Supergear Drive Corp. v. Hollister-Whitney Co.

64 N.E.2d 672, 327 Ill. App. 414, 1945 Ill. App. LEXIS 429
CourtAppellate Court of Illinois
DecidedOctober 23, 1945
DocketGen. No. 9,464
StatusPublished
Cited by6 cases

This text of 64 N.E.2d 672 (Supergear Drive Corp. v. Hollister-Whitney Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Supergear Drive Corp. v. Hollister-Whitney Co., 64 N.E.2d 672, 327 Ill. App. 414, 1945 Ill. App. LEXIS 429 (Ill. Ct. App. 1945).

Opinion

Mr. Presiding Justice Hayes

delivered the opinion of the court.

The plaintiff, Supergear Drive Corporation, brought action against the defendant, Hollister-Whitney Company, a corporation, in the circuit court of Adams county to recover damages for breach of contract, upon the defendant’s failure to machine and deliver certain forgings. The case was tried by the court without a jury, and at the conclusion of plaintiff’s evidence the court entered a judgment for the defendant from which this appeal is taken.

The complaint alleges; that the plaintiff and the defendant entered into a contract whereby the defendant agreed to machine 3,614 parts at the price of $1.68% each; that the defendant completed 100 of the parts and delivered them and was paid by the plaintiff at the rate of $1.68%; that then the defendant informed the plaintiff that it would have to have $3.90 per part instead of $1.68%, which increase the plaintiff refused to pay, and thereupon the defendant refused to deliver to the plaintiff the balance of the machine parts. It further alleges that the defendant had knowledge that plaintiff had contracted to deliver said parts to a third party for $2.92 per part, and that plaintiff suffered damages in the sum of $4,339.29.

Defendant in its amended answer admits the making of the contract and denies the other allegations of the complaint.

It appears from the evidence that the Solar Aircraft Company of San Diego, California contracted with the plaintiff for the machining of the forgings in question, at the price of $2.92. The forgings were to be furnished in the first instance by the Aircraft Company. The plaintiff in turn subcontracted the work to the defendant who had a plant located at Quincy, Illinois at the agreed price of $1.68%; that the defendant had knowledge of the contract existing between the plaintiff and the Aircraft Company and that on July 20,1943, defendant wrote a letter to the plaintiff in which it informed the plaintiff that it would not complete the machining of the forgings unless the plaintiff would pay $3.90 instead of the contract price of $1.68% for each part. It further appears that several weeks had been taken in special tooling for the job and that the tools were in the possession of the defendant; that the plaintiff on getting the letter of July 20 from the defendant informed the Aircraft Company of defendant’s refusal to perform without an increase in price; that about the same time the defendant got in communication with the Aircraft Company for a contract of its own on this work; that on July 27 the defendant offered the Aircraft Company a price of $3.90 for machining the forgings and requested a confirming order after cancellation with the Supergear Drive Corporation. It then appears 'that the Aircraft Company immediately cancelled the contract with the plaintiff and made a contract direct with the defendant.

The question involved in this appeal is, “Did the plaintiff at the close of plaintiff’s evidence drawing all the inferences most favorable to the plaintiff establish a prima facie case?” The question of law presented on a motion to direct a verdict is whether when all the evidence is considered together with all reasonable inferences drawn from it in its most favorable aspect to the party against whom the motion is directed there is a total failure to prove one or more necessary elements of the case? Foreman-State Trust & Savings Bank v. Demeter, 347 Ill. 72; Moudy v. New York, C. S St. L. R. Co., 317 Ill. App. 154. It is also the law that where there is such uncertainty arising from the evidence that fair-minded men may honestly draw different conclusions that it then ceases to be a question of law, but one of fact to be settled by the weighing of the evidence either by a jury or by the court. Plodzien v. Segool, 314 Ill. App. 40; Turner v. Cummings, 319 Ill. App. 225.

It was incumbent upon the plaintiff in establishing a prima facie case to prove the existence of the contract, the breach of the same, and the resulting damages.

From the documentary evidence in the record, also by the admission in the pleadings the existence of the contract is established.

Defendant’s letter, under date, of July 20, states: “we must have $3.90 per piece or we see no alternative than to stop the work on this order . . . we simply cannot make them at the price we originally quoted. ’ ’ This language can hardly be construed other than a breach, particularly when the defendant makes a direct contract with the Aircraft Company for the same work at $3.90 per piece rather than $1.68% as the original contract provided. The. evidence further shows that Mr. Hollister, one of the executives of the defendant, stated to the plaintiff over the telephone that he must have a price of $3.90, and if he did not get that price he would not turn a stick of work on the job.

The other element remaining in plaintiff’s prima facie case is damages, and it appears from the evidence that the contract provided for the machining to be done at $1.68% and the plaintiff was getting $2.92 for each part. It definitely appears that by breach of the contract plaintiff lost $1.23% per part. These parts were made for a specific purpose and could not have a market value.

Where it was known at the time the contract was entered into that the goods were being bought for resale in a particular market, the buyer, on failure of the seller to deliver, may recover the expected profit. Carpenter v. First Nat. Bank, 119 Ill. 352; Lapp v. Illinois Watch Co., 104 Ill. App. 255; Meyer, Hess & Co. v. Way, 187 Ill. App. 67; Black Diamond Fuel Co. v. Illinois Fuel and Phosphate Co., 219 Ill. App. 150. In Carpenter v. First Nat. Bank, supra, it is stated: “The general rule is, that the purchaser is entitled to recover the difference between the contract price and the value of the article in the market at the time and place of delivery. (Messmore v. Lead Co., 40 N. Y. 427.) This rule, however, is changed, where the vendor knows, that the purchaser has an existing contract for a resale at an advanced price, and that the purchase is made to fulfill such contract, and the vendor agrees to supply the article to enable him to fulfill the same, because those profits, which would accrue to the purchaser upon fulfilling the contract of resale, may justly be said to have entered into the contemplation of the parties in making the contract.”

It appears the damages shown are in no way speculative, contingent or uncertain. They can be determined with definiteness and certainty. The evidence in the case shows the plaintiff was in no position to mitigate the damages for the reason that immediately after the breach of the contract by the defendant, the Aircraft Company cancelled plaintiff’s contract with them; that the special tools were in the possession of the defendant who refused to surrender them and that it would take eight weeks to make another set so that the plaintiff had no opportunity to go elsewhere to have the work done in view of the length of time between the refusal of the defendant to perform and the cancellation of its contract by the Solar Aircraft Company.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brewer v. Custom Builders Corp.
356 N.E.2d 565 (Appellate Court of Illinois, 1976)
Edward Electric Co. v. Metropolitan Sanitary District
306 N.E.2d 733 (Appellate Court of Illinois, 1973)
Watson Lumber Co. v. Guennewig
226 N.E.2d 270 (Appellate Court of Illinois, 1967)
Clark v. Compania Ganadera De Cananea, S. A.
387 P.2d 235 (Arizona Supreme Court, 1963)
Jones v. Furlong, Admx.
97 N.E.2d 369 (Indiana Court of Appeals, 1951)
Hubble v. Brown
84 N.E.2d 891 (Indiana Supreme Court, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
64 N.E.2d 672, 327 Ill. App. 414, 1945 Ill. App. LEXIS 429, Counsel Stack Legal Research, https://law.counselstack.com/opinion/supergear-drive-corp-v-hollister-whitney-co-illappct-1945.