Superior Mechanical Plumbing & Heating, Inc. v. Insurance of the West

965 N.E.2d 890, 81 Mass. App. Ct. 584, 2012 WL 1193887, 2012 Mass. App. LEXIS 171
CourtMassachusetts Appeals Court
DecidedApril 12, 2012
DocketNo. 10-P-2255
StatusPublished
Cited by3 cases

This text of 965 N.E.2d 890 (Superior Mechanical Plumbing & Heating, Inc. v. Insurance of the West) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Superior Mechanical Plumbing & Heating, Inc. v. Insurance of the West, 965 N.E.2d 890, 81 Mass. App. Ct. 584, 2012 WL 1193887, 2012 Mass. App. LEXIS 171 (Mass. Ct. App. 2012).

Opinion

Graham, J.

The defendant, Insurance Company of the West (Insurance Company), surety for L.A. Fitness International, LLC (L.A. Fitness), appeals from summary judgment in favor of the plaintiff, Superior Mechanical Plumbing and Heating, Inc. (Superior), on Superior’s claim to enforce a mechanic’s lien pursuant to G. L. c. 254, § 4. Superior performed plumbing work under a subcontract with PinnCon LLC (PinnCon), the general contractor for the construction of an L.A. Fitness sports facility in Saugus (project). The issue on appeal is whether amounts were due or to become due to PinnCon on the date [585]*585L.A. Fitness received notice of Superior’s lien. Based upon the terms of the general contract and the undisputed facts, PinnCon’s failure to provide proof to L.A. Fitness that it had paid its subcontractors, a condition precedent to subsequent payments under the general contract, we conclude that no further payments were due or to become due, and the grant of summary judgment was improper. We reverse.

Facts. The undisputed facts are taken from the summary judgment record. On November 29, 2007, L.A. Fitness and PinnCon entered into a written contract (general contract), whereby PinnCon would serve as the general contractor for the project. The general contract consisted of the American Institute of Architects’ abbreviated standard form of agreement,1 along with exhibits. Attached as exhibit C was a rider, the terms of which controlled in the event of a conflict between the rider and the abbreviated form of agreement.2 Relevant for our purposes, the rider included provisions requiring that PinnCon pay its subcontractors promptly upon receipt of payments from L.A. Fitness, and that, as a condition precedent to further payments, PinnCon provide proof that it paid its construction obligations from the previous payment from L.A. Fitness. On December 4, 2007, PinnCon entered into a written subcontract with Superior.

Over the next few months, PinnCon submitted four applications for payment to L.A. Fitness. L.A. Fitness approved PinnCon’s first application for payment, and made a payment to PinnCon in January, 2008, in the amount of $173,025. L.A. Fitness also approved PinnCon’s second application for payment, and made a second payment to PinnCon on March 4, 2008, in the amount of $690,996.

On March 25, 2008, L.A. Fitness learned that PinnCon had absconded with the March 4, 2008, payment of $690,996, had paid none of its subcontractors from those funds, and was closing [586]*586its business. By letter dated March 28, 2008, L.A. Fitness terminated the general contract due to PinnCon’s material breaches, including, among others, its failure to pay its subcontractors. L.A. Fitness made no further payments to PinnCon.

Prior to PinnCon’s termination, Superior performed subcontract work valued at $105,740. Superior submitted four requisitions for payment to PinnCon for work performed through March 18, 2008, but PinnCon never paid them.3 On March 20, 2008, Superior recorded a notice of contract pursuant to G. L. c. 254, § 4, in the Essex South District registry of deeds and in the Essex South Registry District of the Land Court. L.A. Fitness received actual notice of the lien filing on March 24, 2008.

After PinnCon’s termination, L.A. Fitness hired Konover Construction (Konover) as general contractor to complete the project. Personnel from L.A. Fitness and Konover met with the project subcontractors and asked that they sign agreements to complete their work. In May and June, 2008, L.A. Fitness paid the subcontractors for work submitted in PinnCon’s third and fourth applications for payment, totaling approximately $1.36 million. On May 29, 2009, Superior entered into a ratification agreement with Konover, providing that Superior would complete its subcontract and would also receive $50,166, representing payment for its third and fourth requisitions to PinnCon, plus retainage. Superior was not paid for its first and second requisitions, totaling $55,574, but preserved its rights to pursue payment in its ratification agreement with Konover. On June 25, 2008, L.A. Fitness recorded a bond, naming Insurance Company as surety, securing payment of Superior’s lien, as permitted under G. L. c. 254, § 14.4

The project was eventually completed. L.A. Fitness calculated [587]*587that the cost to complete exceeded the original general contract price by $237,140.5

Superior commenced this action in Superior Court against PinnCon for breach of contract and recovery in quantum meruit, and against Insurance Company to enforce the lien. Final judgment was entered against PinnCon on March 30, 2009, pursuant to Mass.R.Civ.P. 54(b), 365 Mass. 820 (1974). Insurance Company moved for summary judgment, asserting that no funds were due or to become due from L.A. Fitness to PinnCon, because of PinnCon’s default on the general contract at the time L.A. Fitness received notice of Superior’s lien. Superior filed a cross motion for summary judgment, asserting that at the time L.A. Fitness was notified of the lien, money was still due to PinnCon for work performed under the general contract, regardless of PinnCon’s default. The Superior Court judge granted summary judgment for Superior, ruling that “PinnCon was owed monies by the contract owner, L.A. Fitness in at least enough of an [amount] to satisfy the plaintiff’s claim.” Insurance Company appealed.

Discussion. We review the grant of summary judgment de nova. See Miller v. Cotter, 448 Mass. 671, 676 (2007). General Laws c. 254, § 4, permits a subcontractor to file a notice of contract in the appropriate registry of deeds at any time after the execution of a written contract with the general contractor to perform labor or furnish materials. See BloomSouth Flooring Corp. v. Boys’ & Girls’ Club of Taunton Inc., 440 Mass. 618, 622 (2003) (subcontractor “could have protected itself from general contractor’s default by filing its notice of subcontract prior to starting [the] work”). Section 4 provides, in relevant part, that, upon filing and giving actual notice to the property owner, the subcontractor shall have a lien on the property, but that “[s]uch lien shall not exceed the amount due or to become due under the original contract as of the date notice of the filing of the subcontract is given by the subcontractor to the owner.”6 [588]*588G. L. c. 254, § 4, as amended through St. 1996, c. 364, § 5.7 The statute is strictly construed against the party claiming the lien, and that includes establishing that money is due or to become due. National Lumber Co. v. Inman, 77 Mass. App. Ct. 916, 918 (2010).

It is undisputed that L.A. Fitness received actual notice of Superior’s filing of the notice of contract on March 24, 2008. Superior argues that since the date of PinnCon’s formal termination was not until March 28, 2008, amounts were still due or to become due under the general contract when L.A. Fitness received notice of Superior’s lien on March 24, 2008. However, this court’s recent decision in Maverick Constr. Mgmt. Servs., Inc. v. Fidelity & Deposit Co. of Md., 80 Mass. App. Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bruno v. Alliance Rental Group, LLC
Massachusetts Appeals Court, 2023
United Rentals (North America), Inc. v. TGBD, LLC
32 Mass. L. Rptr. 60 (Massachusetts Superior Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
965 N.E.2d 890, 81 Mass. App. Ct. 584, 2012 WL 1193887, 2012 Mass. App. LEXIS 171, Counsel Stack Legal Research, https://law.counselstack.com/opinion/superior-mechanical-plumbing-heating-inc-v-insurance-of-the-west-massappct-2012.