Surfrider Foundation v. California Regional Water Quality Control Board

211 Cal. App. 4th 557, 42 Envtl. L. Rep. (Envtl. Law Inst.) 20248, 149 Cal. Rptr. 3d 763, 2012 WL 5984095, 2012 Cal. App. LEXIS 1223
CourtCalifornia Court of Appeal
DecidedNovember 30, 2012
DocketNo. D060382
StatusPublished
Cited by9 cases

This text of 211 Cal. App. 4th 557 (Surfrider Foundation v. California Regional Water Quality Control Board) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Surfrider Foundation v. California Regional Water Quality Control Board, 211 Cal. App. 4th 557, 42 Envtl. L. Rep. (Envtl. Law Inst.) 20248, 149 Cal. Rptr. 3d 763, 2012 WL 5984095, 2012 Cal. App. LEXIS 1223 (Cal. Ct. App. 2012).

Opinion

Opinion

IRION, J.

Surfrider Foundation (Surfrider) appeals from the trial court’s denial of its petition for a writ of mandamus challenging the approval of the National Pollutant Discharge Elimination System (NPDES) permit by the California Regional Water Quality Control Board, San Diego Region (the Regional Board), for a desalination facility that Poseidon Resources (Channelside), LLC (Poseidon), plans to build on the coast in Carlsbad, California. Surfrider contends that in issuing the NPDES permit the Regional Board failed to comply with the requirements of Water Code section 13142.5, subdivision (b) (section 13142.5(b)),1 which provides that “[f]or each new or expanded coastal poweiplant or other industrial installation using seawater for cooling, heating, or industrial processing, the best available site, design, technology, and mitigation measures feasible shall be used to minimize the intake and mortality of all forms of marine life.” (Ibid.) We reject Surfrider’s arguments and conclude that the Regional Board complied with section 13142.5(b). Accordingly, we affirm the judgment.

I

FACTUAL AND PROCEDURAL BACKGROUND

Poseidon proposes to build a desalination facility in Carlsbad, California, which will process seawater to provide fresh potable water (the desalination facility). As this appeal arises out of the Regional Board’s approval of an NPDES permit needed for the operation of the desalination facility, we begin our discussion by focusing on the relevant features of the proposed facility.

A. Design of the Desalination Facility

The proposed desalination facility is designed to produce 50 million gallons per day of desalinated water. In order to operate, the desalination [562]*562facility will require a total of 304 million gallons per day of seawater both for source water and for the dilution of the concentrated saline wastewater by-product discharge.

With a view toward obtaining seawater for desalination while avoiding unnecessary harm to marine life, Poseidon plans to construct the desalination facility adjacent to the existing Encina Power Station (the EPS). The EPS is an electrical power generating station that uses steam generators cooled by a once-through seawater flow system, with seawater drawn from thé Pacific Ocean via the Agua Hedionda Lagoon. By virtue of being located next to the EPS, the desalination facility will be able to use the cooling water that the EPS discharges as part of the powerplant operations in place of some or all of the seawater needed for desalination. Under this design, even when the EPS’s cooling water discharge is not supplying 100 percent of the necessary seawater, the desalination facility will take in additional seawater by using the same intake structure and pumps that are used by the EPS.

Based on historical data from the EPS, the powerplant’s cooling water discharge will in some cases be able to supply all of the 304 million gallons per day of seawater needed to operate the desalination facility without the need for the intake of additional seawater (Scenario l).2 When the EPS’s cooling water discharge is fully supplying the needs of the desalination facility, Poseidon would have little ability to impose additional design elements on the seawater intake structure and intake pumps, as the desalination facility cannot interfere with or interrupt the powerplant operations.

