Suppa Bros. v. Structures, Inc.

533 A.2d 901, 12 Conn. App. 675, 1987 Conn. App. LEXIS 1144
CourtConnecticut Appellate Court
DecidedDecember 1, 1987
Docket4994
StatusPublished
Cited by5 cases

This text of 533 A.2d 901 (Suppa Bros. v. Structures, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Suppa Bros. v. Structures, Inc., 533 A.2d 901, 12 Conn. App. 675, 1987 Conn. App. LEXIS 1144 (Colo. Ct. App. 1987).

Opinion

O’Connell, J.

The plaintiff appeals from the judgment rendered, in a contract dispute, for the defendant on the defendant’s counterclaim. We find no error.

[676]*676The plaintiff brought this action alleging breach of contract, monies owed under the doctrine of quantum meruit and wrongful waiver of a mechanics’ lien. The contract in question concerned excavation work to be performed by the plaintiff at the defendant developer’s residential project in Cheshire (the Cheshire contract). The Cheshire contract was signed by the parties on or about August 3, 1983.

The defendant counterclaimed, alleging, inter alia, that the plaintiff breached a February 4,1984 contract for road and drainage work on a separate project in East Haven (the East Haven contract), and that it was owed damages resulting from that breach.

The attorney trial referee who heard the matter awarded the plaintiff $10,101.09 damages on the complaint, and awarded the defendant $71,998.50 in damages on its counterclaim. The trial court rendered judgment in accordance with the referee’s findings. On appeal, the plaintiff alleges that the trial court erred (1) in finding that the “monetary disagreements” of the parties were insufficient justification for the plaintiff’s breach of the East Haven contract, and (2) in basing its assessment of the defendant’s damages upon estimated costs rather than actual expenses. Additionally, the plaintiff contended at oral argument that the issue of justification for repudiation of the East Haven contract was an issue of law, not fact, and accordingly was not subject to the rules of practice concerning attorney trial referee reports. We disagree and find no error on any of the three claims.

I

Addressing first the plaintiff’s claim made at oral argument, we note that the referee found that the plaintiff’s “monetary disagreements [with the defendant] on the Cheshire project . . . [do] not appear to be sufficient grounds for repudiating the [East Haven] con[677]*677tract.” Accordingly, the referee then found that the East Haven contract “was breached by the plaintiff without cause.” It is a well settled principle of law that a renunciation or repudiation of a contract prior to performance allows the adverse party to treat the contract as breached and gives that party the right to institute an action for damages. 17 Am. Jur. 2d, Contracts § 449 (and cases cited therein). In such situations, “[t]he decisive question [is] whether the [plaintiff] had abandoned, and consequently breached, the contract. This [is] a question of fact.” M. Shapiro & Son Construction Co. v. Battaglia, 138 Conn. 238, 244, 83 A.2d 204 (1951). It is also beyond dispute that the role of the attorney trial referee is that of factfinder. Seal Audio, Inc. v. Bozak, Inc., 199 Conn. 496, 507-508, 508 A.2d 415 (1986). The above-quoted portions of the referee’s report set forth the referee’s conclusions regarding a question of fact, not law. By accepting the referee’s report and rendering judgment in accordance with his recommendation, the trial court accepted the referee’s conclusions of fact. Because the defendant “ ‘filed no [timely] exceptions to the acceptance of the report by the court in accordance with Practice Book [§ 440] . . . the conclusions must stand.’ ” Seal Audio, Inc. v. Bozak, Inc., supra, 518, quoting Jensen’s, Inc. v. Killingworth, 152 Conn. 237, 243, 206 A.2d 114 (1964).1 The plaintiff cannot circumvent procedural [678]*678time prerequisites merely by framing a factual dispute as an issue of law.2

II

Concerning the two claims addressed in the plaintiffs brief, we once again note that our review of a matter heard by an attorney trial referee is strictly limited when, as here, the plaintiff failed to file timely exceptions, objections or motions to correct the referee’s report. Such failure precludes an attack upon the subordinate factual findings contained in the report or the conclusions based thereon. See generally Seal Audio, Inc. v. Bozak, Inc., supra, 518; J. M. Rosa Construction Co. v. New Haven Redevelopment Agency, 9 Conn. App. 481, 485, 519 A.2d 1227 (1987); Kowalsky Properties, Inc. v. Sherwin-Williams Co., 7 Conn. App. 136, 140, 508 A.2d 43 (1986). In this case, the referee filed his report on January 21, 1986. On January 31, 1986, the plaintiff filed a motion for extension of time to file an objection to the referee’s report. This motion was denied by the trial court on February 4, 1986. On February 7, 1986, the plaintiff filed a motion to correct the report, which filing was three days beyond the two week period mandated by Practice Book § 438.3 On February 19, 1986, the plaintiff filed an objection to the acceptance of the referee’s report, which likewise was untimely.

Because we conclude that all claims of error address matters of fact, and because the plaintiff did not timely [679]*679file proper motions attacking the referee’s findings, we will not review further the acceptance of the report by the trial court. “ ‘A litigant cannot wholly ignore established procedures for the protection of its rights, as this [plaintiff] has done, and hope to receive on appeal the same treatment accorded to those who follow the rules of practice.’ ” Ross v. Renzulli, 9 Conn. App. 87, 90, 516 A.2d 149 (1986), quoting Seal Audio, Inc. v. Bozak, Inc., supra. We therefore decline to review further the judgment of the trial court.

There is no error.

In this opinion the ther judges concurred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson-Goodyer v. O'Neil Mech., No. Cv 97 040 0865s (Nov. 16, 1999)
1999 Conn. Super. Ct. 15283 (Connecticut Superior Court, 1999)
Abdelsayed v. Drougas, No. Cv95-0323650 S (Aug. 9, 1996)
1996 Conn. Super. Ct. 5256-BBBB (Connecticut Superior Court, 1996)
MacEy Noyes Association v. Remd Intl., No. Cv94 031 67 43 (Jul. 30, 1996)
1996 Conn. Super. Ct. 5114-II (Connecticut Superior Court, 1996)
Quality Elec. Co. v. Suffolk Constr., No. Cv92 0518000s (Jun. 30, 1993)
1993 Conn. Super. Ct. 6393 (Connecticut Superior Court, 1993)
Rostenberg-Doern Co. v. Weiner
552 A.2d 827 (Connecticut Appellate Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
533 A.2d 901, 12 Conn. App. 675, 1987 Conn. App. LEXIS 1144, Counsel Stack Legal Research, https://law.counselstack.com/opinion/suppa-bros-v-structures-inc-connappct-1987.