T. A. Haigh Lumber Co. v. Drinkwine

287 A.2d 560, 130 Vt. 120, 1972 Vt. LEXIS 238
CourtSupreme Court of Vermont
DecidedFebruary 1, 1972
Docket90-70
StatusPublished
Cited by6 cases

This text of 287 A.2d 560 (T. A. Haigh Lumber Co. v. Drinkwine) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T. A. Haigh Lumber Co. v. Drinkwine, 287 A.2d 560, 130 Vt. 120, 1972 Vt. LEXIS 238 (Vt. 1972).

Opinion

Smith, J.

This is an action brought to perfect a lien pursuant to 9 V.S.A. § 1924. The judgment order of the Chittenden County Court was that the plaintiff should have a lien upon a lot of land, and building thereon, in Jericho, Vermont, owned by the defendants Drinkwine, husband and wife, which property was under mortgage to the defendant Burlington Savings Bank. Both the Drinkwines and the Bank have duly taken their appeal to this Court from such judgment.

The Drinkwines desired to build a home on the lot of land owned by them in Jericho. On or about April 25th, 1966, these defendants entered into a contract with Orville Forslund, d.b.a. Forestline, Inc., for the construction of such dwelling house on their land. This contract provided for payment to the contractor of installments upon completion of .certain stages of the work. For the purpose of making such payment the Drinkwines secured a loan from the Burlington Savings Bank. The so-called stage payments were made by the Bank to the contractor with the knowledge of the Drinkwines upon information given by the contractor that work had been performed by him to entitle him to a payment.

The plaintiff, after the 25th of April, 1966, furnished Forslund material intended to be used in the construction of the dwelling house in the amount of $2,800.92, which material was delivered to. the premises owned by the Drinkwines. The *123 lower court found that Forslund was not the agent or employee of the Drinkwines.

Our first concern here is with the claimed lien of the plaintiff upon the premises. The plaintiff, by notice in writing dated May 19, 1966, notified both the Drinkwines and the bank of its intention to claim a lien on said property pursuant to 9 V.S.A. § 1921(c). However, it was not until August 26, 1966, that it filed its notice of lien in the Jericho Land Records pursuant to 9 V.S.A. § 1921(c).

It was the contention of the defendants below, as well as here, that the mechanic’s lien, filed by the plaintiff, did not affect an attachment on the property in question. Defendants say that the findings of the lower court disclose that no money was owed by the Drinkwines to Forslund either at the time the notice of intent to file a lien was filed on the defendants, or that any money was due from the defendants to Forslund at the time of the filing of the mechanic’s lien in the Jericho Land Records on August 26, 1966. Finding 17 states “That at the time said notice of lien was served upon them there were no monies due from Donald Drinkwine and Betsy Drinkwine.”

The lower court also found that Forslund abandoned work on the building of the Drinkwines sometime after August 9, 1966. Equally important, in view of the contentions of the defendants, is Finding 14 which states:

“The dwelling house was never completed in accordance with the terms of the contract and at the time the payments were made by Burlington Savings Bank to the Drinkwines and at the time of the endorsement by the Drinkwines to Forestline and Forslund, Forslund in fact owed the Drinkwines money inasmuch as the work was never completed covering the monies paid.”

The lower court did find, however, that after receipt of the plaintiff’s notice of intention to claim a lien there remained unpaid on the contract price the sum of $12,800.00.

It was the plaintiffs contention below, as well as here, that while no monies were due and owing the contractor by the Drinkwines when the notice of lien was filed on August'26, 1966, the plaintiff had already acquired a lien on the property, at a time when money was still due from the defendants to *124 Forslund by reason of the notice to claim a lien served on the defendant bank on May 19, 1966. Such notice of intention to claim a lien, says the plaintiff, under the provisions of 9 V.S.A. § 1921 (b) is not required to be recorded. In substance, the claim of the plaintiff, which must have been accepted by the lower court in rendering its judgment and order for the plaintiff, is that the statute creates two liens, although the filing of both is not required. One such lien, which is not necessary to be recorded, being that provided for in 9 V.S.A. § 1921 (b), while the other, requiring recording, is that provided in the lien which is required to be filed by the provisions of 9 V.S.A. § 1921(c). Such an interpretation of the statutes we find to be in error.

In construing the provisions of the so-called Mechanic’s Lien Statute, we said, in Cote v. Bloomfield, 128 Vt. 806, 262 A.2d 467, 470 (1970): “It is our duty to harmonize different sections of this act if it can be done reasonably.” Under this guidance we shall now proceed to examine the act, including not only the sections here in dispute but upon the whole act, to determine its reasonable construction in view of the questions presented.

9 V.S.A. § 1921(b) reads as follows:

“A person who by virtue of a contract or agreement, either in writing or parol, with an agent, contractor or subcontractor of the owner thereof, performs labor or furnishes materials to the amount of $15.00 or more for erecting, repairing, moving or altering such building, steam engine or waterwheel shall have a lien, to secure the payment of the same upon such building, steam engine or waterwheel and the lot of land upon which the same stands, by giving notice in writing to such owner or his agent having charge of such property that he shall claim a lien for labor or material. Such lien shall extend to the portions of the contract price remaining unpaid at the time such notice is received.”

In (c) of the same section, it is provided:

“A lien herein provided for shall not continue in force for more than sixty days from the time when payment *125 became due for the last of such labor performed or materials furnished unless a notice of such lien is filed in the office of the town clerk as hereinafter provided.”

9 V.S.A. § 1923, “Recording Notice of Lien”:

“A person claiming a lien under section 1921 of this title, shall file for record in the clerk’s office of the town where such real estate is situated, a written memorandum, signed by him, asserting his claim, which shall charge such real estate with such lien as of the visible commencement of work or delivery of material to the extent and subject to the exceptions provided in sections 1921 and 1922 of this title. Several such liens, asserted as aforesaid, shall be paid pro rata, if the sum due or to become due from the owner thereof is not sufficient to pay the same in full.”

Plaintiff contends that the lien created by the notice provided for in 9 V.S.A. § 1921 (b) is not required to be recorded by the provisions of 9 V.S.A. § 1922, which we now quote:

“1922. Effect of lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
287 A.2d 560, 130 Vt. 120, 1972 Vt. LEXIS 238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/t-a-haigh-lumber-co-v-drinkwine-vt-1972.