Susan Tennant v. Peaks & Valleys, Inc., and Toni Staples (mem. dec.)

CourtIndiana Court of Appeals
DecidedJuly 6, 2018
Docket92A04-1710-CC-2474
StatusPublished

This text of Susan Tennant v. Peaks & Valleys, Inc., and Toni Staples (mem. dec.) (Susan Tennant v. Peaks & Valleys, Inc., and Toni Staples (mem. dec.)) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Susan Tennant v. Peaks & Valleys, Inc., and Toni Staples (mem. dec.), (Ind. Ct. App. 2018).

Opinion

MEMORANDUM DECISION Pursuant to Ind. Appellate Rule 65(D), this Memorandum Decision shall not be FILED regarded as precedent or cited before any Jul 06 2018, 8:39 am court except for the purpose of establishing CLERK the defense of res judicata, collateral Indiana Supreme Court Court of Appeals estoppel, or the law of the case. and Tax Court

ATTORNEY FOR APPELLANT ATTORNEY FOR APPELLEES Nathan D. Hoggatt Dawn M. Boyd Fort Wayne, Indiana Law Office of Dawn M. Boyd Columbia City, Indiana

IN THE COURT OF APPEALS OF INDIANA

Susan Tennant, July 6, 2018 Appellant-Defendant/Counter-Plaintiff, Court of Appeals Case No. 92A04-1710-CC-2474 v. Appeal from the Whitley Circuit Court Peaks & Valleys, Inc., and The Honorable Matthew J. Toni Staples, Rentschler, Judge Appellees-Plaintiffs/Counter- Trial Court Cause No. Defendants 92C01-1505-CC-201

Baker, Judge.

Court of Appeals of Indiana | Memorandum Decision 92A04-1710-CC-2474 | July 6, 2018 Page 1 of 24 [1] Susan Tennant hired Peaks & Valleys, Inc. (P&V), to construct a pole building

on her property. As the construction was nearing completion, Tennant fired

P&V and refused to pay for its work. P&V filed a complaint against Tennant,

and Tennant filed a counterclaim against P&V. A bench trial took place, and

now both parties appeal. Tennant argues that the trial court erred in its

application of the Home Improvement Contracts Act (HICA);1 P&V argues that

the trial court erred by denying its motion for prejudgment interest; and both

parties argue that the trial court erred in its attorney’s fee award to P&V.

Finding that the trial court did not err in its application of HICA or in its

attorney’s fee award, but that the trial court erred by denying P&V’s request for

prejudgment interest, we affirm in part, reverse in part, and remand.

Facts 23

The Project

1 Ind. Code § 24-5-11-1 et. seq. 2 We commend and thank the trial court for its thorough order. 3 The purpose of our appellate rules, especially Indiana Appellate Rule 46, is to aid and expedite review and to relieve the appellate court of the burden of searching the record and briefing the case. Thacker v. Wentzel, 797 N.E.2d 342, 345 (Ind. Ct. App. 2003). The briefs in this case violate several provisions of our appellate rules, which impedes our ability to expeditiously consider the issues.

First, the briefs for both parties violate Rule 46(A)(5) by omitting some citations in their statements of the case. Second, Tennant’s brief violates Rule 46(A)(6)(a), (b), and (c) because many facts in the statement of facts are unsupported by citations, the facts are not stated in accordance with the appropriate standard of review, and the statement is at times argumentative, rather than in a narrative form. P&V’s brief similarly fails to include citations for certain facts. Third, Tennant’s brief violates Rule 46(A)(8)(a) because the brief contains contentions that are not supported by cogent reasoning or by citations to the authorities. Fourth, although Rule 46(D)(3) provides that the “appellant’s reply brief shall address the arguments raised on cross-

Court of Appeals of Indiana | Memorandum Decision 92A04-1710-CC-2474 | July 6, 2018 Page 2 of 24 [2] Tennant owns a farm in Whitley County. P&V is a roofing and construction

company. Its owner, sole shareholder, and president is Toni Staples.

Sometime in May 2014, Tennant told P&V that she wanted a pole building

constructed on her property (the Project) and some land cleared. On or around

May 15, 2014, P&V presented Tennant with a written estimate of $33,812 for

the Project and the land clearing. The estimate was based on the pole building

as a basic structure—a frame, metal siding, a roof, a cement slab, three garage

doors, and a regular door—with an unfinished interior and no plumbing or

electricity. Tennant understood and agreed to the terms of the estimate.

Tennant did not sign the estimate, nor did the parties put their agreement in a

written, signed contract.

[3] P&V spent ten days clearing the land. On or around August 22, 2014, P&V

began the Project. P&V purchased supplies on credit from a third-party

business (the Supplier), expecting to repay the Supplier once Tennant paid for

the Project. On August 26, 2014, Tennant paid P&V $6,000 for the clearing

work.

