Swanson v. Beco Const. Co., Inc.

175 P.3d 748, 145 Idaho 59, 2007 Ida. LEXIS 210
CourtIdaho Supreme Court
DecidedNovember 23, 2007
Docket32827
StatusPublished
Cited by29 cases

This text of 175 P.3d 748 (Swanson v. Beco Const. Co., Inc.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Swanson v. Beco Const. Co., Inc., 175 P.3d 748, 145 Idaho 59, 2007 Ida. LEXIS 210 (Idaho 2007).

Opinion

EISMANN, Chief Justice.

This is an appeal from the grant of summary judgment holding that an equipment lease agreement was not ambiguous and that an alleged usage of trade was not applicable. We affirm the judgment of the district court, as modified, and award attorney fees on appeal.

I. FACTS AND PROCEDURAL HISTORY

In the summer of 2004, BECO Construction Co., Inc., (BECO) was working on a government construction contract in downtown Pocatello, and Ted A. Swanson, d/b/a Swanson Construction (Swanson) had been hired to perform some of the work on that project. Swanson had been in the construction business for ten or eleven years, doing mostly excavation and hauling. He owned various items of construction equipment, including a Bobcat skid steer loader (Bobcat).

BECO had been using a rented skid steer loader, but had repeated mechanical problems with that loader. It approached Swanson to see whether he would rent his Bobcat to BECO. Swanson was not in the business of leasing his equipment, but agreed to do so. He understood that BECO would be using the Bobcat for a week or so until the other skid steer it was renting was repaired. To determine an appropriate charge, Swanson contacted an equipment rental company to find out what that company charged per day for a skid steer loader. He was told $300 plus tax, and so decided to charge BECO $300 per day. On August 27, 2004, the parties entered into a hand-written lease for the Bobcat. The lease provided that its term would be from “8-27-04 until finished” and that BECO was to pay rent of $300 “per working day.” The lease also required Swanson to deliver the Bobcat “clean, serviced + full of fuel in need of no repairs,” and it required BECO to return it “in same condition.”

BECO had the Bobcat in its possession from August 27 through October 18, 2004. Swanson had twice contacted BECO wanting to have his Bobcat returned, and each time he was told that BECO was still using it. On October 18, 2004, at 8:00 p.m., he went to the jobsite and retook possession of his Bobcat.

Swanson billed BECO $13,200 for the use of his Bobcat. BECO refused to pay, and on December 20, 2004, Swanson filed this action *61 seeking to recover from BECO the sum of $13,200 in unpaid rent, damages for failure to return the Bobcat in the condition required by the lease, and prejudgment interest. On February 3, 2005, BECO paid $6,219 as the maximum amount it believed it should owe under the lease.

On August 25, 2005, Swanson moved for summary judgment. He supported the motion with his affidavit in which he listed the forty-four days for which he contended he was entitled to rental payments and asserted that it would cost $590 in service and new tires to put the Bobcat in the same condition it had been when leased. In his supporting brief, Swanson argued that “working day” meant every day that BECO was working on the job site.

BECO responded by arguing that the term “working day” was ambiguous. It submitted the affidavit of its president in which he stated that the Idaho Transportation Department uses a different definition of “working day” in its contracts. BECO’s president also asserted that Swanson was entitled to only $219 for BECO’s failure to return the Bobcat in the same condition it had been when leased.

After oral argument on the motion, the district court on October 6, 2005, granted Swanson partial summary judgment regarding the meaning of the term “working day.” The district court stated that it was unambiguous and meant the days BECO was working on the jobsite. It also ordered Swanson to submit an affidavit showing how many days BECO was working on the jobsite during the lease term. The court denied summary judgment on the claim seeking damages for the failure to return the Bobcat in the condition required by the lease.

On October 12, 2005, Swanson filed his second affidavit, stating in essence that BECO was working on the job site on each of the forty-four days listed in his prior affidavit. On November 1, 2005, the district court granted Swanson partial summary judgment on the issue of unpaid rent. It held that Swanson was entitled to $13,200 in rent (44 days x $300 per day), less the $6,219 paid by BECO after the lawsuit was filed, for a net judgment of $6,981 in unpaid rent. It held that the damages claimed regarding the condition of the Bobcat would have to be tried.

