Brighton Development, Inc. v. Quenzer Farms, LLLP

CourtIdaho Court of Appeals
DecidedOctober 28, 2024
Docket50741
StatusUnpublished

This text of Brighton Development, Inc. v. Quenzer Farms, LLLP (Brighton Development, Inc. v. Quenzer Farms, LLLP) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brighton Development, Inc. v. Quenzer Farms, LLLP, (Idaho Ct. App. 2024).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF IDAHO

Docket No. 50741

BRIGHTON DEVELOPMENT, INC., an ) Idaho Corporation, ) Filed: October 28, 2024 ) Plaintiff-Counterdefendant- ) Melanie Gagnepain, Clerk Appellant, ) ) THIS IS AN UNPUBLISHED v. ) OPINION AND SHALL NOT ) BE CITED AS AUTHORITY QUENZER FARMS, LLLP, an Idaho ) limited liability limited partnership; ) DEAN L. QUENZER, an individual in ) his capacity as trustee of THE DEAN L. ) AND DEBORAH S. QUENZER LIVING ) TRUST; and DEBORAH S. QUENZER, ) in her capacity as trustee of THE DEAN ) L. AND DEBORAH S. QUENZER ) LIVING TRUST, ) ) Defendants-Counterclaimants- ) Respondents. ) )

Appeal from the District Court of the Fourth Judicial District, State of Idaho, Ada County. Hon. James S. Cawthon, District Judge.

Judgment dismissing complaint for breach of contract, affirmed.

Givens Pursley LLP; Bradley J. Dixon, Boise, for appellant. Bradley J. Dixon argued.

Powers Farley, PC; John M. Howell, Boise, for respondent. John M. Howell argued. ________________________________________________

LORELLO, Judge Brighton Development, Inc., appeals from the district court’s judgment granting summary judgment in favor of Quenzer Farms, LLLP, and Dean L. Quenzer and Deborah S. Quenzer, in their individual capacities and as trustees of The Dean L. and Deborah S. Quenzer Living Trust

1 (collectively Quenzer Farms) and dismissing Brighton’s claims for breach of the implied covenant of good faith and fair dealing and unjust enrichment. We affirm. I. FACTUAL AND PROCEDURAL BACKGROUND In January 2020, Brighton and Quenzer Farms entered into a purchase and sale agreement (PSA) in which Brighton agreed to purchase real property owned by Quenzer Farms with options to purchase additional parcels. At the time the parties executed the PSA, Quenzer Farms owned approximately 277 acres of land. Brighton agreed to purchase a thirty-two-acre parcel from Quenzer Farms known as Parcel 1, and Brighton had the exclusive option to purchase the remaining 245 acres from Quenzer Farms in up to eight separate transactions. The PSA required the sale of Parcel 1 to close no later than July 31, 2020, unless otherwise agreed in writing. In February 2020, the parties amended the PSA to address development issues with the property and to grant Quenzer Farms an easement. On July 28, 2020, the parties amended the PSA a second time to reduce the size of Parcel 1. As contemplated by the PSA, the purchase of Parcel 1 closed on July 31, 2020, at which time Quenzer Farms recorded a special warranty deed transferring Parcel 1 to Brighton. On March 1, 2021, the parties amended the PSA a third time to modify the timing for exercising options. The amendment provided, in part: (1) “the parties agree that the first Option Closing shall be no later than the one year anniversary of the Purchase, or August 3, 2021”; and (2) “each Option exercised thereafter shall be closed no later than one year from the previously closed Option.” On March 4, 2021, Brighton notified Quenzer Farms of its intent to exercise its option to purchase an additional 41.925 acres (Parcel 2). The parties closed on Parcel 2 on April 15, 2021. Over a year later, on April 19, 2022, Quenzer Farms sent a letter to Brighton stating that the option contract was “of no force or effect” due to Brighton’s failure to timely exercise its remaining options. According to Quenzer Farms, the language of the option contract’s Third Amendment required Brighton to close on its future options “no later than one year from the previously closed Option, which was April 15, 2021,” the date the parties closed on Parcel 2. As such, Quenzer Farms refused to proceed with any future sales of its “property at the prices set forth in the” option contract and requested Brighton execute a quitclaim deed to remove any lien that