However, when operation of the EPS’s cooling water discharge does not provide enough seawater for the desalination facility—-for instance, when the EPS is not operating at capacity or temporarily shut down—additional seawater may be taken in through the EPS’s cooling water intake structure solely for use in the desalination facility (Scenario 2). In that circumstance, the desalination facility will use additional measures to reduce the intake and mortality of marine life. These additional measures consist of (1) reducing the velocity at the inlet screen to the minimum needed for the desalination facility’s operation; (2) pumping the seawater through an optimum combination of existing fine screens and condensers to minimize the velocity and turbulence of the water; (3) using ambient temperature seawater rather than seawater with an elevated temperature as during the EPS’s operations; and (4) discontinuing periodic heat treatment of the seawater intake and discharge.3

[563]*563B. Agency Approvals of the Desalination Facility

Prior to the Regional Board’s issuance of the NPDES permit that is at issue in this lawsuit, several additional agencies considered and approved the construction and operation of the desalination facility.

1. Carlsbad City Council’s Consideration of the Final Environmental Impact Report and Its Approval of the Desalination Facility Project

In June 2006, the Carlsbad City Council certified a final environmental impact report (FEIR) for the desalination facility. The FEIR determined that the desalination facility would not cause significant adverse environmental impacts either when the desalination facility was operating together with the EPS or when the EPS was shut down. In certifying the FEIR, the City of Carlsbad approved the desalination facility with the condition, among others, that a new environmental impact report would be required if the EPS permanently ceased its operations (i.e., in Scenario 3).

2. Permit from the California Coastal Commission

In November 2007, the California Coastal Commission (Coastal Commission) granted a coastal development permit for the desalination facility, with the condition, among others, that Poseidon prepare a marine life mitigation plan (MLMP). Specifically, Poseidon was required to document the expected entrainment and impingement of marine life that would be caused by the desalination facility and to develop a plan for mitigation that, to the maximum extent feasible, was comprised of the “creation, enhancement, or restoration of aquatic and wetland habitat.”4 Several agencies, including the Regional Board and the Coastal Commission, coordinated with Poseidon to develop the required MLMP. In August 2008, the Coastal Commission [564]*564considered a version of the MLMP, and it agreed to final language for the MLMP in November 2008.

3. The State Lands Commission’s Amendment of Lease of Tidal Lands

Because the desalination facility will make use of the EPS’s intake and discharge channels, which are located on tidal lands under the jurisdiction of the State of California, the State Lands Commission was required to amend its lease of state tidal lands to the EPS in order to allow the desalination facility to operate at the same location. In November 2008, the State Lands Commission approved Poseidon’s application for a lease amendment and required Poseidon to comply with the MLMP as adopted by the Coastal Commission. Surfrider filed an unsuccessful petition for writ of mandate to challenge the State Land Commission’s approval of the lease amendment, and a December 10, 2010 opinion from this court affirmed the trial court’s denial of the petition.

4. The Regional Board’s Approval of an NPDES Permit

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Mendoza CA5
California Court of Appeal, 2025
John Doe R.L. v. Merced City Sch. Dist.
California Court of Appeal, 2025
Caltec AG v. Dept. of Pesticide Regulation
California Court of Appeal, 2019
Caltec AG v. Dep't of Pesticide Regulation
242 Cal. Rptr. 3d 156 (California Court of Appeals, 5th District, 2019)
Monterey Coastkeeper v. Monterey Cnty. Water Res. Agency
226 Cal. Rptr. 3d 592 (California Court of Appeals, 5th District, 2017)
California State University, Fresno Ass'n v. County of Fresno
9 Cal. App. 5th 250 (California Court of Appeal, 2017)
People v. Childs
220 Cal. App. 4th 1079 (California Court of Appeal, 2013)
Appel v. Superior Court
214 Cal. App. 4th 329 (California Court of Appeal, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
211 Cal. App. 4th 557, 42 Envtl. L. Rep. (Envtl. Law Inst.) 20248, 149 Cal. Rptr. 3d 763, 2012 WL 5984095, 2012 Cal. App. LEXIS 1223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/surfrider-foundation-v-california-regional-water-quality-control-board-calctapp-2012.