On November 18, 2005, Swanson moved to dismiss its claim for the remaining damages. The district court granted the motion and entered judgment for Swanson in the sum of $6,981 plus costs and attorney fees in the sum of $4,207, for a total judgment of $11,188.

BECO filed three successive motions for reconsideration, which the district court denied. The court also awarded Swanson additional costs and attorney fees for responding to those motions. The final judgment entered in favor of Swanson totaled $13,358.65. BECO then timely appealed.

II. ISSUES ON APPEAL

1. Did the district court err in holding that the phrase “per working day” is unambiguous?
2. Was there a genuine issue of material fact as to the number of working days that BECO had the Bobcat during the term of the lease?
3. Did the district court err in refusing to construe the parties’ lease as including a practice among commercial equipment lessors of discounting the daily rental charge when the equipment is kept by the lessee for a period longer than one week?
4. Is either party entitled to an award of attorney fees on appeal?

III. ANALYSIS

A. Did the District Court Err in Holding that the Phrase “Per Working Day” Is Unambiguous?

Ken Wright, the project supervisor for BECO, asked Swanson if he would lease BECO the Bobcat. Swanson wrote out a lease on a work order form he used in his business. The handwritten portion of the lease agreement stated as follows:

Rent 1 Bobcat 773 SkidSteer to start 8-27-04 until finished. Machine to be delivered clean serviced + full of fuel in need of no repairs and to be returned in same condi *62 tion. Becco [sic] responsible for all repairs while rented. Original hours as of 8-27-04 (1052). Tires + 60% or 7/8. Renter to keep machined [sic] serviced.
(per day $30000

Rent to be per working day.

Swanson testified in his deposition that he inserted the words “per working day” because those words were in lease contracts he signed when he leased equipment. The record does not indicate that Swanson and Wright ever discussed the meaning of the term “working day.” Swanson simply wrote the lease agreement and Wright signed it on behalf of BECO, agreeing that BECO would pay Swanson $300 per working day for the lease of the Bobcat. BECO contends that the term “working day” is ambiguous.

“Whether a contract is ambiguous is a question of law over which we exercise free review.” Howard v. Perry, 141 Idaho 139, 142, 106 P.3d 465, 468 (2005). Ambiguities can be either patent or latent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Litster v. Litster Frost
Idaho Supreme Court, 2024
TCR, LLC v. Teton County
Idaho Supreme Court, 2024
Nelsen v. Nelsen
508 P.3d 301 (Idaho Supreme Court, 2022)
Mulberry v. Burns Concrete
Idaho Supreme Court, 2019
Mulberry v. Burns Concrete, Inc.
435 P.3d 509 (Idaho Supreme Court, 2019)
Thurston and T3 v. Safeguard
Idaho Supreme Court, 2019
Thurston Enters., Inc. v. Safeguard Bus. Sys., Inc.
435 P.3d 489 (Idaho Supreme Court, 2019)
Brand Makers v. Archibald
Idaho Court of Appeals, 2018
Bret and Marti Kunz v. Nield, Inc.
398 P.3d 165 (Idaho Supreme Court, 2017)
Gearhart v. Mutual of Enumclaw Insurance Co.
378 P.3d 454 (Idaho Supreme Court, 2016)
Jay Brown v. Auga Greenheart
Idaho Supreme Court, 2014
Brown v. Greenheart
335 P.3d 1 (Idaho Supreme Court, 2014)
Idaho Trust Bank v. Christian
301 P.3d 1275 (Idaho Supreme Court, 2013)
Buku Properties v. Raoel H. Clark
291 P.3d 1027 (Idaho Supreme Court, 2012)
MWI Veterinary Supply Co. v. Wotton
896 F. Supp. 2d 905 (D. Idaho, 2012)
Steel Farms, Inc. v. Croft & Reed, Inc.
297 P.3d 222 (Idaho Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
175 P.3d 748, 145 Idaho 59, 2007 Ida. LEXIS 210, Counsel Stack Legal Research, https://law.counselstack.com/opinion/swanson-v-beco-const-co-inc-idaho-2007.