MacKnight Flintic Stone Co. v. Mayor

31 A.D. 232, 52 N.Y.S. 747
Appellate Division of the Supreme Court of the State of New York·Decided July 1, 1898·Published·Cited by 1 cases

Opinion

Patterson, J.:

The learned counsel for the appellant insists that by the amended pleadings new issues were raised in this case, and that in consequence thereof different questions are presented oh this appeal from those which were decided by this court on the two former appeals. (13 App. Div. 232; 21 id. 472.) The complaint before the court on the first and second appeals contained an allegation of strict performance in accordance with the terms and conditions of the contract between the plaintiff and the defendant, but the amended complaint contains an allegation of substantial performance by the plaintiff of all the conditions of the contract and the completion of the work under the contract in accordance with the plans and specifications. The original complaint contained also an allegation that [233] when, the work under the contract was fully performed, a certificate was demanded from the superintendent appointed under the contract. The amended complaint, in addition to the last allegation, contains the averment that, after the performance of the work, the same was accepted and actually taken possession of and was used by and remains in the absolute possession and use of the defendant. Upon the last trial the plaintiff asked to go to the jury on the question of substantial performance, on the question of the waiver of the conditions of the contract, on the question of waiver by acceptance and use of the work by the city, and upon all the other facts of the cas'e. That motion was denied, and the trial court dismissed the complaint.

Upon the question of waiver by acceptance of the work by the city, we find no substantial difference between the evidence as it was given on the last and as it appeared on the previous trials. We held on the first appeal that there was no waiver by the city of the conditions of the contract nor of the defects in performance, and that the acts of the commissioner of public works were not tantamount to an actual and voluntary acceptance of the work as a fulfillment of the contract, carrying with it an implied promise to pay for it. It was held on the first appeal that there was no waiver by taking possession of the work, and we do not see that the question is now presented under the proofs in any such way as to call for a different ruling. It is asserted that the claim as now made by the plaintiff is simply that of a waiver of full performance, to the extent of precluding the defendant from insisting that there was not a substantial performance, and there is not such a waiver as would prevent the defendant from recovering any damages suffered by reason of a failure fully to perform. Or, in other words, that the plaintiff would be entitled to recover upon proof of substantial performance, subject to recoupment of damages proven to be the result of nonperformance. There are cases in which on contracts, as, for instance, the sale and delivery of goods, a waiver of full performance may be shown and a deduction allowed a defendant for a plaintiff’s failure to perform the whole contract, and such are Brady v. Cassidy (145 N. Y. 171); Dalzell v. Fahys Watch Co. (138 id. 285); Avery v. Willson (81 id. 341); but the amended answer in this case sets up a [234] defense to each and every cause of action set forth in the complaint of a complete failure of the plaintiff to perform provisions of the contract. The use of the building by the city, under the circumstances of the case, with the work as performed by the plaintiff in and upon it, cannot be regarded in law as a waiver of performance. That work was done on the city’s property. It had no alternative but to use the work or abandon the use of its property. This is a case of work done in a building standing on the defendant’s land. The contractor failed to complete that work in the manner required by the contract, and it has been held under such circumstances that where an owner resumes possession and enjoys the fruits of the labor of a contractor, it is not an acceptance such as alone would imply a promise to pay under the contract; “ for the possession of the land necessarily involves possession of the buildings in their existing state, and the owner has no option of rejecting them.” (Elliott v. Caldwell, 43 Minn. 357, citing Leake Cont. 68; Munro v. Butt, 8 El. & B. 738.)

We have only then remaining for consideration the question whether any real change is made in the case, by reason of the abandonment of the allegation of the complaint of strict performance and the substitution of one of substantial performance. We think there is not, and for the reason that the proof does not show substantial performance. What is meant by the substantial performance of such a contract as that involved here is fully settled in the State of New York. In Woodward v. Fuller (80 N. Y. 312) it is said that literal or exact performance of a contract to build is no longer required. “ It is now the rule that where a builder has in good faith intended to comply with the contract, and has substantially complied with it, although there may be slight defects 'caused by inadvertence or unintentional omissions, he may recover the contract price.” And it is further said that the defects must not run through the whole work, nor ~be so essential as that the object of the parties to have the specific cmnount of work done in a particular way is not accomplished. The language of the court as quoted in the case last cited is but a repetition of what was said by Church, Ch. <7., in Phillip v. Gallant (62 N. Y. 264). The identical expressions first quoted are repeated in Nolan v. Whitney (68 N. Y. 650), which was also a case of a contract to do work in the erection [235] of buildings. In the case of Miller v. Benjamin (142 N. Y. 613), which was a contract for the sale and delivery of goods, it is said: The right of a party to enforce a contract will not be forfeited or lost by reason of technical, inadvertent or unimportant omissions or defects. * "* * There must be no willful or intentional departure, and the defects of performance must not pervade the whole, or be so essential as substantially to defeat the object which the parties intended to accomplish.” It is also said in that case, as in the others, that whether in any case such defects or omissions are substantial, or merely unimportant mistakes that have been or may be corrected, is generally a question of fact.

Free access — add to your briefcase to read the full text and ask questions with AI

MacKnight Flintic Stone Co. v. Mayor, 31 A.D. 232, 52 N.Y.S. 747 (N.Y. Ct. App. 1898).

31 A.D. 232 (MacKnight Flintic Stone Co. v. Mayor) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Superior Trailer Mfg. Corp. v. J. W. Scatterday, Inc.
185 N.E.2d 417 (Indiana Supreme Court, 1962)