Syme v. Symphony Grp. LLC

2018 UT App 212, 437 P.3d 576
CourtCourt of Appeals of Utah
DecidedNovember 8, 2018
Docket20170531-CA
StatusPublished
Cited by4 cases

This text of 2018 UT App 212 (Syme v. Symphony Grp. LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Syme v. Symphony Grp. LLC, 2018 UT App 212, 437 P.3d 576 (Utah Ct. App. 2018).

Opinion

POHLMAN, Judge:

¶ 1 Al and Martha Syme met with Symphony Group LLC to discuss the construction of a custom home. The parties signed a contract, but the Symes cancelled it before construction began. Symphony, however, retained the Symes' earnest money and construction deposits. The Symes sued to recover both deposits, and Symphony moved for summary judgment, which the district court granted. The Symes appeal. We affirm in part, reverse in part, and remand for further proceedings.

BACKGROUND 1

¶ 2 In the spring of 2015, the Symes met with representatives of Symphony about the construction of a new, custom home in Layton, Utah. The parties signed a written contract (the Agreement) on June 1, which set forth the basic details of the house Symphony was to construct, including its location, price, and floor plan. Some of the details, such as the color and type of brick, countertops, and floor coverings, were left to be selected in future meetings. The Agreement also set forth the obligations of each party and provided for specific remedies in the event of a breach.

¶ 3 As part of the house's purchase price, the Symes agreed to pay Symphony an earnest money deposit of $2,000 (the Earnest Money) and a construction deposit of $43,000 or $48,000 (the Construction Deposit). 2 The Symes delivered the Earnest Money to Symphony when they signed the Agreement. They delivered a $48,000 Construction Deposit to Symphony at a subsequent "Structural Review Meeting." 3

¶ 4 Regarding the house's financing, the Agreement required the Symes "to receive written evidence of loan pre-approval within ten (10) days from" Symphony's acceptance of the Agreement, "or such longer period as [Symphony], in its sole discretion may allow." The same provision stated that if the Symes failed "timely to provide such loan approval to [Symphony]," then Symphony could elect to terminate the Agreement. If Symphony elected to terminate the Agreement under this provision, the Agreement required Symphony to return the Earnest Money to the Symes unless they were in default. 4

¶ 5 Another provision in the Agreement required the Symes to deliver to Symphony a loan pre-approval letter "prior to or at" the "Color Selection Meeting"-a meeting the Symes were required to attend at Symphony's "reasonable request." If the Symes failed to deliver the loan pre-approval letter as required by this provision, Symphony could, "in its sole and reasonable discretion," deem the Symes "in default" and enforce its remedies "as allowed by [the] Agreement and Utah law, including but not limited to, [Symphony's] retention of [the] Earnest Money and Construction Deposit."

¶ 6 The Color Selection Meeting never took place. According to the Symes, they "waited in vain" for Symphony to "follow through on [the Color Selection Meeting]" or "request [the pre-approval letter]."

¶ 7 Before construction started or any other meetings were held, the Symes sent a letter to Symphony through their attorney purporting to cancel the Agreement. The Symes conceded in the letter that they would have to forfeit their $2,000 Earnest Money but requested the return of their Construction Deposit. Because the Symes did not deliver the pre-approval letter and "failed to finalize other preconstruction selections at the Color Selection Meeting," Symphony refused to return the Construction Deposit.

¶ 8 The Symes brought suit for the return of the Earnest Money and Construction Deposit, seeking a declaration that no contract existed and, alternatively, seeking damages for breach of contract and breach of the implied covenant of good faith and fair dealing. Symphony moved for summary judgment on each claim.

¶ 9 The district court granted Symphony's motion. It concluded that there was an enforceable contract between the parties and determined that the Symes would be unable to prove their breach of contract claim because the Symes themselves breached the Agreement by failing to provide the pre-approval letter "within 10 days of acceptance of the contract." The court reasoned that "[e]ven if the [Color Selection Meeting] never took place, [the Symes] were still required by the contract to provide the pre-approval letter." The court also concluded that the Symes would be unable to prove their implied covenant of good faith and fair dealing claim. At the heart of that claim was the Symes' contention that the liquidated damages clause Symphony relied on to retain the Earnest Money and Construction Deposit was unconscionable. The court concluded that "expert testimony would be required" to establish unconscionability and that the Symes would be unable to prove their claim because they had conceded they "would be precluded from offering expert testimony at trial." 5 Thus, the court entered final judgment in favor of Symphony. The Symes timely appeal.

ISSUE AND STANDARD OF REVIEW

¶ 10 The Symes' arguments on appeal all flow from the district court's summary judgment decision. Summary judgment is appropriate "if the moving party shows that there is no genuine dispute as to any material fact and the moving party is entitled to judgment as a matter of law." Utah R. Civ. P. 56(a). "An appellate court reviews a district court's legal conclusions and ultimate grant or denial of summary judgment for correctness and views the facts and all reasonable inferences drawn therefrom in the light most favorable to the nonmoving party." ZB, NA v. Crapo , 2017 UT 12 , ¶ 11, 394 P.3d 338 (quotation simplified).

ANALYSIS

I. The Enforceability of the Agreement

¶ 11 The Symes first contend that the district court erred in granting summary judgment to Symphony on their claim for declaratory relief because there were disputed facts material to the question of whether a contract was formed. In support, they make three related arguments: first, that the Agreement is too indefinite to be enforced; second, that the parties never intended the Agreement to be the final agreement; and finally, that the Agreement is ambiguous. We address each argument in turn.

A. Contract Formation

¶ 12 The Symes assert that the Agreement is too indefinite to be an enforceable contract because it is "silent as to much of the work that [was] to be performed by Symphony." Without specifying "exterior materials," "interior finishes," and the "types of countertops, cabinets, shingles, lighting fixtures, or appliances" that were to be used in the construction of their house, the Symes assert that the Agreement "cannot be performed."

¶ 13 "Whether a contract exists between parties is ordinarily a question of law ...." Cea v. Hoffman , 2012 UT App 101 , ¶ 9,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Regal Realsource v. Enlaw
2024 UT App 95 (Court of Appeals of Utah, 2024)
Commercial Club v. Global Rescue
2023 UT App 37 (Court of Appeals of Utah, 2023)
Bear v. Lifemap Assurance
2021 UT App 129 (Court of Appeals of Utah, 2021)
KB Squared LLC v. Mem'l Bldg. LLC
2019 UT App 61 (Court of Appeals of Utah, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2018 UT App 212, 437 P.3d 576, Counsel Stack Legal Research, https://law.counselstack.com/opinion/syme-v-symphony-grp-llc-utahctapp-2018.