Sustainable 9, LLC d/b/a Sustainable 9 Design + Build v. Jacqueline Coleman, Riverland Bank, ...

Supreme Court of Minnesota·Decided August 5, 2026·No. A241548·Published

Opinion

STATE OF MINNESOTA

IN SUPREME COURT

A24-1548

Court of Appeals Gaïtas, J.

Sustainable 9, LLC d/b/a Sustainable 9 Design + Build,

Respondent,

vs. Filed: August 5, 2026 Office of Appellate Courts Jacqueline Coleman,

Appellant,

Riverland Bank,

Defendant,

John Doe, et al.,

Defendants.

________________________

Courtney J. Ernston, North Star Law Group PLLC, Saint Paul, Minnesota, for respondent.

Carl E. Christensen, William J. Rogers, Christensen Sampsel PLLC, Minneapolis, Minnesota, for appellant.

________________________

When the amount of damage caused by a contractor’s negligent construction of a

home exceeds the amount of that contractor’s mechanic’s lien for the home, the

homeowner’s defense of recoupment eliminates the lien, and the lien cannot serve as the

basis for an award of attorney fees and costs to the contractor under Minnesota Statutes

section 514.14 in a mechanic’s lien enforcement action.

Reversed and remanded.

OPINION

GAÏTAS, Justice.

This case concerns a contractor’s entitlement to attorney fees and costs in a

mechanic’s lien foreclosure action arising from the construction of a new home. In 2019,

appellant Jacqueline Coleman hired respondent Sustainable 9, LLC (the contractor) as a

general contractor to build her home in Medina. Near the end of the construction project,

Coleman alleged unresolved issues with the construction and began withholding

payments to the contractor. The contractor then initiated a lawsuit, seeking to enforce its

mechanic’s lien on Coleman’s property and asserting a breach of contract claim against

Coleman. Coleman counterclaimed for breach of contract and negligence. A jury awarded

damages to Coleman on her negligence claim and to the contractor on its breach of

contract claim.

After the jury verdicts, the district court considered the mechanic’s lien foreclosure

action. Coleman asserted the common law doctrine of recoupment as a defense to the

mechanic’s lien. She argued that the amount of the lien should be reduced by the amount

2 of damage caused by the contractor’s negligent construction, as represented by the jury’s

damages award for her negligence claim. The district court rejected the recoupment

defense and found that the contractor had a valid mechanic’s lien in the amount of the

jury’s damages award for the contractor’s breach of contract claim. But the district court

determined that the value of the mechanic’s lien was fully offset by the jury’s damages

award for Coleman’s negligence claim. Notwithstanding this determination, the district

court awarded the contractor attorney fees and costs under Minnesota Statutes

section 514.14—which provides for attorney fees to the prevailing party in a mechanic’s

lien proceeding—because it determined that the offset of the award did not void the lien.

Coleman appealed to the court of appeals, and the court of appeals affirmed.

Before this court, Coleman argues that the district court erred by awarding

attorney fees and costs to the contractor to enforce its mechanic’s lien. She asserts that

both the district court and the court of appeals erred by rejecting her affirmative defense

of recoupment, which she argues extinguished the mechanic’s lien. We therefore examine

if, and how, the common law doctrine of recoupment applies when a contractor’s

negligence causes damage that exceeds the amount of the mechanic’s lien on the

property. We conclude that, under these circumstances, recoupment operates as a

complete defense and eliminates the mechanic’s lien. Thus, we reverse and remand,

holding that the court of appeals erred by affirming the district court’s ruling on the

validity of the mechanic’s lien and the award of associated attorney fees and costs to the

contractor.

3 FACTS

In October 2019, Coleman contracted with Sustainable 9, LLC, to build a home in

Medina. Per the contract, Coleman paid for the construction with installment payments.

When the project was nearly complete, Coleman raised several concerns with the

contractor regarding the construction. These concerns included gaps in the fascia (the

long, straight board that runs along the lower edge of the roof), the appearance of the

basement floor, and damage to the stairs. In January 2020, Coleman informed the

contractor that she would withhold future installment payments if these concerns were

not resolved. Discussions between Coleman and the contractor soon broke down, and

Coleman began withholding payments.

In February 2021, the contractor filed a mechanic’s lien statement against

Coleman’s property. The contractor then initiated this lawsuit in March 2021, seeking to

enforce the mechanic’s lien and bringing a separate breach of contract claim against

Coleman. Coleman counterclaimed for breach of contract and negligence. Additionally,

Coleman asserted several affirmative defenses, including: “Plaintiff’s claims are barred

by its unlawful conduct and breach of duties owed to Coleman” and “Plaintiff’s alleged

damages are offset by its own breach of the applicable agreements, contracts and/or

correspondence.”

