Swaye v. Sylvan Construction Co.

7 Conn. Super. Ct. 456
CourtConnecticut Superior Court
DecidedDecember 2, 1939
DocketFile No. 38391
StatusPublished

This text of 7 Conn. Super. Ct. 456 (Swaye v. Sylvan Construction Co.) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Swaye v. Sylvan Construction Co., 7 Conn. Super. Ct. 456 (Colo. Ct. App. 1939).

Opinion

The defendant, The Capitol National Bank and Trust Company, of Hartford, has moved to establish priority of liens. The validity of the lien of the defendant O. J. Seguin is attacked as being defective on its face, in that it was not filed within 60 days from the time of ceasing to render services and furnish materials. Seguin seeks by cross complaint a reformation of his lien to show that the last day of work did fall within the 60 day period prior to the filing of the lien. The defendant bank has demurred to this claim for relief on the ground that as a matter of law this court has "no power or authority .... to grant the relief requested."

This question was raised at the Short Calendar hearing on October 27th, but was not disposed of at that time as the parties were given time to file briefs. At the same hearing the defendant Seguin was allowed to present evidence to substantiate his prayer for reformation in order to save time and expense of appearing at a postponed hearing.

All the testimony introduced by him was objected to on the ground it was incompetent and irrelevant since as a matter of law the lien could not be reformed. The court admitted the evidence subject to a determination of the legal question.

The bank has filed an answer to the cross complaint, which answer is subject to the determination of its demurrer.

The lien was filed July 27, 1938. The defendant bank's attachment was filed November 15, 1938, in an action brought to recover the balance due on a note dated October 3, 1938.

Judgment was entered on October 13, 1939, that the plaintiff recover $211.33, plus costs, and attorney's fee. The bank is thus a subsequent encumbrancer in point of time, and its attachment is subject to prior valid liens and encumbrances. It is prior, however, to general creditors having no specific claim to the property subject to attachment.

Now, in this case there are two questions: First: Can the defective mechanic's lien which was filed in this case be reformed on the facts disclosed by the evidence so that its validity will be retroactive to the original date of filing? Second: If the lien is reformed, was it on the facts disclosed by the evidence, filed within 60 days after the performance of services and furnishing of materials had ceased? The defendant bank denies both propositions.

Section 5106 of the General Statutes, Revision of 1930, reads *Page 458 in part as follows: "No such lien shall be valid, unless the person performing such services or furnishing such materials, within sixty days after he has ceased so to do, shall lodge with the town clerk of the town in which such building is situated a certificate in writing...."

The defendant Seguin had a plumbing contract in a house being built by the defendant Sylvan Construction Company, Inc., at No. 356 Fern Street, West Hartford. The lien states that the work began December 15, 1937. Seguin's book of account, exhibit 2, shows that the work began November 15, 1937. The lien further states that he completed his work May 25, 1938.

He alleges in his cross complaint and offered evidence to prove that he committed an error personally drafting this certificate by inserting the date "May 25, 1938", whereas "May 28, 1938" was the correct date.

In Westland vs. Goodman, 47 Conn. 83, the petitioner offered evidence to prove that the date in the certificate for completion of work was a mistake. The Supreme Court said, at page 84: "It will be observed that the statute requires that the date of the commencement of the claim shall be stated in the certificate, but it does not require in express terms that the date of its completion shall be stated, simply requiring that the certificate shall be lodged for record within sixty days." The court continued: "We are inclined to think that if that fact appears upon the record in any form it is sufficient. The statute was made for the benefit of mechanics; and while the court properly insists that all the provisions of the statute shall be complied with, it does not insist upon technical nicety in the statement of details, but will be satisfied with a substantial compliance."

The court further went on to say that: "Assuming that the petitioner can prove all that he claims, the real question is whether he shall be precluded from showing the truth." And on page 86, the court said: "It is obvious that the statute did not intend that a mistake in these matters should vitiate the lien, provided the notices required were given and the certificate filed within the time prescribed.... Hence, if the date had been omitted, leaving only the direct averment that it was filed within sixty days, we think it is quite clear that the averment might be proved by showing when the work was actually completed." The court concluded that the real date might be shown, "especially when the controversy arises between the original *Page 459 parties, and it does not appear that anyone was injured by it."

This case was cited with approval in Pierce, Butler PierceMfg. Corp. vs. Enders, 118 Conn. 610, 615, where the court said: "The statute governing mechanics' liens is to be so construed and applied as to reasonably and fairly carry out its remedial intent," and held that the plaintiff gained and the defendant lost nothing, and no one was misled by the error committed in the mechanic's lien upon which the action was based.

New Britain Lumber Co. vs. American Surety Co., 113 Conn. 1, concerned an action by a materialman on a construction bond, in which case the filing of a statement of claim within sixty days was held by the court to be a condition precedent. The court did not hold that the actual date of completion could not be established by evidence other than the date stated in the statement of claim.

In Hartford Building and Loan Assn. vs. Goldreyer, 71 Conn. 95, the building contract was executed May 11, 1896. The certificate of lien filed May 17, 1897, gave the date upon which the lien attached as May 12, 1896. This lien was later assigned, in June, 1897, to the party who sought priority over a mortgage which had been executed May 4, 1896, and recorded May 5, 1896, dates prior to the date of the building contract, May 11, 1896. In other words, the work performed on May 4th was not regarded, so the decision says, by the parties to the contract as of sufficient importance to require the contract to be made as of that date. "Such certificate was intended by statute to give reasonable notice to creditors and purchasers of the existence and extent of the lien" (p. 100). The mortgage holder acquired title in November, 1897. The court held on the foregoing facts that the town records disclosed to the holder when he purchased in November, 1897, in good faith and for value, that the mortgage was a prior encumbrance to the lien.

This latter decision must be the main reliance of the defendant bank, while Westland vs. Goodman, supra, is the main sup. port of Seguin, the lienor. From a mere recital of the facts in the Hartford Building and Loan Assn. vs. Goldreyer case, it is easily understandable why the mortgage was held prior to the lien. But the facts of the Westland case seem to me to be more applicable to the instant case. From the evidence, Seguin made a mistake in the date, May 25th. To repeat some of the quotations from the Westland case: "Hence, if the date had been omitted, leaving only the direct averment that it was filed within *Page 460 sixty days, we think it is quite clear that the averment might be ....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Martin Tire Rubber Co. v. the Kelly Tire Rubber
122 A. 102 (Supreme Court of Connecticut, 1923)
Pierce, Butler & Pierce Manufacturing Corp. v. Enders
174 A. 169 (Supreme Court of Connecticut, 1934)
New Britain Lumber Co. v. American Surety Co.
154 A. 147 (Supreme Court of Connecticut, 1931)
Flint v. Raymond
41 Conn. 510 (Supreme Court of Connecticut, 1874)
Sanford v. Frost
41 Conn. 617 (Supreme Court of Connecticut, 1874)
Cole v. Uhl
46 Conn. 296 (Supreme Court of Connecticut, 1878)
Westland v. Goodman
47 Conn. 83 (Supreme Court of Connecticut, 1879)
Nichols v. Culver
51 Conn. 177 (Supreme Court of Connecticut, 1883)
Hartford Building & Loan Ass'n v. Goldreyer
41 A. 659 (Supreme Court of Connecticut, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
7 Conn. Super. Ct. 456, Counsel Stack Legal Research, https://law.counselstack.com/opinion/swaye-v-sylvan-construction-co-connsuperct-1939.