2 may have been recorded. The next day, Brighton replied to Quenzer Farms’ correspondence, arguing that there was “some confusion about the language of the third amendment” and asserting the option contract remained in effect. A month later, Brighton sent Quenzer Farms a letter attempting to exercise its option to purchase additional property (Parcel 3). Quenzer Farms rejected Brighton’s offer as untimely and notified Brighton that any additional funds or effort spent securing entitlements to portions of the land subject to the option contract would be at Brighton’s sole risk. Brighton subsequently filed a lis pendens on the entire property subject to the option contract in the PSA. Additionally, Brighton filed suit against Quenzer Farms and moved the district court for a declaratory judgment that Brighton’s offer to exercise its option to purchase Parcel 3 was timely. Brighton also alleged claims for breach of the implied covenant of good faith and fair dealing and unjust enrichment. In response, Quenzer Farms moved for summary judgment on several claims. First, Quenzer Farms argued that, as a matter of law, Brighton failed to exercise its option to purchase additional property by April 15, 2021. Accordingly, Quenzer Farms contended Brighton was not entitled to exercise additional options pursuant to the PSA. Quenzer Farms also moved the district court to dismiss Brighton’s request for declaratory judgment and its claims for unjust enrichment and breach of the implied covenant of good faith and fair dealing. In addition, Quenzer Farms asked the district court to declare as void the lis pendens filed on the remaining property. Brighton opposed the motion for summary judgment, contending the same language relied upon by Quenzer Farms proved that it had until August 3, 2022, to exercise its option to purchase additional property. Brighton further asserted that, should the district court reject its interpretation of the PSA, the terms of the PSA, and the Third Amendment in particular, should be deemed ambiguous and, as such, the district court should deny Quenzer Farms’ motion for summary judgment. Ultimately, the district court found Quenzer Farms “was well within their rights to terminate the option contract” and that the options to purchase included in the PSA were “no longer of any force or effect.” Accordingly, the district court granted Quenzer Farms’ motion for summary judgment and declaratory judgment. The district court also dismissed Brighton’s request for a declaratory judgment as well as its claims for unjust enrichment and breach of the implied covenant of good faith and fair dealing. Finally, the district court voided the lis pendens filed on

3 the remaining land and awarded Quenzer Farms costs and attorney fees in the amount of $35,340.60. Brighton appeals. II. STANDARD OF REVIEW On appeal, we exercise free review in determining whether a genuine issue of material fact exists and whether the moving party is entitled to judgment as a matter of law. Edwards v. Conchemco, Inc., 111 Idaho 851, 852, 727 P.2d 1279, 1280 (Ct. App. 1986). This Court also freely reviews issues of law. Cole v. Kunzler, 115 Idaho 552, 555, 768 P.2d 815, 818 (Ct. App. 1989). III. ANALYSIS Brighton argues the district court erred in granting Quenzer Farms’ motion for summary judgment. Specifically, Brighton contends the district court erred in finding the PSA, as amended, unambiguously required Brighton to exercise its option to purchase Parcel 3 by April 15, 2022. Brighton further argues the district court erred in determining that Quenzer Farms did not breach the implied covenant of good faith and fair dealing. Lastly, Brighton argues the district court erred in dismissing its unjust enrichment claim. Quenzer Farms responds that summary judgment was proper and supported by the record.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stoddart v. Pocatello School District 25
239 P.3d 784 (Idaho Supreme Court, 2010)
Castorena v. General Electric
238 P.3d 209 (Idaho Supreme Court, 2010)
Buku Properties v. Raoel H. Clark
291 P.3d 1027 (Idaho Supreme Court, 2012)
Cole v. Kunzler
768 P.2d 815 (Idaho Court of Appeals, 1989)
Edwards v. Conchemco, Inc.
727 P.2d 1279 (Idaho Court of Appeals, 1986)
Sanders v. Kuna Joint School District
876 P.2d 154 (Idaho Court of Appeals, 1994)
Dunnick v. Elder
882 P.2d 475 (Idaho Court of Appeals, 1994)
Bondy v. Levy
829 P.2d 1342 (Idaho Supreme Court, 1992)
Vanderford Co., Inc. v. Knudson
165 P.3d 261 (Idaho Supreme Court, 2007)
Lexington Heights Development, LLC v. Crandlemire
92 P.3d 526 (Idaho Supreme Court, 2004)
Heath v. Honker's Mini-Mart, Inc.
8 P.3d 1254 (Idaho Court of Appeals, 2000)
Potlatch Education Ass'n v. Potlatch School District No. 285
226 P.3d 1277 (Idaho Supreme Court, 2010)
Swanson v. Beco Const. Co., Inc.
175 P.3d 748 (Idaho Supreme Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Brighton Development, Inc. v. Quenzer Farms, LLLP, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brighton-development-inc-v-quenzer-farms-lllp-idahoctapp-2024.