The district court held a jury trial on both parties’ breach of contract claims and

Coleman’s negligence claim. At the jury trial, the parties disputed whether there were

construction defects and the amount it would cost to repair any defects. The contractor

also argued that Coleman had impeded it from completing repairs on the claimed defects,

4 which would excuse its performance under the contract. The jury found that Coleman

breached the contract and awarded the contractor $94,951.89 in damages. The jury also

found that the contractor breached the contract but did not award Coleman damages on

that claim. Finally, the jury found that the contractor was negligent in its work on

Coleman’s property and awarded Coleman $278,622 in damages for the negligence.

Coleman filed post-trial motions, arguing that the jury’s award of damages on her

negligence claim was inconsistent with its decision not to award damages on her contract

claim. The district court denied Coleman’s post-trial motions, reasoning that the jury’s

findings were not inconsistent, in part because the jury could have found that the

obligations under the contract were not identical to the duties underlying the negligence

claim.1

Following the jury trial, the district court held a hearing on the contractor’s action

to enforce the mechanic’s lien. Coleman argued that the contractor should not recover

anything on its lien because the amount of damage to her home—represented by the

jury’s finding of negligence damages—exceeded the amount of the claimed lien. She

contended that, under the doctrine of recoupment, the lien was extinguished because the

1 The district court reasoned that the jury could have found that Coleman impeded the contractor from returning to her home to make the repairs. The district court stated that “[t]here is a duty to mitigate in contract, there is not a duty to mitigate in negligence.” Thus, the jury could have concluded that Coleman failed to mitigate her damages under the contract claim and still awarded damages under the negligence claim. The court of appeals later concluded that this statement by the district court was legal error. Sustainable 9, LLC v. Coleman, No. A24-1548, 2025 WL 2389072, at *5 (Minn. App. Aug. 18, 2025).

Free access — add to your briefcase to read the full text and ask questions with AI

Sustainable 9, LLC d/b/a Sustainable 9 Design + Build v. Jacqueline Coleman, Riverland Bank, ..., (Mich. 2026).

Sustainable 9, LLC d/b/a Sustainable 9 Design + Build v. Jacqueline Coleman, Riverland Bank, ... (Sustainable 9, LLC d/b/a Sustainable 9 Design + Build v. Jacqueline Coleman, Riverland Bank, ...) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bull v. United States
295 U.S. 247 (Supreme Court, 1935)
Rothensies v. Electric Storage Battery Co.
329 U.S. 296 (Supreme Court, 1946)
Obraske v. Woody
199 N.W.2d 429 (Supreme Court of Minnesota, 1972)
Dolder v. Griffin
323 N.W.2d 773 (Supreme Court of Minnesota, 1982)
Becker v. Alloy Hardfacing & Engineering Co.
401 N.W.2d 655 (Supreme Court of Minnesota, 1987)
T.A. Schifsky & Sons, Inc. v. Bahr Construction, LLC
773 N.W.2d 783 (Supreme Court of Minnesota, 2009)
Household Finance Corp. v. Pugh
288 N.W.2d 701 (Supreme Court of Minnesota, 1980)
Karl Krahl Excavating Co. v. Goldman
208 N.W.2d 719 (Supreme Court of Minnesota, 1973)
Anderson v. Breezy Point Estates
168 N.W.2d 693 (Supreme Court of Minnesota, 1969)
Klingelhutz v. Grover
236 N.W.2d 610 (Supreme Court of Minnesota, 1975)
S.M. Hentges & Sons, Inc. v. Mensing
777 N.W.2d 228 (Supreme Court of Minnesota, 2010)
Knutson v. Lasher
18 N.W.2d 688 (Supreme Court of Minnesota, 1945)
Imperial Elevator Co. v. Hartford Accident & Indemnity Co.
204 N.W. 531 (Supreme Court of Minnesota, 1925)
Pacific Fire Insurance v. Kenny Boiler & Manufacturing Co.
277 N.W. 226 (Supreme Court of Minnesota, 1937)
Ryan Contracting Company v. O'Neill & Murphy, LLP
883 N.W.2d 236 (Supreme Court of Minnesota, 2016)
Mason & Craig v. Heyward
3 Minn. 182 (Supreme Court of Minnesota, 1859)
Townsend v. Minneapolis Cold-Storage & Freezer Co.
48 N.W. 682 (Supreme Court of Minnesota, 1891)
C. Aultman & Co. v. Torrey
57 N.W. 211 (Supreme Court of Minnesota, 1893)
Emery v. Hertig
61 N.W. 830 (Supreme Court of Minnesota, 1895)
Soderberg v. Anderson
922 N.W.2d 200 (Supreme Court of Minnesota, 2019)