Sylvester v. Town of Ville Platte

49 So. 2d 746, 218 La. 419, 1950 La. LEXIS 1087
CourtSupreme Court of Louisiana
DecidedDecember 11, 1950
Docket39666
StatusPublished
Cited by13 cases

This text of 49 So. 2d 746 (Sylvester v. Town of Ville Platte) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sylvester v. Town of Ville Platte, 49 So. 2d 746, 218 La. 419, 1950 La. LEXIS 1087 (La. 1950).

Opinion

McCALEB, Justice.

The town of Ville Platte, following a special meeting of the Board of Aldermen on October 28th 1947, at which it was decided to move a gas pipe line in order to facilitate the widening of a highway by the Louisiana State Highway Department, advertised for bids for the performance of this public work. The advertisement provided that “Notice is hereby given that bids will be received Friday, November 14, 1947 * * * for a contract to remove the Gas Pipe Line extending from meter house on Chataignier Street to a distance in a southern direction of approximately 22,000 feet” along the proposed highway ‘‘said contract to cover all labor, materials, crossings, connections and every requirement of the State Highway Department, and to meet all specifications on file in the City Hall of Ville Platte * * * ”.

Plaintiff, a contractor residing in Evangeline Parish, and two others were interested bidders on the project. On the date upon which bids were received, plaintiff submitted the low bid of $6,900 for the entire work “as per your public notice” which was accepted by the Board of Aldermen. The next lowest bid was $11,880 and the other bid was several hundred dollars in excess of that.

*424 Prior to the preparation and submission of his bid, plaintiff visited the Mayor and Town Clerk for the purpose of examining the specifications for the work, which had been advertised to be on file in the City Hall, and was informed that none had been prepared. Plowever, he was told at the City I-Iall that Messrs. Sompton Soileau and Orise Fontenot, who were in charge of the gas system operated by the town, could supply all necessary -information. Conformably, plaintiff and his foreman contacted Soileau and Fontenot, who told them that there were 12 or 13 gas connections, and not over 14, to be moved and they went to the site of the work with plaintiff to show him the location of these connections, placing pegs where they were situated. Plaintiff’s bid for the work was based upon these representations. 1

The execution of the work did not begin until early in April of 1948 or more than four months after plaintiff was awarded the contract. On April 6th, during the progress of the job, plaintiff ascertained that there were more than 12 or 13 gas connections requiring removal. Upon making this discovery, he immediately stopped work and called upon the Mayor and Board of Aldermen for an increase in his bid. He also contacted Fontenot and Soileau and was informed by them that the additional connections that had been found were new — that is, gas connections which had been made since the acceptance of plaintiff’s bid. With these facts at hand and upon plaintiff’s representation that $130 for the removal of each additional connection would be a fair price, the Board of Aldermen resolved that “Whereas, additional connections have been made on the gas line * * * ” since the letting of the contract to plaintiff, which increased the cost of moving the line, “Therefore, * * * Oscar Sylvester, Contractor, shall be paid $130 for each unit or connection made since the letting of the contract”.

Upon being thus' assured of extra compensation for the removal of additional connections (which were then believed to have been made during the interval between the letting and execution of the contract), plaintiff performed the job specified in the advertisement for bid-s. However, this necessitated the removal of a total of 41 connections of which only three had been made after the letting of the contract. Hence, there were actually 38 connections which required removal at the time plaintiff bid on the job instead of 12 or 13, as depicted by Soileau and Fontenot.

Later, the job was accepted by the town and a voucher was drawn in plaintiff’s favor for the original contract price of $6,900. The Board of Aldermen also issued a warrant for $390 in payment for removal of the three additional connections, which *426 bad been made subsequent to the contract, recompense for which was specifically covered by the Board’s resolution of April 6th 1948. Plaintiff cashed the voucher issued in payment of .the original contract bid price of $6,900 but refused the $390 voucher on the ground that, under the resolution of the Board of April 6th 1948, he was entitled to payment for the removal of 29 additional connections at $130 each, being the difference between the 41 connections removed and the 12 connections allegedly contemplated by his bid. Upon the town’s refusal to accede to this demand, this suit followed.

Plaintiff’s action, which is for the recovery of $3,770 or $130 each for 29 additional connections, is founded on the theory that, due to misrepresentation on the part of the employees of the town, he made a bid based upon a belief that there were only 12 gas connection pipes to be moved; that, upon discovering that there were additional connections, he stopped the job and insisted upon extra compensation for any work not contemplated by his bid; that, thereafter, a new contract was made whereby he was to receive $130 for each additional gas connection in excess of 12 requiring removal and that, accordingly, he i-s entitled to recover the sum demanded under that agreement. Alternatively, he asserts that, should the resolution of April 6th be considered insufficient to constitute a contract and inadequate to justify his reliance thereon in the removal of additional connections, then he should nevertheless have judgment for the amount •sought on a quantum meruit basis.

The defense of the town is primarily that there is no justification in law for plaintiff’s position that he was misled or acted under an error of fact in making his original bid which was accepted and resulted in a binding contract between the parties; that, furthermore, plaintiff’s reliance for recovery on the resolution of the Board of Aldermen of April 6th 1948 is without merit as that resolution specifically limits liability for additional compensation to removals of connections which were installed subsequent to the letting of the contract (of which there are three) for which proper voucher in the sum of $390 has been tendered to plaintiff.

After a hearing on these issues, there was judgment in favor of plaintiff for the sum of $2990, based on the removal of 23 additional connections at $130 each. 2 The district judge was of the opinion that plaintiff had been misled by the employees of the town into submitting a bid calculated on the removal of 12 or 13 (and, assuredly, not more than 18) connections; that, there *428 fore, the contract was voidable at plaintiff’s option and that, although the resolution of the Board of Aldermen could not be viewed' as a binding contract to pay for all additional connections, plaintiff was entitled to recompense on a quantum meruit for the removal of 23 at $130 each, which represented a fair value of the work. The town has appealed from the decision and plaintiff has answered, praying for an increase in the judgment to .the amount demanded in his petition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoffman v. CRAFTWORLD INTERN., INC.
463 So. 2d 89 (Louisiana Court of Appeal, 1985)
Con-Plex, Div. of US v. La. Dept. of Transp.
439 So. 2d 567 (Louisiana Court of Appeal, 1983)
McCarty Corp. v. Pullman-Kellogg
571 F. Supp. 1341 (M.D. Louisiana, 1983)
Ferace v. Fullerton
425 So. 2d 393 (Louisiana Court of Appeal, 1982)
Ortego v. Lebert
406 So. 2d 253 (Louisiana Court of Appeal, 1981)
Pelican Aviation Corp. v. Airport Authority for the Parish of Iberia
372 So. 2d 1266 (Louisiana Court of Appeal, 1979)
Nugent v. Stanley
336 So. 2d 1058 (Louisiana Court of Appeal, 1976)
Savoie v. Bills
317 So. 2d 249 (Louisiana Court of Appeal, 1975)
Tobin v. Louisiana State Board of Education
319 So. 2d 823 (Louisiana Court of Appeal, 1975)
Van Vracken v. Harry J. Spiro, Inc.
139 So. 2d 89 (Louisiana Court of Appeal, 1962)
Overby v. Beach
55 So. 2d 873 (Supreme Court of Louisiana, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
49 So. 2d 746, 218 La. 419, 1950 La. LEXIS 1087, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sylvester-v-town-of-ville-platte-la-1950.