an unfair labor practice charge with the National Labor Relations Board (NLRB or Board) against the Carpenters' Union. They alleged, in effect, that the Carpenters had threatened to refuse to work and engaged in other illegal activity because of the stripping dispute. The Contractors' counsel appeared before the arbitrator and took the position that the filing of an unfair labor practice charge with the NLRB deprived the arbitrator of jurisdiction. This resulted in a delay of the arbitration proceeding. The hearing terminated, after two days, on July 2, 1996. The NLRB proceeded promptly under section 10(k) of the National Labor Relations Act to hear the dispute. On October 30, 1996, it issued its determination: After considering all the relevant factors, we conclude that employees represented by the Carpenters are entitled to perform the work in dispute. We reach this conclusion relying on the factors of collective-bargaining agreements, company preference and past practice, relative skills and safety, and economy and efficiency of operations. In making this determination, we are awarding the work to employees represented by the Carpenters, not to that Union or its members. The determination is limited to the project known as the Old Colony Railway.

DETERMINATION OF DISPUTE

The National Labor Relations Board makes the following Determination of Dispute.

Employees of T. Equipment Corporation and C.R.C. Co., Inc. represented by Local 624, United Brotherhood of Carpenters and Joiners of America, AFL-CIO are entitled to perform stripping of reusable panel forms on the Old Colony Railway project.

Dated, Washington, D.C. October 30, 1996

The arbitrator issued his opinion on November 4, 1996. He was fully aware of the NLRB's decision; see first paragraph below. The pertinent parts of the arbitrator's opinion follow. The Employers suggest that the 1988 NLRB decision in Hawkins should control the question of arbitrability because the carpenters were awarded stripping work in [the NLRB] proceeding. However, this arbitration arises under the parties' collective bargaining agreement and concerns the parties' rights and obligations under this contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carey v. Westinghouse Electric Corp.
375 U.S. 261 (Supreme Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
T. Equipment v. Mass. Laborers, Counsel Stack Legal Research, https://law.counselstack.com/opinion/t-equipment-v-mass-laborers-ca1-1999.