Supreme Construction Co. v. Olympic Recreation, Inc.

7 Wis. 2d 74
CourtWisconsin Supreme Court
DecidedApril 7, 1959
StatusPublished
Cited by2 cases

This text of 7 Wis. 2d 74 (Supreme Construction Co. v. Olympic Recreation, Inc.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Supreme Construction Co. v. Olympic Recreation, Inc., 7 Wis. 2d 74 (Wis. 1959).

Opinions

Fairchild, J.

Appellants Christifulli make no express claim that the findings of the court are not sustained by the evidence. Their specific challenges are that the trial court abused its discretion in refusing to allow appellants to amend [79]*79their complaint to allege a cause of action for the unjust enrichment of Olympic and they further claim that the trial court should have allowed a new trial.

We have, however, reviewed the evidence in order to comprehend and deal with the issues which appellants have directly raised. We come to the conclusion that the court’s findings were supported by the evidence and that there was no abuse of discretion in denying appellants’ motion for amendment of their complaint and for a new trial.

(1) Sufficiency of the evidence to■ support the findings. One of the main issues was whether the parties had expressly or impliedly agreed that all work done by Christifulli and not called for in the original plans should be done only upon authorization of Olympic and should be Olympic’s direct obligation to Christifulli. It did appear that the original plans were not adequate for the desired building and that the building as constructed differed from the building called for by the plans in some substantial ways. More electrical outlets and some electrical installations different from those called for by the original plans were installed. The contract between Supreme and Olympic included what was referred to as “partially proposed drawings,” and contemplated that the contractor would complete the “partially prepared plans.” The contract also contained the provision “if at any time during the progress of the work, the owner shall require any additions, alleviations, deviations, or omissions from said contract the owner shall have the right to make the changes desired and the said changes shall in no way affect or make void this contract but the difference in cost shall be borne by the owner.” There was nothing in this contract or in the document considered to be the contract between Supreme and Christifulli which contained any express provision as to procedure in the matter of changes and extras. Mr. Darby, one of the Christifulli partners, testified generally that as to all ex[80]*80tras Supreme referred him to Olympic and officers of Olympic authorized all extras. On the other hand Mr. Raasch, an officer of Olympic, testified that many of the changes were agreed upon between Supreme and Olympic and were not discussed with Darby. The Christifulli time slips and invoices for materials were produced in court but they showed only that certain time had been spent and materials bought for the bowling-alley job and did not segregate extras from contract items. It was conceded that Christifulli kept no separate record of charges under the contract and for extras. There were no office records showing that hours of labor or items of material were billed against Olympic during the time that Supreme was acting as contractor. No statement was ever rendered to Olympic by Christifulli before February 4, 1957, billing Olympic for extras. There was also a statement in evidence rendered by Supreme to Olympic on January 9, 1957, claiming amounts due for extras performed by subcontractors, including Christifulli. Raasch testified that Darby was present with Raasch and representatives of Supreme at a conference at which this statement was discussed and Darby discussed the items on it for electrical work. Thus there was ample evidence tending to show that all parties acted as if the owner was obligated to Supreme for extras and Supreme in turn was obligated to the subcontractor for them.

Another important issue was whether in early February Christifulli and Olympic had made an agreement under which Christifulli agreed to finish the work in return for a payment of $3,000 by Olympic or whether the $3,000 was simply a payment on account. When the abandonment of the work by Supreme became imminent in late January, Christi-fulli supplied all parties with copies of a letter in which Christifulli asserted that they were 90 per cent finished with the original contract and 90 per cent finished with the extras and that their time to complete the original contract and [81]*81extras was estimated at ten working days or one week for two men. Raasch testified that Darby agreed to complete the contract for the sum of $3,000 and testified that a notation on a lien waiver given by Christifulli on February 7, 1957, at the time the $3,000 was paid was evidence of this agreement. The printed form of waiver was signed not only by Christifulli but by the officers of Olympic and contained the written notation, “for the full amount of $3,000 only.” The sum of $3,000 was paid to Christifulli by Mutual Savings & Loan Association pursuant to an agreement between the Association and Olympic in which it was' agreed that the balance of funds then on hand to the credit of Olympic would be paid by the Association: to various subcontractors upon certain conditions. The conditions specified for the payment of $3,000 to Christifulli were “upon oral to complete all work without delay.” While the billings rendered later by Christifulli treated the $3,000 payment as a credit on the total bill for all the work, including that which had been done for Supreme, the evidence referred to was sufficient to sustain a finding that it was paid for the completion of the work.

Another matter about which there was considerable conflict was the amount of Christifulli’s total claim for extras. There was sufficient confusion in Darby’s testimony and in the records of Christifulli prepared under Darby’s ■ instructions to warrant- the court in disregarding much of Darby’s testimony. On October 30, 1956, Christifulli had made an application to Supreme for payment in the amount of $3,331.38. No allocation was made between work under contract and- extras. Supreme made the- payment. On November 26th, there was another application for payment in the total amount of $4,643.25,. again with no allocation and again paid by Supreme. On December 28, 1956, there was another application for payment in the total amount of $4,359.06, without any allocation, and this amount was paid by Mutual Savings & Loan Association on January 24, 1957, [82]*82after the statement by Christifulli that they were 90 per cent finished with the original contract and the extras. On February 4, 1957, Christifulli submitted an application for payment listing the balance of the contract at $1,666.37, listing labor and materials on extras as $5,870.18, and a total due of $7,536.55. The same amount of extras was listed on a statement dated February 22d, although in that statement the $3,000 payment was claimed as a payment on the total account. As late as September 26, 1957, Christifulli, over Darby’s signature, rendered a statement to Olympic claiming the contract price of $14,000, extras in the amount of $8,561.08, giving credit for payment of $16,333.69, and leaving a balance due Christifulli of $6,227.39. This was some time after very different figures indicating a much larger claim had been used in the cross complaint filed in' this action.

Part of the total bill was computed by a formula of $15 for each electrical outlet. Christifulli introduced a statement claiming a sum of money for approximately 550 extra outlets, but when Darby attempted to testify as to the additional outlets placed in all parts of the building, the court found he only testified to 256. Darby estimated the number of all outlets in the building in excess of 1,000, but the total number of all outlets shown by the city permits was 548.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fullerton Lumber Co. v. Korth
155 N.W.2d 662 (Wisconsin Supreme Court, 1968)
Supreme Construction Co. v. Olympic Recreation, Inc.
7 Wis. 2d 74 (Wisconsin Supreme Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
7 Wis. 2d 74, Counsel Stack Legal Research, https://law.counselstack.com/opinion/supreme-construction-co-v-olympic-recreation-inc-wis-1959.