Cote v. Bloomfield

262 A.2d 467, 128 Vt. 306, 1970 Vt. LEXIS 226
CourtSupreme Court of Vermont
DecidedFebruary 3, 1970
Docket1118
StatusPublished
Cited by5 cases

This text of 262 A.2d 467 (Cote v. Bloomfield) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cote v. Bloomfield, 262 A.2d 467, 128 Vt. 306, 1970 Vt. LEXIS 226 (Vt. 1970).

Opinion

Smith, J.

This is an action instituted under the provisions of the so-called Mechanic’s Lien Statute to recover for labor and materials furnished by the plaintiff to the residence of the defendant in the Town of Winhall, Vermont. Trial by jury was held before the Windham County Court in April, 1969, with verdict and resultant judgment for the plaintiff. Only two issues are presented by this appeal. The first deals with the interpretation given by the trial court in its rulings on defendant’s motion for a directed verdict, as well as the charge of the lower court to the jury. The second deals with the Judgment Order under which the plaintiff was granted an in personam judgment against the defendant.

Defendant Bloomfield entered into a contract with one Peter L. Butynski, Inc., a general contractor, to construct a house in Winhall, Vermont, for a total price of $54,000.00. This sum, under the contract, was payable in five equal installments of $10,800 each, in accordance with a schedule contained in the contract, with the final installment of $10,800 payable within thirty days of completion of construction and its ac *307 ceptance by the designer and owners, and only upon satisfaction of any liens.

■ Plaintiff Cote was a sub-contractor in the construction of the building, and was employed by Butynski to do the plumbing and heating work on the residence. The plaintiff entered into two contracts with Butynski for the performance of the work, which contracts for plumbing work called for a price of $4,100.00 and for the heating work of $3,875.00, for a total of $7,975.00. These contracts provided for three equal installment payments to be made by Butynski to the plaintiff of $2,659.00. each. Only one of such payments was made by Butynski to the plaintiff.

The evidence is undisputed that the defendant made four payments under his contract with Butynski totalling $43,-200.00. It is also undisputed that the defendant paid $1,775.00 to another sub-contractor, with the consent of Butynski, which amount was credited to the remainder of the contract price unpaid. Thus, at the time that the defendant received notice of the lien of the plaintiff on February 26, 1966, there was still a balance due under the terms of the contract from the defendant to Butynski of $9,025.00.

On February 26, 1966, the contract had not been completed by Butynski, and in fact said contract never was completed. It was the undisputed evidence of the defendant below that under the terms of the contract, Butynski’s failure to complete the work specified under the contract gave the defendant the right to terminate the contract, complete the work himself, and charge the cost of the completion to any sums unpaid. Defendant’s testimony was that he did complete the work, and that the cost of such completion exceeded the $9,025.00 remaining unpaid to Butynski. Butynski’s testimony that he never made any demand upon the defendant for the balance of the payments that would have been due him under the contract, if completed, was undisputed. Also undisputed was that Butynski had gone into bankruptcy and that the trustee in bankruptcy has never made a claim for any claimed payment due under the contract. It was the contention of the defendant that on February 26, 1966, the date upon which he received the lien of the plaintiff, that his expenditures in completing the work not finished by Butynski exceeded the amount of the final payment that would have been due Butynski, had he com *308 pleted his contract and that there was nothing due to Butynski from him to which the lien of the plaintiff could apply.

■The first issue presented to us by the appellant reads: Whether or not the trial court erred in interpreting the provisions of the last sentence of 9 V.S.A. Sec. 1921(b) so as to extend a mechanic’s lien to amounts unpaid under a contract which amounts were not due the contractor on the date the notice of lien was received or which amounts were not thereafter to become due the contractor. ■

9 V.S.A. Sec. 1921(b). “A person who by virtue of a contract or agreement, either in writing, or parol, with an agent, contractor or subcontractor of the owner thereof, performs labor or furnishes materials to the amount of $15.00 or more for erecting, repairing, moving or altering such building, steam engine or waterwheel shall have a lien, to secure the payment of the same upon such building, steam engine or waterwheel and the lot of land upon which the same stands, by giving notice in writing to such owner' or his agent-having charge of such property, that he shall claim a lien for labor or material; Such lien shall extend to the portions of the contract price remaining unpaid at the time such' notice is received.” ■ '

It was the motion of the defendant at the end of the plaintiff’s case- that the cause be dismissed on the ground that, viewing the evidence in the light most favorable to the plainr tiff, it showed- that at the time the lien of the plaintiff was filed that the defendant did not owe any sums to the general contractor. The same motion was made by the defendant at the close of all the evidence in the ease. Both motions were denied by the lower court.

In its' instructions to the jury, the lower court submitted to them two issues, with a special verdict to be rendered on each issue. One such issue was how much was due and payable as a balance to the plaintiff. The second issue, and the one of importance here, was what was the amount in the hands of the defendant on February 26, 1966, remaining as a balance and unpaid of the $54,000.00 contract price.

The lower court also instructed the jury in the following languagé: . ' . - '

*309 “Now, we charge' you as á matter of law that defendant, upon receipt of plaintiff’s notice of the filing of a mechanic’s lien on his house in Winhall was obliged to retain .in his hands and possession any and all sums of the contract price remaining unpaid by him at the time he receive (sic) notice of the lien. He had no choice under the law. He had to retain that amount. The law required him to retain it and keep this amount in his possession. He-had to do that, regardless of any hardship that it might have worked upon him. If he failed to retain this unpaid balanee,- used it, expended it for whatever he did so at his own peril and this is so regardless of how worthy a purpose he may have expended it. So we instruct you as a matter of law that this sum of $9,025.00 the defendant testified he had in his hands remaining unpaid at the time he received notice of the plaintiff’s lien is the amount of the unpaid balance of the contract price of $54,000.00.”

Defendant objected to this portion of the charge.

During its deliberations, the jury returned to the courtroom for. further instructions from the court. The court then instructed them that they must find that the defendant had on hand the sum of $9,025.00, an unpaid balance on the contract of $54,000.00 as of February 26, 1966. Defendant again objected.

It is the position of the defendant that the legislative intent in providing the statutory remedy of a mechanic’s lien was not to compel an owner to be forced to pay more than he was pbligated to do under the original contract. In support of this position, he cites to us 9 V.S.A. Sec.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Newport Sand & Gravel Co. v. Miller Concrete Construction, Inc.
614 A.2d 395 (Supreme Court of Vermont, 1992)
Nadeau Lumber, Inc. v. Benoit
437 A.2d 1108 (Supreme Court of Vermont, 1981)
T. A. Haigh Lumber Co. v. Drinkwine
287 A.2d 560 (Supreme Court of Vermont, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
262 A.2d 467, 128 Vt. 306, 1970 Vt. LEXIS 226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cote-v-bloomfield-vt-1970.