Superior Trailer Mfg. Corp. v. J. W. Scatterday, Inc.

185 N.E.2d 417, 243 Ind. 473, 1962 Ind. LEXIS 187
CourtIndiana Supreme Court
DecidedOctober 4, 1962
Docket30,028
StatusPublished
Cited by6 cases

This text of 185 N.E.2d 417 (Superior Trailer Mfg. Corp. v. J. W. Scatterday, Inc.) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Superior Trailer Mfg. Corp. v. J. W. Scatterday, Inc., 185 N.E.2d 417, 243 Ind. 473, 1962 Ind. LEXIS 187 (Ind. 1962).

Opinion

Achor, J.

— Heretofore this court by a written opinion in Superior Trailer Mfg. Corp. v. J. W. *474 Scatterday, Inc. (1961), 241 Ind. 459, 462, 169 N. E. 2d 721, 722-723, made a general statement regarding the factual circumstances in this case and determined that:

“[U]nder the issues as formed by the pleadings and the evidence it was the duty of the trial court to make a specific finding upon the issue of completion of the contract, upon which finding the court could conclude, as a matter of law, that an indebtedness did or did not exist under the contract.
“Therefore, under Rule 2-30, judgment herein is remanded back to the trial court for 'findings on the material issues of fact’ as to the completion of the contract which is the subject of this- litigation,- and for further proceedings consistent with this opinion.”

Pursuant to the mandate of this court, the trial court thereafter entered an additional finding of fact and renderéd judgment against the appellant upon all the findings of fact and conclusions of law thus stated. The additional finding of fact was stated as follows:

“[A]nd the Court now being duly advised in the premises now, pursuant to the order and direction of the Supreme Court of Indiana in cause number 30028 in said Court ... makes and enters its additional finding of fact: No. 58. That J. W. Scatteray, Inc. immediately after the execution of the . contract between it and Superior Trailer Mfg. Corp. on September 21, 1951 and the amendments thereto, entered upon the performance of said contract in accordance with the plans, specifications and modifications and that said J. W. Scatterday, Inc. substantially performed said contract in accordance with the plans, specifications and supplements thereto.”

Thus, the trial court having entered a “finding” “that said J. W. Scatterday, Inc. substantially performed said contract in accordance with the plans, specifications and supplements thereto,” the issue now pre *475 sented for our determination as to whether such contract was in fact “substantially performed [with respect to its completion]” in a skillful and workmanlike manner, within the purview of the evidence and the finding of fact otherwise stated in the case.

As stated by the trial court in its Finding No. 14:

“14. That at and before the time the contracts above referred to were entered into and by said contracts the defendant, J. W. Scatterday, Inc., represented to the plaintiff that its president, John W. Scatterday, was a registered professional engineer and qualified builder and that said defendant was, through its president and employees, qualified to complete the building and do all of the construction work contemplated by said contracts and as designed by said John W. Scatterday, in a skillful, careful and workmanlike manner, and by its contract the defendant, J. W. Scatterday, Inc., agreed to furnish all the material contemplated and to do and perform all the work contemplated by its contract, plans and specifications in a first-class workmanlike manner.” [Emphasis added.]

In this case the dominant issue related to the performance and responsibility of appellee Scatter-day, with respect to the collapse of two major sections of the brick wall of appellant’s original building, the material facts bearing upon this issue are as follows:

J. W. Scatterday, who was an experienced engineer and contractor, was familiar with the hazardous condition of the existing wall resulting from its deterioration and lack of lateral support. On Wednesday, December 5, 1951, Scatterday, who had previously submitted plans and specifications for the construction, entered into a contract to build a new and independent wall, immediately adjacent to and parallel with the original wall, the footings of which were expected to provide needed underpinning of the *476 original wall. 1 On. Friday, December 7, immediately after entering into said contract, appellee Scatterday put in two 20 foot sections of footings, so designed as to serve as an underpinning for the existing-wall, and a footing for the new wall. These footings were constructed by cutting away to the sheer perpendicular lines of the wall of the original building, to and including the digging of a trench to a depth of approximately eight inches below the grade for the spur track. Thus, the exposed earth formed the interior wall of the footing, and timbers about two feet in height were constructed to form .the exterior wall. Into these forms concrete was poured. This method of construction proved successful on Friday, but was halted because of rain on' Saturday and Sunday.

On Monday morning, December 8, a similar form was . dug and constructed at the báse of á three-story section of the building. At. this time the earth was very muddy and water stood in a trench. On this occasion the building settled and the wall collapsed where this work was done. This happened while appellee was waiting for the cement to be delivéred with which to fill the form. Thereafter, on the same day, appellee undertook to construct a second and similar 20 foot section of footing under a different part of the building, which part also collapsed before *477 thé form was completed and filled with concrete. Thereupon appellee Scatterday terminated his activity on the job until after appellant had reconstructed the collapsed portions of the wall and placed underpinning under the remaining portions of the wall. Because of this unfortunate experience additional cost was allegedly incurred in the approximate amount of $90,000. This is the primary subject of controversy in the case.

The appellant asked for special findings of fact and conclusions of law. Several findings of fact stated by the court demonstrate that its decision was based upon a clearly erroneous conception of both the law and the facts as they related to the important issue as to whether or not appellee Scatterday was negligent or lacking in skill in the manner in which he attempted to construct the footings at the base of the sections of the wall which collapsed.

In Finding No. 25 the court stated:

“25. That prior to the time that said excavation was made for the spur track, proposals were made to underpin the existing walls of the Tucker Dorsey buildings by the defendant, J. W. Scatter-day, Inc., and rejected by the plaintiff.” [Emphasis added.]

The proposal to which this finding relates was made in conjunction with a proposal to build a new four inch cement block, wall as a veneer to the old wall. The proposal was superseded by a new proposal made by Scatterday. It was not “rejected by the plaintiff [appellant].”

In Finding No. 31 the court stated:

“31. That the plaintiff knew that the collapse of said walls was imminent and the change of the contract, plans and specifications of December 5th were made by the plaintiff and agreed to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ethyl Corp. v. Forcum-Lannom Associates, Inc.
433 N.E.2d 1214 (Indiana Court of Appeals, 1982)
Phillips v. GREEN STREET CORP.
237 N.E.2d 590 (Indiana Court of Appeals, 1968)
Department of Insurance v. Hendrickson
196 N.E.2d 574 (Indiana Supreme Court, 1964)
MONTGOMERY, ETC. v. Board of Zoning Appeals
193 N.E.2d 142 (Indiana Court of Appeals, 1963)
Cassidy v. INDIANA STATE BD. OF REGIS., ETC.
191 N.E.2d 492 (Indiana Supreme Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
185 N.E.2d 417, 243 Ind. 473, 1962 Ind. LEXIS 187, Counsel Stack Legal Research, https://law.counselstack.com/opinion/superior-trailer-mfg-corp-v-j-w-scatterday-inc-ind-1962.