[4] By early September, P&V was ready to prepare and pour the concrete slab for

the Project. Around this time, Tennant requested certain modifications and

upgrades—including relocating the Project and adding water and electric

lines—to the Project, which resulted in increased material and labor costs and

appeal,” (emphasis added), Tennant’s reply brief fails to mention any of the issues that P&V raises on its cross-appeal. Instead, the reply brief is a near-verbatim reiteration of sections of her initial brief.

Court of Appeals of Indiana | Memorandum Decision 92A04-1710-CC-2474 | July 6, 2018 Page 3 of 24 delayed the Project. P&V informed Tennant that the requested changes would

increase the Project’s cost and timeline; Tennant verbally agreed to pay for the

additional costs. P&V made changes and incurred expenses based on these

requests.

[5] Around the middle of October 2014, P&V once again began to prepare the

concrete site. Tennant then told P&V that she wanted to increase the depth of

the concrete slab from four to six inches. This change required P&V to adjust

the building frame. On October 23, 2014, the stone fill for the concrete was

delivered. On October 24, 2014, P&V’s concrete subcontractor placed the stone

fill in the building frame and graded it. Meanwhile, Tennant and P&V

mutually agreed to allow Tennant to have a different contractor lay the

concrete, and on October 24, 2014, Tennant began contacting other contractors.

She hired Barry Myers and Roger Conrad to pour the building’s concrete slab

by separate agreement.

[6] By early November, P&V had completed most of the work for the Project.

When Myers and Conrad worked on the concrete, they chose to remove and

replace the concrete fill that P&V had installed because it was saturated and

muddy. P&V was not permitted to work on the Project while the concrete was

being poured. On November 11, 2014, Tennant called Staples and fired P&V

from the Project. When P&V’s subcontractors returned to the Project to finish

the few remaining tasks, Tennant told them they were fired and ordered them

to leave her property. Tennant refused to pay P&V for the Project. As a result,

P&V was unable to repay the Supplier and accrued interest on its debt to the

Court of Appeals of Indiana | Memorandum Decision 92A04-1710-CC-2474 | July 6, 2018 Page 4 of 24 Supplier; P&V then took out a loan at a lower interest rate to mitigate its

damages.

Procedural History

[7] On December 4, 2014, P&V filed a mechanic’s lien on the Project for

$33,511.39. At some point, P&V admitted to an error in the amount and

excluded certain materials, reducing the amount of the lien to $26,511.39. On

May 13, 2015, P&V and Staples filed a complaint against Tennant, alleging

breach of contract and other claims. P&V also sought to foreclose on its

mechanic’s lien. On July 20, 2015, Tennant filed counterclaims against P&V,

alleging breach of contract, slander of title, and other claims. On March 30,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Troxel v. Troxel
737 N.E.2d 745 (Indiana Supreme Court, 2000)
Prime Mortgage USA, Inc. v. Nichols
885 N.E.2d 628 (Indiana Court of Appeals, 2008)
Thacker v. Wentzel
797 N.E.2d 342 (Indiana Court of Appeals, 2003)
Kopka, Landau & Pinkus v. Hansen
874 N.E.2d 1065 (Indiana Court of Appeals, 2007)
Town of New Ross v. Ferretti
815 N.E.2d 162 (Indiana Court of Appeals, 2004)
Sand Creek Country Club, Ltd. v. CSO Architects, Inc.
582 N.E.2d 872 (Indiana Court of Appeals, 1991)
Fackler v. Powell
923 N.E.2d 973 (Indiana Court of Appeals, 2010)
Imperial Insurance Restoration & Remodeling, Inc. v. Costello
965 N.E.2d 723 (Indiana Court of Appeals, 2012)
Goins v. Riddle
946 N.E.2d 61 (Indiana Court of Appeals, 2011)
Ponziano Construction Services, Inc. v. Quadri Enterprises, LLC
980 N.E.2d 867 (Indiana Court of Appeals, 2012)
Daniel P. Millikan v. Lori A. Eifrid
968 N.E.2d 243 (Indiana Court of Appeals, 2012)
Timothy W. Paul v. Stone Artisans, Ltd.
20 N.E.3d 883 (Indiana Court of Appeals, 2014)
Larry J. Jernas and R & R Horse Haven, Inc. v. Kevin J. Gumz
53 N.E.3d 434 (Indiana Court of Appeals, 2016)
Cheng Song v. Thomas Iatarola and Theresa Iatarola
76 N.E.3d 926 (Indiana Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Susan Tennant v. Peaks & Valleys, Inc., and Toni Staples (mem. dec.), Counsel Stack Legal Research, https://law.counselstack.com/opinion/susan-tennant-v-peaks-valleys-inc-and-toni-staples-mem-dec-indctapp-2018.